Hamilton County Facilities

TPC – Center Beam Repair (F053)

PM: Matt Butz, Matt Rigdon
12/14/21 – Hamilton County published a project list for 2022. Project to be complete by Fall of 2022.
02/24/22 – THP submitted a SOSS for review by the County.
03/11/22 – SOSS approved.
03/25/22 – THP completed a survey of the beam repair area.
04/28/22 – THP is developing documents.
05/17/22 – THP published review documents.
05/27/22 – County published review comments to DD documents.
06/30/22 – THP – Issue with Concrete repair around building electrical feeds determined. Repair needs in electrical feed area minor and can wait until electrical area needs service and come off line. THP documents ready. THP coordinating bid dates. Anticipates bidding in July.
07/11/22 – THP issued “For Bidding” submittal with drawings and project manual.
07/19/22 – THP hosted pre-bid meeting at HC Portune Center Lobby.
07/21/22 – THP issued Addendum #1.
07/22/22 – THP issued Addendum #2.
08/03/22 – Bids are due.
08/03/22 – Bids from LRT, Buckeye and ZSR were received. All base bid within budget.
08/18/22 – THP and LRT completed an initial bid review meeting.
08/22/22 – THP issued a follow up sketch for field clarification.
08/24/22 – LRT reviewed sketch and bid, and provided an updated price to their bid.
09/01/22 – Site visit and developed a design change to accommodate existing MEP.
09/16/22 – THP issued new “For Bidding” submittal with design change.
09/27/22 – THP hosted pre-bid meeting at HC Portune Center Lobby. Bids are due 10/7/22.
10/06/22 – THP issued Addendum #1 with new Bid Opening Date for October 13.
10/13/22 – Bids are due.
10/13/22 – Bids from ZSR, LRT, Buckeye, and SSRG were received.
10/14/22 – THP and ZSR completed an initial bid review meeting. THP sent a follow up letter to the County recommending they proceed with ZSR for the based bid and all four alternates.
12/12/22 – ZSR was approved contract and corresponding PO. ZSR has signed and returned COI. Kick-Off meeting sometime after the first of the year. Anticipate work in February 2023 depending on background checks.
01/12/23 – ZSR has begun submittal process.
01/18/23 – HC approved contract and corresponding PO. ZSR has yet to complete background check process. Once completed, pre-construction meeting will be held the following week. Anticipated start of work in February 2023.
01/26/23 – HC approved contract and corresponding PO. ZSR has yet to complete background check process. Once completed, pre-construction meeting will be held the following week. Anticipated start of work in February 2023.
02/14/23 – Preconstruction Meeting
02/23/23 – All submittals are in. Anticipating work to start February 27.
03/23/23 – Drilled holes for rebar on 3/20/23. Permit completed by end of this week. Anticipating deck supporting steel to be installed week of 3/27. Special inspections to be completed following the steel installation.
04/20/23 – On-site visit with Hamilton County to observe completed work. No comments on work from Hamilton County. THP to send close out report.
07/26/23 – Bulletin being prepared and to be sent July 31.
09/28/23 – THP forwarded pricing from ZSR for the beam repair. County coordinating possible repair of beam with electricians.
10/19/23 – County moving forward with electrical and beam repair. County requested ZSR beam repair proposal to develop an AIA Change Order.
10/26/23 – County developing AIA Change order for ZSR.
01/12/24 – Change order for additional beam repair cancelled due to electrical conflicts.
01/31/24 – Project is in the process of closing out. Awaiting final close out docs.
02/28/24 – THP received project close out documents and is reviewing.
03/14/24 – THP received revised project close out documents and is reviewing.
04/25/24 – THP approved draft closeout package. ZSR to send hard copies and USB drive.
05/01/24 – ZSR revised their project close out documents and sent to County. Project is closed. No more updates.
08/29/24 – All final work closeout documents completed. Waiting on final pay application.
12/09/24 – THP reached out to Terracon to provide special inspector stamp for close out to Permit. Terracon to provide this week.
01/29/25 – THP Closedout Procedure – January 3 – City of Cincinnati is currently closing out the permit (Jeffery Hinkle).
03/26/25 – Project Archived.

Scroll to Top