12/14/22 – Hamilton County published a project list for 2022. City Inspection to be completed by June 30.
04/06/22 – THP Submitted SOSS for review by the County.
04/22/22 – County Approved the SOSS.
04/28/22- Rappelling anticipated first week of June. Report to be published in June.
6/30/22 – City Report due 7/1/2023. THP completed review of new cellular towers. THP to schedule rappelling late July. Report to be complete by end of August.
7/28/22 – THP schedule rappelling 9/7/22.
10/27/22 – THP completed field work. THP to publish reports and budget 11/10/22.
12/15/22 – THP issued draft report.