04/30/21 – SOSS Submitted to County
05/11/21 – Signed SOSS received.
06/23/21 – Meeting on site to review scope. Champlin finishes scope removed. Light fixture selection and photometrics to be done.
07/29/21 – Sconce selection is made. acoustical selection is not required. Researching main light fixtures.
08/11/21 – Provided cutsheets for suggested fixture replacements.
08/18/21 – County provided feedback on fixture selections.
10/27/21 – Draft Rendering/Photo provided to County. Fixture cuts provided to Thermaltech for photometric calculations.
12/14/21 – No Update.
01/26/22 – No Update.
02/24/22 – No Update.
03/31/22 – No Update.
04/28/22 – No Update.
05/26/22 – No Update. Ready to archive.