04/21/21 – Cannon created post from Bert Watts email for 2022 Project Request.
05/27/21 – Bert sent the preliminary list out to the partners for SOSS authoring. Kickoff meeting next Tuesday with TEI, THP, and Champlin.
06/11/21 – Started research on 230 MEP upgrades including new above grade boiler and chiller room.
06/22/21 – Met at Comm Center to discuss project scopes for repurposing and academy rework.
06/25/21 – User meetings held to discuss the scope for most Champlin lead estimates.
07/28/21 – Work continues on the individual estimates. Some will be complete by July 31 and all will be complete by August 31. Cost, data and scope still coming in the CH controls, Mechanical Yard items which are the “biggies” for TTC. Champlin is making progress. Smaller estimates will be done by 7/31, the rest by 8/31.
08/20/21 – Champlin has provided almost all of the floor plans we need to complete estimates. TEI is currently putting together the cost and scope documents for the remaining estimates.
08/24/21 – Teleconference held on the 230 East 9th estimates between all partners to finalize the scope and estimating. TTC followed an update later that day with additional information after speaking with BW about the #2105 estimate.
08/26/21 – TEI – work continues and we plan on making the 8/31 completion date as discussed. Estimate and drawings are being uploaded daily.
10/28/21 – Project complete. A couple of final projects have been added and updated to the list.