TPC – Elevator Modernization 2020

PM: Matt Butz, Mike Barth
12/09/20 – TEI submits SOSS for approval from HCFD. Project to commence upon receipt of approved SOSS and PO.
01/26/21 – TEI receives signed SOSS and PO for project. Project kickoff to be scheduled with facilities and project work to commence.
02/23/21 – TEI requests times/days to meet and have a design kick-off with HCFD and Champlin. Meeting to be scheduled as soon as availability is coordinated.
03/24/21 – TEI meets with Champlin, HCFD and building manager. kick off the meeting. lobby beautification project to determine the interiors for the elevators #2,3,4, and 5. project in design phase.
03/25/21 – We talked about phasing of the elevator work and TTC shared the HVAC smoke evacuation procedures for this building as they may be related to the work being done on the AHU, elevators and fire alarm systems.
04/28/21 – Project in design process.
05/26/21 – Project in design process. Interiors shall be coordinated with the lobby beautification project.
06/23/21 – Project design continues.
07/28/21 – Project design continues, will be completed once interior finishes are finalized with lobby beautification project.
07/29/21 – Finishes are selected and the job can go forward with bidding. Keep bronze colors intact, Murphy is working on selections. We have enough information from equipment vendor to give to the Admin committee to move this forward. MB to setup a design meeting for next steps.
08/26/21 – No update
10/28/21 – MCB updating elevator package based on JC learnings, low voltage, coordination issues into the TPC work. County requested elevator cab rendering with new finishes to use with the Lobby Renovation. Keep and polish up the existing mailbox.
05/26/22 – Final review sent to county. To be determined if this will be bid as one project with the lobby renovation.
06/28/22 – Project HCFD review completed and received.   Drawing pack schedule coordinated with Champlin for the Lobby Beautification project.  Drawings to be sent to Purchasing on 07/05/22, available for bidding 07/07/22, with bids opening on 08/04/22.
07/27/22 – Project bidding.    Bid opening on 08/04/22.   Prebid completed and addendum #1 and #2 issued.
08/24/22 – Bids opened.   Graybach is apparent low bidder.  Project contracts drafted and sent to Prosecutors office.  Project to commence upon contract approval and PO.
10/26/22 – Bids opened.   Graybach is apparent low bidder.  Project contracts drafted and sent to Prosecutors office.  Project to commence upon contract approval and PO.
12/15/22 – Preconstruction meeting occurred on 12/14/22 with Graybach, HCFD, TEI.  Submittal are starting to arrive.  Graybach to submit a project schedule.
01/25/23 – Submittals are arriving slowly.  Electrical and Elevator submittals still pending.
03/29/23 – Submittals are arriving slowly.  Electrical and Elevator submittals still pending.
04/27/23 – Submittals reviewed and returned.   There are a couple of submittals (floor base, etc) that Champlin has requested samples and are still pending.  Anticipated start of construction is around the beginning of July ’23.  Graybach instructed to not make sure all materials are procured and received prior to starting actual construction so that there are no material delays once construction begins.  Basement door selected for mock-up of door finish.  mock up to be installed in next 2-3 weeks.
05/23/23 – Sill plate painted.  The door mock up materials arrived at site damaged.  Upon receipt of undamaged materials, the mock up will be installed for approval.
06/28/23 – TEI, Graybach, and HCFD meet on 06/28/23 to discuss schedule.  Door frame finish selection is critical path item.  Prior to taking an elevator off line, all materials for that elevator shall be on site.  Door frame wraps are a 4-6 week lead time item.
07/26/23 – Door frame selections have occurred.  Sent to Graybach and American Elevator.   Permit applications have been submitted.   Graybach anticipates starting on 1st elevator mid/late August.
08/24/23 – Graybach and subs are getting ready to start the project.
09/26/23 – Construction commencing on project.   first elevator to be taken from service early October.
10/26/23 – Elevator #3 (Right hand Side Passenger Elevator) has been taken out of service and machine is being disassembled.  There is a crane lift scheduled for 10/28/23 to remove Machine #3 from the penthouse, and lift the new equipment for #2 and #3.  A second lift will be scheduled once Cab #2 is complete and ready to work on cab #1 (freight).
12/06/23 – Work continues on Cab #3.  Old equipment is removed and new equipment is set in place in penthouse.   work in shaft, cab and landings ongoing.  new doors on multiple floors.
01/30/24 – First cab (cab #3), nearly complete.  Graybach tentatively scheduling inspections for approval on week of 02/05, and pending approved inspections, will turn cab #3 over for use by end of week.
02/28/24 – First CAB turned over and in use.  Working on second cab (Elev #2).
02/29/24 – Graybach sent email about air pressure in the lobby affecting for the doors, TTE advised them to check elevator door settings first before we change the HVAC and Smoke Evac fans in this building.
03/27/29 – Work continues on Elevator #2 (second passenger elevator).  Graybach indicates that they are “on schedule”.
04/24/24 – Elevator #2 inspection scheduled for 05/01/24.  Upon approved inspections and turn over – then #3 (the first one modernized) will be taken out of service for approx 1 week to address manufacturer’s recall on components.  Then both lobby elevators will be returned to service for the building occupants.
05/29/24 – Elevator #2 passes inspections and is placed back into service.  Elevator #3 recall work completed ahead of schedule and placed back in service.  Freight elevator taken out of service and is being worked on.  Anticipated completion late July/beginning of August.
06/26/24 – Project work progressing on the Freight. No schedule delays indicated by American Elevator or Graybach.
07/24/24 – Pretest of the FA connections on 07/24/24. Elevator inspection on 07/26/24. Turnover immediately after the approvals.
08/28/24 – Freight elevator complete, inspected and returned to service.
09/25/24 – Project complete pending closeouts from Graybach.
12/11/24 – Project complete pending closeouts from Graybach.
02/27/25 – Ready to Archive.