CH – Fire Pump Electrical Investigation

12/09/20 – Fire pump and fire alarm are having multiple trouble signals (excessive amount). HCFD had SA Comunale investigate, and also JCI/Simplex, both stated that their systems are working correctly. TEI suggests that a logging meter be installed to determine if it is an incoming voltage issue to the fire pump since the alarm is a single phase alarm. Meter on pump and more data to follow once results from the metering are reviewed.

01/26/21 – Meter data indicated voltage variations and excessive rapid voltage changes. TEI reported to facilities the voltage issues. Facilities requests SOSS for study to determine options for power quality correction. SOSS submitted and approved by facilities. Study in progress.

02/23/21 – HCFD sends TEI email stating that the existing phase loss monitor on the existing fire pump does not have adjustable ranges. Study to develop “clean” power supply to fire pump continues.

03/24/21 – TEi continues working on project, no new developments to report.

04/28/21 – TEI Finalizing owner review draft, will send to HCFD by 5/5/21 for initial review. TEI identifies issues from previous report also associated with the fire pump that possibly may required to be addressed if implementations occur.

05/26/21 – TEI submits draft for owner review. TEI and HCFD evaluating additional options. TEI suggests a temporary solution, and requests a quote from DK (since they did fire alarm project and are working on another project in building). Solution pending pricing from DK.

06/23/21 – The temporary solution was installed on the system, and it was reported to TEI that there are no longer the troubles on the FACP. TEI to finalize report to HCFD with results of solution included.