Hamilton County Facilities

TPC – Autotitle and BMV Combined Renovation

PM: Matt Butz, Mike Murphy
09/28/21 – SOSS received from County
10/27/21 – Champlin reached out to BMV contact to schedule programming meeting.
11/12/21 – Programming Meeting held with County, Champlin and BMV.
12/14/21 – Narrowed down potential layouts to two options. sending to BMV for comments.
12/22/21 – Met with BMV to finalize design. BMV to submit design to State. No response yet.
02/09/22 – Met with Greg Brush and Shawna Derencamp. Plan approved with small changes. SD and Estimate to be submitted by 3/4.
03/31/22 – SD plan and estimate submitted to County
04/28/22 – Estimate combined with Re-entry and sent to County.
05/26/22 – No update.
06/30/22 – No update.
08/25/22 – No Update.
09/29/22 – SOSS for DD-CA to be submitted in the near future.
10/27/22 – SOSS approved. DD meeting to be scheduled for week of 11/7.
12/15/22 – Final owner approval scheduled for 12/20
01/26/23 – Project will be posted for bid today
02/22/23 – Bid opening on 2/24.
03/29/23 – Graybach awarded the bid.
04/27/23 – RCF has met on site to provide furniture quote.
05/25/23 – Contracts finalized. Quote received from RCF. Kickoff meeting to be scheduled in the near future.
06/29/23 – Two separate kick off meetings will be held with each department. Design team to provide meeting options for next two weeks.
07/27/23 – Mid august start date. Meeting held with Autotitle. Meeting with BMV scheduled for next week. Plumbing and HVAC submittals have been received. TTE will send back this week.
08/31/23 – Construction began 8/14. Demo almost complete.
09/28/23 – Construction ongoing. Bulletin #1 issued for minor deduct work. Furniture for phase 1 ordered.
10/25/23 – Construction ongoing. Coordination between state and county data + telephone ongoing. State has been onsite to drop their data lines.
10/26/23 – The two large VAV boxes ductwork configuration has been modified to fit final wall construction installation. TTC met with NKYHC last week. Plumbing pilot holes reported to be filled, not verified by TTC yet. Drain pan in basement is being fabricated and should be here soon.
12/07/23 – Construction ongoing. phase 1 to be complete 12/22. Punchlist scheduled 12/21.
02/01/24 – Phase 1 is complete, Autotitle has moved into their temporary space. Toilets and restrooms are being installed now. City water tie-in next week. Triton begins demo of old Autotitle space and continues to work on Phase 2 work.
02/29/24 – Phase 2 began. Demo almost complete.
03/28/24 – Construction ongoing. Punchlist scheduled for 4/9.
04/25/24 – Punchlist items in progress. Autotitle moved into their space. BMV to be moved in two weeks after we make some additional changes in network infrastructure. Nick setting up meeting with Sonitrol to finalize new detail on how the new system is going to be monitored.
05/30/24 – Final punch items are in progress.
06/27/24 – Change order pricing outstanding.
08/29/24 – Pricing received. Waiting on materials for Triton to mobilize.
09/26/24 – Materials are in hand or arriving in near future. Triton to be on site this month.
10/31/24 – Triton back on site this week to finish last items.
12/12/24 – Triton has completed some punch items. Subs will be onsite to finish casework next week.
01/30/25 – Triton still has a couple items to complete on site.
02/27/25 – Punch work ongoing. Working on final connections to doors and get fire alarm tie-ins for FA system.
03/27/25 – Punch work still ongoing.
04/24/25 – Repair conducted on the auto operator. Fire tie in still outstanding.
05/29/25 – Access control have been on site a couple times. Problems are still not resolved.
06/26/25 – All items are not complete. Closeouts in progress.
08/28/25 – Closeout received. Ready to Archive.