09/20/21 – Kick-off meeting with County, Champlin, Thermaltech, THP, and Cushman & Wakefield.
09/27/21 – Building Tour.
09/30/21 – SOSS received from County
10/13/21 – Programming Meeting held with Comm Center, County, Cushman & Wakefield.
10/15/21 – Programming Meeting held with EMA, Champlin, County, and Cushman & Wakefield.
10/20/21 – Draft Program sent to User groups for comments.
12/03/21 – Signed SOSS received for SD.
12/13/21 – SD Kickoff meeting held with Champlin. EMA and 911. SD to be finished by 1/7.
12/22/21 – progress meeting with Users.
01/06/22 – 90% review meeting with Users
01/07/22 – SD set and estimate submitted to County.
02/24/22 – The building purchased is moving forward. 4 teams made the short list, interview will be held in March 2022.
04/28/22 – Revised plans and estimate sent to County. Project is complete, ready to archive.