TPC – Risk Management Renovation

PM: John Nester, Sam Hoffman, Mike Murphy, Terry Cannon
04/29/21 – TEI and Champlin on board with providing programming for this work for the current SOSS in place. Discuss with John and Bert after partner meeting.
05/19/21 – Kick-off meeting held to review scope.
05/20/21 – Champlin sent County preliminary layout of Scenario 1
05/25/21 – User meeting with Rodney Lofland. Review his stated program needs.
06/16/21 – Met with Risk Mgmt and reviewed Champlin proposed floor plans. Got input from the department and discussed needs for space from the Architectural Review. We also started the MEP needs of the space and settled on some basic requirements for HVAC zoning, plumbing use, and security requirements. They do want a kitchenette for a sink, coffee pot, microwave, and refrigerator.
06/25/21 – Sent updated floor plan to County.
07/29/21 – Two estimates will be done. One with 900 SF, one for 2500 SF. County will open the Archiubs estimate for us to put our numbers in. Put the small estimate in as a line item change in the larger estimate. Get number and get schedule.
10/18/21 – SD and Estimate uploaded to Archibus. Provided plans and estimate for a base, upsize and downsize option. ThermalTech drawings, cost and archibus updates also complete.
01/27/22 – Should have a decision on budget and option on Tuesday.
02/22/22 – DD-CA SOSS submitted.
03/31/22 – Signed SOSS received. Deadline of end of April to be Bid ready.
02/25/22 – Signed SOSS Received.
04/06/22 – Kickoff meeting scheduled, to be complete by the end of April.
04/28/22 – Requested Plan review confirmation meeting mid-May. TTC combined our version with Champlin version, we will continue with the Champlin version from here on out.
5/12/22 – Review meeting held. Revised layout approved. TTE to get started on design and Champlin to finalize finishes.
06/30/22 – Project issued for bid.
07/28/22 – Bids received. bid review 7/26
08/23/22 – Building Permit applied for. Contracts in Progress.
09/29/22 – Contracts finalized. Kickoff meeting to be scheduled in the near future.
10/13/22 – Pre-construction meeting held. Kickoff meeting to be scheduled once submittals are returned.
12/15/22 – Construction ongoing.
01/26/23 – Construction on going. Schedule pushed back to be substantially complete on 2/20/23.
02/22/23 – Construction not complete. Will need a couple more weeks.
03/30/23 – Punch list completed 3/29.
04/27/23 – Still waiting on various punch list items to be complete.
05/25/23 – Furniture installed. Triton to send signed off punchlist.
06/29/23 – Waiting on closeout documents
07/27/23 – Extra permit withdrawal paperwork sent to Triton Jeff to give to city. Check and make sure they done.
08/31/23 – No update.
09/28/23 – No Update.
10/25/23 – No Update.
12/07/23 – No Update.
02/29/24 – Closeouts received
03/28/24 – Hardcopies outstanding.
04/25/24 – No Update.
05/30/24 – No Update.
06/27/24 – No Update.
07/24/24 – Additional request sent to Triton for closeout documents.
08/29/24 – No Update.
09/26/24 – No Update.
12/12/24 – Requested updates last month. No update.
01/30/25 – Meeting held with Triton and County to go over outstanding items for several projects.
02/27/25 – Final Pay app processed.