Hamilton County Facilities

JC – 2022 Cell Door Replacement (Ph 2 Triton)

PM: Matt Butz, Sam Hofmann
01/21/22 – Signed SOSS Received.
03/23/22 – Meeting with Sheriffs to define scope. Number of doors defined. Hold pending door lock replacement project scope.
06/30/22 – Scope to be defined at project kickoff meeting for current set of doors.
07/28/22 – Scope to be defined at project kickoff meeting for current set of doors.
08/23/22 – Scope finalized. Plans to be sent and confirmed with sheriffs.
09/29/22 – Project out to Bid
10/27/22 – Triton won bid.
12/15/22 – Contracts signed and returned.
01/26/23 – No update.
02/25/23 – No update.
03/30/23 – Triton has subbed Jails Products again. Submittals to arrive shortly.
04/27/23 – No Update.
05/25/23 – No Update.
06/29/23 – No Update.
07/27/23 – No Update.
08/31/23 – Submittals received. Changes noted. Meeting to discuss with Sheriffs to be scheduled in near future.
09/28/23 – Meeting held with Captain Wilson. Submittals to be returned with changes as required.
10/25/23 – No update.
12/07/23 – No update.
07/27/23 – No Update.
08/31/23 – Submittals received. Changes noted. Meeting to discuss with Sheriffs to be scheduled in near future.
09/28/23 – Meeting held with Captain Wilson. Submittals to be returned with changes as required.
10/25/23 – No update.
12/07/23 – No update.
02/29/24 – Kick off to be scheduled close to delivery.
03/28/24 – Triton asked question. Site visit to confirm to be scheduled for next week.
04/25/24 – Waiting on sheriffs to answer keying questions.
05/30/24 – Questions sent to Triton. Triton has not responded.
06/27/24 – New project manager assigned to project. Doors to ordered in near future.
02/27/25 – Doors are ordered and scheduled for delivery the last week of April.
03/27/25 – No update.
04/24/25 – Mobilization scheduled for early May.
05/29/25 – Delivery was delayed. mobilization scheduled for mid June.
06/26/25 – Mobilization scheduled for Monday.
07/31/25 – Frames came in with incorrect dimensions. They will all be modified by Triton and remobilized in a couple weeks.
08/28/25 – Modified frames were manufactured for thicker wall dimension. Triton to provide correct frames as soon as possible.
09/25/25 – Corrected frames will arrive with Cornerstones delivery.
10/30/25 – Frames to be delivered monday. Triton to mobilize and complete their scope.
12/11/25 – Triton discovered that the doors were the wrong thickness. Cornerstone doors can be used to cover all but one of their doors. The one door has been ordered and will be delivered shortly.
01/28/26 – Door delivery date has been pushed back. Work has been paused.
02/26/26 – Door still not delivered. Door suppossedly will be delivered tomorrow. two more doors in this project once the door delivered is completed.
03/26/26 – Final phase to begin next week.
04/30/26 – Frames came in the wrong size. Frames to be delivered next week. Project to be complete end of May.
05/28/26 – Cornerstone to complete final pod for Triton. 6/24 install date.
06/25/26 – Demo revealed damage to block walls. Change order accepted. Cornerstone to complete work. Mobilized this week.
07/30/26 – Work is complete. Closeouts ongoing.
08/28/26 – No Update.
09/24/26 – Change order to order new millenium pac units submitted. No update on closeouts.