Winton – New Animal Shelter Building

PM: Rycca Thacker, Mike Murphy, Terry Cannon
12/11/25 – Land purchase is complete. The new building should be online by September 2029-ish.
02/26/26 – SOSS and PO received. Site investigation has begun. Kickoff to be scheduled sometime in March.
03/26/26 – Kick-off held with County, Cares and design partners. Geotech will begin investigation shortly. SPoA to send out programming survey shortly.
04/30/26 – Geotech beginning their scope. Needs assessment confirmation meeting on the calendar for 6/3.
05/28/26 – Data collection teams meeting held on 5/12. CARES needs to confirm some operational questions to prepare for the needs assessment on 6/3.
06/25/26 – Programming verification meetings complete. CARES will review and compare data to existing concept plan.
07/30/26 – SPoA to provide final program report.
08/28/26 – Programming report provided to CARES for review. Add services for Geotech approved. Additional testing scheduled for first week of september.
09/24/26 – Additional clearing needed for geotech. Approval pushed new borings until October. Program verification meeting held and concept plans incoming.
10/29/26 – Concept plan presented. CARES provided comments. SD plan in progress.