PM: Rycca Thacker, Eryn Thamann
12/11/25 – SOSS requested for space allocation drawing updates. Awaiting final building priority list from HCFD to finalize SOSS.
01/29/26 – Elevar working on SOSS.
02/26/26 – Elevar provided SOSSs.
03/26/26 – SOSSs approval pending.
04/30/26 – SOSS approved for three buildings. Need schedule from HCFD for access hours, building priority, and deadlines.
05/28/26 – Waiting for Elevar badging to be finalized.
06/25/26 – Started scanning of 1701 06/22 and will last the week. Drawings will be updated as scans come back and starting with JFS areas for leasing diagrams.
07/30/26 – Working thru 1701 set and met with HC IT Dept to review on 07/23. Scanning complete for 111 Tri-Co. Scanning scheduled at TPC for 08/10-08/14.
08/27/26 – Provided 1701 CAD and pdf files. Just received pdfs files of the parking garage and will bgin on those soon. Scanning completed at TPC and 111 Tri-Co. As staff area vailable, these drawings will be checked against scans.
09/24/26 – CAD files received of 1701 parking garage from Champlin to complete that portion of work. Files for 111 are almost complete and sent to HCFD for indications of tenant spaces. Templates for 138 are complete.
10/29/26 – Working thru TPC now.