Hamilton County Facilities

Comm Center-A

Communication Center
Archive

Comm Center – BE Assessment (F041)

PM: Rycca Thacker / Ian Zellner, John Millar
03/06/26 – HC requested an assessment SOSS.
03/13/26 – THP provided an SOSS for review.
04/09/26 – HC approved SOSS.
04/30/26 – THP working on Assessment. Roof testing/thermal scans 4-6 weeks out from April request. Testing contingent on weather conditions.
06/16/26 – THP completed field survey and roof scans.
08/05/26 – THP published the final report.
08/27/26 – Put into Archibus. THP has full restoration and partial, agreed to enter full cost and in notes put reduced scope.

Comm Center – BE Assessment (F041) Read More »

Comm Center – EV Charging Project

PM: John Nester, Mike Barth
02/29/24 – Project created for tracking. MCB says we have all we need.
03/27/24 – Project docs to be sent to JN ASAP.
04/24/24 – BW and TEI review ODOT documents and submit what we can.  Balance of data required from tenant.
05/29/24 – Project pending data from tenant.
06/26/24 – Project pending data from tenant.
07/24/24 – Project pending data from tenant.
08/28/24 – TEI and HCFD develop a package to send to ODOT for review and commentary including bid documents, project manual and OPC. Package sent to ODOT on 08/28/24.
09/25/24 – Project pending ODOT approval.
10/30/24 – Pending ODOT approval
12/11/24 – No Updates from ODOT.
01/29/25 – No updates from ODOT.
02/26/25 – No Updates from ODOT.
04/23/25 – Received Stage 3 approval from ODOT. HCFD investigating funding gap from the grant and the updated costs. Then notify TEI on next steps.
05/28/25 – Next steps to be coordinated with HCFD.
06/25/25 – TEI sends updated opinion of probable cost to HCFD for county to discuss grant funding/cost differential.
07/30/25 – No Updates
10/29/25 – DEG receives email from HCFD that this project is cancelled. OK to Archive.

Comm Center – EV Charging Project Read More »

Comm Center – Lobby and Breakroom Renovation

PM: Rycca Thacker, Sam Hofmann
02/22/23 – Bid awarded to Alpha. Contracts are in progress.
03/30/23 – Contracts still in progress.
04/27/23 – Pre-construction meeting held. Submittals incoming.
05/25/23 – Some submittals received and returned. Permit approved. Construction is almost ready to begin.
06/29/23 – Construction ready to begin 2 weeks from notice from Rycca.
07/27/23 – Construction began this week. Most submittals complete.
08/31/23 – Construction ongoing. CO#1 in progress to add minor scope. TTE responded to the plumbing change order work with comments.
09/28/23 – Construction ongoing. CO#1 settled. CO#2 has not been agreed on.
10/25/23 – Construction ongoing. Change Order #2 rejected by TTE. Alpha to rework change and send back to us. Lights have been reworked in current ceiling configuration.
12/07/23 – Work is finishing up. Punch list held on 11/27. Back punch to be scheduled.
02/01/24 – Drinking Fountain cover still not acceptable, TE to work on better cover for the plumbing.
02/29/24 – Back punch items still unresolved. Closeouts in review.
03/28/24 – Waiting on hard copies from Alpha.
04/25/24 – Closeouts received. Check to see why its so large. Three hard copies still required with a thumb drive.
05/30/24 – Waiting on release of liens. TTC repaired the water cooler cover to give it more accessibility.
06/27/24 – No Update. TTC modified the EWC wrap so it’s better than it was.
07/23/24 – TTV replaced the pipe wrap again and it looks better than “better than it was”
08/29/24 – All closeouts received. Final pay app released. Ready to archive.

Comm Center – Lobby and Breakroom Renovation Read More »

Comm Center – Asphalt Resurfacing (F056)

PM: Matt Butz, John Millar/Matt Rigdon
12/14/22 – Hamilton County published a project list for 2022. Project to be complete by Fall of 2022.
02/25/22 – THP and County met to discuss scope.
04/04/22 – THP submitted a SOSS for review by the County.
04/25/22 – County approved SOSS.
06/10/22 – THP issued design development documents.
06/21/22 – THP received contractor opinion of probable cost. Within project budget.
06/22/22 – County published AIA forms for final bid documents.
06/30/22 – THP documents ready for bid. THP coordinating bid dates. Anticipates bidding in July.
07/11/22 – THP issued “For Bidding” submittal with drawings and project manual.
07/19/22 – THP hosted pre-bid meeting at HC Comm Center Visitor Lot
07/21/22 – THP issued Addendum #1.
08/03/22 – Bid opening scheduled.
08/03/22 – No bids received at opening. THP contacted over 12 contractors during the bid period. Contractors noted extremely busy for 2022.
08/25/22 – Project documents updated and work rescheduled for spring of 2023. New bidding period advertise 8/26/30, prebid 9/6/22 and bids due 9/13/22.
08/26/22 – THP issued “For Bidding” submittal with new schedule for 2023.
09/06/22 – THP hosted pre-bid meeting at HC Comm Center Visitor Lot.
09/14/22 – Bids are due.
09/14/22 – Bids from Rack7, Prus and JK Meurer were received. All base bid within budget. Rack7 was the apparent low bidder.
09/21/22 – THP and Rack7 completed an initial bid review meeting. Rack7 did not include unit cost work in the base bid and has withdrawn from the bid.
09/28/22 – THP and Prus will complete an initial bid review meeting.
09/29/22 – THP and Prus completed an initial bid review meeting. Prus did not include unit cost work in the base bid and has withdrawn from the bid
10/05/22 – THP and JK Muerer completed an initial bid review meeting.
10/11/22 – THP issued a Bid Summary Letter recommending JK Meurer for the contract.
11/21/22 – J.K. Meurer was approved contract and corresponding PO. Kick-Off meeting sometime after the first of the year. Anticipate work after Winter/start of Spring.
01/04/23 – HC sent CO 001.
01/05/23 – THP signed and returned CO 001.
01/06/23 – J.K. Meurer signed and returned CO 001.
01/10/23 – J.K. Meurer to update THP/HC on background checks, expected submittal process date, and intended work completion date. THP proposed date for Pre-construction for March 15, 2023.
01/26/23 – J.K. Meurer to update THP/HC on background checks, expected submittal process date, and intended work completion date. THP proposed date for Pre-construction for March 15, 2023.
02/23/23 – Background checks to begin this month. Anticipating Preconstruction Meeting for March 15, 2023.
03/15/23 – Preconstruction Meeting
03/23/23 – Anticipating work schedule is May 1st-22nd. The following still needs to be submitted by J.K. Meurer: SOV, emergency contacts, and official schedule. No submittals have been submitted; Anticipating Mix Design Submittal.
04/25/23 – No updates for April. Work to start on May 1st (weather pending). Anticipating on-site visit with J.K. Meurer and Hamilton County on May 2nd (weather pending).
05/01/23 – J.K. Meurer provided mix design submittals. Asphalt resurfacing work began at Visitor Lot.
05/02/23 – THP site visit performed. Revisions were made to full depth repair quantities. Approx. 50% less area than original after observation of base course. Revisions by HamCo were made to ADA space to allow for access aisle to be at west side rather than east side of parking space.
05/05/23 – J.K. Meurer completed work at Visitor Lot and THP performed site visit. Work appeared to conform to drawings and revisions.
05/08/23 – J.K. Meurer began work at Secured Lot.
05/09/23 – THP site visit performed. Revisions were made to full depth repair quantities. Approx. 50% less area than original after observation of base course. Revisions by HamCo were made to the berm at the loading dock ramp.
05/15/23 – J.K. Meurer completed work at Secured Lot and THP performed site visit. Work appeared to conform to drawings and revisions.
07/26/23 – Bulletin being prepared and to be sent for review July 31.
08/09/23 – THP met with Ian to review drive repair needs.
09/26/23 – County request gate repair as part of drive work. Motor details sent to THP.
09/28/23 – THP forward JK Meurer quote for drive and gates.
10/06/23 – County approved quote for drive and gate. THP notified JK Meurer to proceed.
10/11/23 – JK Meurer proposed full slab replacement. THP provided slab requirements for the new ramp. JK Meurer provided updated proposal.
10/17/23 – Project budgetary numbers sent to County for review. JK Meurer proposal using cash allowance funds. Work is below total project budget.
10/17/23 – County sent draft Change Order No. 2 for authorization of new drive and gate motor.
10/25/23 – County published executed Change Order No. 2.
10/26/23 – JK Meurer schedule to begin drive work the middle of November.
11/03/23 – Drive repair work rescheduled to accommodate interior renovation project.
12/04/23 – Demolition of the ramp started.
12/06/23 – Lower section of ramp subgrade and steel prepared. Bottom half of ramp poured and concrete tested. THP inspected steel and Terracon tested concrete.
12/07/23 – Upper section of ramp schedule for completion.
01/15/23 – Concrete replacement at ramp was completed mid-December. Email received from contractor that installation of new gate operator is expected to be installed at the end of January.
01/30/23 – Gate contractor notified THP that the operator is now expected for production on 01-31-24. Production is backed up for LiftMaster and the ship date keeps changing. Installation is TBD in February.
0002/28/24 – Gate contractor is to notify THP and County once the vendor is contacted. Delivery has been delayed for approximately two months.
03/13/24 – Gate operator was delivered and installed on site. Overhead Door did not put the operator in service due to the condition of the gate.
03/18/24 – THP, HamCo Facility Manager, and Overhead Door met on site to review condition of inoperable gate.
03/27/24 – THP received quote from Mills Fence Co to replace existing gate. HamCo has approved. CO to be made up next week.
04/25/24 – JK Meurer planning on complete repair to top of drive on 4/26/24.
05/1/24 – JK Meurer and subcontractor has revised their project close out documents and sent to County. Project is closed. No more updates.
05/18/24 – JK Meurer to revise their pay app 2.
05/23/24 – Mills Fence Co checked gate to ensure it is working. JK Meurer and THP to start the project close out process.
09/26/24 – Awaiting final Change Order deduct from Hamilton County and Mills Fence lien waiver for close out documents.
12/11/24 – THP to review close out documents following updated close out procedures.
01/29/25 – Closing out – last phase. All documents are in and reviewed by THP. (3) As-built Hard Copies, (1) copy of final pay app & AIA docs, (3) copies in notebooks of O&M, and (1) USB flash drive. Will hand in at Thursday’s meeting.
02/24/25 – Final pay application approved.
02/25/25 – Final pay application prevailing wage documentation sent to County.

Comm Center – Asphalt Resurfacing (F056) Read More »

Comm Center – Cell Tower AC Replacements

PM: Rycca Thacker, Terry Cannon
10/20/21 – SOSS approved.
10/21/21 – Draft project manual distributed for review.
10/28/21 – Project prebid tomorrow 10/29. 12 sites. One base bid Blue Ash, 11 alternates.
11/08/21 – Bid received by TEI.  JCI and DK bid the work and Trane declined to submit a bid.  Bids were tabulated and sent to County for award.
12/13/21 –  This month we worked on getting the contract in place with Debra Kuempel for the Bid Bid and seven Alternates.  We continue to work on paperwork and contract.  Terry talked to Kerry last Friday about the intent of the specifications and verified with DK that the bids include all the labor and materials for the work.  Kerry preparing to write a non-AIA contract for use on this project and warned that an STD contract ADA contract protects the county less than a full ADA contract.
01/25/22 – Contract in signing stages at DK
02/24/22 – Still in contract stages, goes to BOCC this Wednesday and PO after that.
03/31/22 – PreConst next week.
04/28/22 – Pre-const meeting was held. Debra is preparing to start the work and call Scott. Submittals have been sent in for the Marvair unit, DK working on the Indian Hill split system.
05/25/22 – DK is scheduling kickoff meeting and fieldwork with Comm Center. I check in a couple of times with Dave. We also reached out to Mobilcom on alarm monitoring and set up a field meeting with DK and Comm Center to all visit a site to see how the alarms are connected to the AC units so we order them correctly. Submittals are still in my inbox pending this field finding.
06/30/22 – All submittals returned and approved. Equipment is on order DK starting at Indian Hill, however the installed equipment is different than planned, DK taking care of it. Payapps should start this month.
07/27/22 – DK started the Indian Hill site this month and is trying to get three Marvair units for the other sites this summer.
08/24/22 – Indian Hill #1 is complete, #2 is being done this week. Payapp #1 submitted with corrections for payment.
09/25/22 – Payapp #1 submitted, Rycca working with DK on some PW issues. No update on the Marvair units for delivery date, checked in with Dave 2 or 3 times.
10/26/22 – Equipment scheduled to arrive Nov 16.
12/15/22 – About 6 sites are complete and Debra is working on the additional sites daily. They hope to be done by the end of the year if the weather holds up.
01/24/23 – All sites are done and DK has billed for all the material. Scott says as soon as he gets time, he will coordinate a punchlist visit for us.
02/17/23 – Scott, Rycca, Terry performed an punchlist at three sites. TTC to prepare punchlist for DK to use on this project. TTC spoke to Dave about some issues we found in the first few locations and DK will take care of them.
03/29/23 – Closeout documents are under review for this project. Final payapps have also arrived. TTE making three binders for closeout.
04/25/23 – Punchlist sent to DK, O&M printed and will be delivered this week to Rycca. DK to check Eden Park for status.
05/21/23 – Working on closeout and punchlist with DK. Eden Park site was checked for issues.
06/28/23 – Punchlist complete, DK working on closeout documents.
07/26/23 – Signed punchlist sent to County for approval. Final payapps sent in for processing. Ready to archive.

Comm Center – Cell Tower AC Replacements Read More »

EMA/Comm Center – SD & Cost

09/20/21 – Kick-off meeting with County, Champlin, Thermaltech, THP, and Cushman & Wakefield.
09/27/21 – Building Tour.
09/30/21 – SOSS received from County
10/13/21 – Programming Meeting held with Comm Center, County, Cushman & Wakefield.
10/15/21 – Programming Meeting held with EMA, Champlin, County, and Cushman & Wakefield.
10/20/21 – Draft Program sent to User groups for comments.
12/03/21 – Signed SOSS received for SD.
12/13/21 – SD Kickoff meeting held with Champlin. EMA and 911. SD to be finished by 1/7.
12/22/21 – progress meeting with Users.
01/06/22 – 90% review meeting with Users
01/07/22 – SD set and estimate submitted to County.
02/24/22 – The building purchased is moving forward. 4 teams made the short list, interview will be held in March 2022.
04/28/22 – Revised plans and estimate sent to County. Project is complete, ready to archive.

EMA/Comm Center – SD & Cost Read More »

Comm Center – Building Masterplan

05/22/21 – SOSS Submitted to County
06/02/21 – Received signed SOSS
08/09/21 – Meeting held with users to review scope.
08/26/21 – County said to let THP look at floor loading for this work. OK to get them involved now. Previous work created a lot of penetrations in the existing floor and new furniture was heavy. THP to review. New furniture should be less substantial than existing spaces.
10/28/21 – Keep masterplan work in place because this building will remain in the county portfolio for repurposed training facilities.
12/14/21 – No Update.
02/24/22 – Combined Estimate required. need to schedule a meeting to resolve scope overlap.
03/31/22 – SD plan of Combined 2022 estimates created. Meeting is needed to confirm final SD scope.
04/28/22 – We discussed the scope in the Admin Office spaces? Were the Radio Room involved? and we decided that we have not. Should we include Mission Critical involved in this report? Kitchen and Locker room are included.
05/26/22 – Finalizing estimate.
06/30/22 – Combined scope plans provided to TEI for estimate. Finalizing estimate
08/25/22 – SD set sent to HC. Plans need further broken down and resent.
09/29/22 – Site visit scheduled for 10/11.
10/27/22 – Scope refined after field visit. Owner Review Issuance scheduled for 11/11.
12/15/22 – Masterplan drawings need to be changed to reflect current project. waiting until bids are accepted to update according to which alternate is chosen.
01/26/23 – Updated plans will be completed by end of next week.
03/30/23 – Updated plans and estimate uploaded to Archibus.
04/27/23 – No Update.
05/25/23 – No Update.
07/27/23 – No Update.
08/31/23 – No Update.
09/28/23 – No Update.
12/07/23 – No Update.
02/29/24 – No Update.
03/28/24 – No Update.
04/25/24 – No Update.
05/30/24 – No Update.
06/27/24 – No Update.
08/29/24 – No Update.
09/26/24 – No Update.
10/31/24 – No Update.
06/26/25 – No Update but keep on list per HC.
03/26/26 – Leave on list.
07/30/26 – OK to Archive, RT

Comm Center – Building Masterplan Read More »

Comm Center – Electrical Service Upgrade

PM – John Nester, Mike Barth

01/28/20 – TEI authors and submits SOSS for project upon request of Facilities Department.
01/30/20 – This in in the approved projects list.
02/26/20 – TEI receives PO and signed SOSS for project. TEI to schedule kickoff meeting with facilities and building manager to kick off the project.
03/26/20 – TEI, County Facilities, and building manager to kick off the project. Due to the COVID-19 restrictions, design meetings and field work at this facility have been placed on hold until all restrictions are lifted.
04/30/20 – Project pending COVID-19 restrictions.
05/27/20 – Project pending COVID-19 restrictions.
06/23/20 – Project pending COVID-19 restrictions.
07/29/20 – TEI met with Bryan Collins and Ian Zellner to re-kick off the project. TEI contacting Joey Downs at Buckeye Power to re-evaluate the proposed solutions and add any updated recommendations/parts-pieces to develop the drawings and specifications.
08/21/20 – TEI contacts Buckeye Power to follow up on the initial quotation that Buckeye submitted. Design has commenced and coordination with EMI equipment supplier. We will notify HCFD once design review is ready.
09/23/20 – TEI, HCFD, and Ian meet with BPS, review the two options for the HMI replacement that BPS submitted. TEI and HCFD requested Sole Source letter from BPS. TEI developing Construction Documents for permitting and construction.
10/27/20 – TEI receives Sole Source letter from BPS. Working on permitting package – will provide draft of package for HCFD review once funding is released for the project.
12/09/20 – TEI wrapping up permitting package, and will send HCFD a review set prior to holiday break for review and to prepare for a January 2021 issuance.
01/26/21 – TEI sends JN at facilities a review set for the project. Upon facilities department review – TEI to finalize bid package and send to get costs.
02/23/21 – TEI and JN establishing final design review meeting with Ian Zellner and Comm Center Staff (within the next week), and will discuss dates for walkthroughs, etc at the meeting, then the project will be sent out for bidding.
03/24/21 – TEI receives sole source letter (modified as requested by Hamilton County). TEI and HCFD meet with the staff at Comm Center, and can issues the project once the procurement method is determined (sole source or ITB). purchasing approves sole source letter on 3/24/21. TEI and HCFD to conduct final meeting to finalize bidding documents ASAP.
04/28/21 – Per HCFD request – TEI requests a current quote from BPS, that has not expired. BPS confirms on 4/28/21 the latest version that we have recieved. Project to be issued upon receipt of this information from BPS and HCFD approval.

05/26/21 – TEI Submits Package to HCFD – who sent to prosecutors office for review and comments. Will issue to BPS upon prosecutor approval.

06/23/21 – Contracts mailed to BPS for signature and return to HCFD. Upon receipt of signed contracts, project will be approved and PO issued.

07/28/21 – PO issued to BPS for project. TEI and HCFD to schedule meeting with BPS to kick off construction and get leadtimes, etc.

08/26/21 – Construction pending procurement of equipment.

10/26/21 -Construction pending procurement of equipment. Anticipated to be Nov/Dec work.

12/13/21 – BPS on site starting today to install upgrades in the gear.  Anticipate project work completed by end of the week.

01/25/22 – Work completed on the original contract work.  HCFD requests quote from BPS for a replacement breaker to use incase of a breaker failure.  BPS issues the quote and HCFD issues a PO for quote.  BPS to purchase breaker.

02/23/22 – Upon receipt of breaker from BPS, project will be complete.

04/27/22 – Breaker received.  Training completed.  work from BPS completed.   Upon receipt of closeout documents (AIA) from BPS – project complete.

05/26/22 – Upon receipt of closeout documents (AIA) from BPS – project complete.

06/28/22 – Project complete.

Comm Center – Electrical Service Upgrade Read More »

Comm Center – Temp Trailer Due Diligence

05/21/19 – TEI to study feasibility of adding a temporary trailer behind the building for additional office space.
07/25/19 – TTC to submit an SOSS for this work.
08/28/19 – No updates this month.
09/24/19 – No updates this month.
10/30/19 – No updates this month.
01/24/20 – No updates this month but officials are started to ask about starting this study.
02/24/20 – No updates this month.
03/24/20 – No updates this month.
04/30/20 – No updates this month.
05/27/20 – No updates this month.
06/24/20 – No updates this month.
06/25/20 – Archive for now, if the project comes back we will bring it back.

Comm Center – Temp Trailer Due Diligence Read More »

Comm Center – Lower Level Quiet Room

05/29/19 – ThermalTech authors an SOSS for the project – pending SOSS approval and PO.
06/26/19 – Project Pending approval of SOSS and PO.
07/24/19 – Project pending approval of SOSS and PO.
08/27/19 – Project pending approval of SOSS and PO.
09/25/19 – Project pending approval of SOSS and PO.
10/30/19 – Project pending approval of SOSS and PO.
12/11/19 – Project pending approval of SOSS and PO.
01/28/20 – Project pending approval of SOSS and PO.
02/26/20 – Project pending approval of SOSS and PO.
03/26/20 – Project pending approval of SOSS and PO.
04/30/20 – Project pending approval of SOSS and PO.
05/27/20 – Project pending approval of SOSS and PO.
06/23/20 – Project pending approval of SOSS and PO.
06/25/20 – Latest discussion was to just archive this project as it is not needed at this time. OK to archive.

Comm Center – Lower Level Quiet Room Read More »

COMM CENTER Asbestos Study

Partner Lead: GBBN

10/20/11 – Kick-off Meeting with Pinnacle and Facilities Department

11/04/11 – Facilities Department send list of buildings to be included in Asbestos Abatement Reporting.

03/30/12 – Meeting with Tim Schue of Facilities Department to discuss Archibus Input Strategy

04/05/12 – Meeting with GBBN and Facilities to discuss drawing format.

05/10/12 – Meeting with GBBN and Pinnacle to discuss drawing format for reports. Tony Matre’s request for ‘General Information Notes to occur on each floor plan are discussed.

10/27/12 – Pinnacle Engineering sent ACM list from Archibus/BRG for purposes of designation conversion from Pinnacle report to Archibus data entry.

04/05/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response.

04/20/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

03/26/14- All asbestos reports and associated drawings are complete. Final drawing input into Archibus/WebCentral is ongoing. GBBN was granted access to the database to complete the drawing downloads.

07/01/14- GBBN sends another email and follow-up voice mail to Pinnacle Engineering inquiring about status of billings and final completion.

8/29/14- Pinnacle Engineering sends invoices for services to GBBN.

10/29/14 – GBBN sends Tony Matre SOSS invoice status with all of the Pinnacle Engineering invoices included.

10/31/14 – GBBN pursuant to Tony Matre’s request sends letter of documentation regarding scope overruns.

02/20/15 – GBBN in communications with Tony Matre to finalize invoicing on all projects.

COMM CENTER Asbestos Study Read More »

Comm Center – Fire Alarm Upgrade

10/05/04 – TEI, Greg and Dan from HCDF meet with Security Fence to review proposal. It was agreed upon that we where going to reuse the existing closer that HCDF installed and provide new hinges. This is less that work that originally quoted. Security fence is to revise quote and get to TEI for approval from Diana.

09/30/04 – Final test approved by fire marshal and county building inspector. Waiting for final close out documents from T.J. Williams to close project out. Simplex to provide training to Greg and other personnel. TEI to send as-built drawings with final closeout documents to Diana. We are nearing completion. Contractors preparing for pre-testing with simplex. Final testing approximately in two weeks around.

09/28/04 – Pretest complete and everything tested correctly. As Built drawings complete and delivered to site. Final test with the County Inspectors and Fire Marshal scheduled for 9/30/04 at 9:00am.

09/3004 – Fire Alarm Test passed.

10/19/04 – TEI left a message with TJ Williams for Rick and spoke to the person doing billing to request final billing documents. She was familiar with HC AIA documents and I explained the ones needed. She indicated she would get with Rick and send the correct documents. I spoke with them over a week ago, but I have not received anything yet.

The issue with the man gate, when we meet Charles from Security Fence he was going to get you a new quote that is corrected to reflect the work they are proposing to do, which is less than original. I have not received anything from him yet. I plan to follow up this week.

10/21/04 – TEI to follow up with T.J. Williams for training. As builts were forwarded from TEI to HCFD for archive room. TEI spoke with T.J. Williams and assisting in final documents.

Comm Center – Fire Alarm Upgrade Read More »

Communication Center – Electric Building and Boiler Plant Upgrade

09/02/06 – TEI has paid Triton over $6000 in boiler cost and now another $4000 is going to them to cover the boiler snafu at the Comm Center. TTC advised Grady to finish up the paperwork and they will provide the Change Order for the project for completion. TTC asked for completion this week.

04/26/06 – TTC and Kevin approved the $850 allowance usage for Triton for stronger panels in the old louver spaces. TTC requested all O&M’s and final paperwork back from the contractors via email. Triton said the painting was complete for both the prime coat and supposedly the final coat two as Grady said is should be done last week.

04/04/06 – TTC emailed Kevin back with this information: gary and I already sent an FINAL email to AO Smith Monday morning and gave them a deadline of tomorrow at 4pm (wed) to reverse the cost on this project or else be out of spec’s. we will know something on thursday. I emailed grady today because, he, majid and I were working on a solution that could possibly remove all extra cost to the county in regards to the boiler work – don’t know if he made it work yet. finally, I have asked triton to paint the gas line and brace the aluminum pans in the boiler room to complete their punchlist. dave meier had a control question about a specific wire which I asked spectrum to give him a call directly. talk to you soon. ttc

03/06/06 – TTC and Mike talked about the building being in cooling today even though the OA temperature was 39F. Nevertheless the personnel had the building in cooling. We will keep an eye on the building. Kevin requested the price breakdown on the boilers. TTC will fax to Kevin today.

03/01/06 – TTC & Matt reprogrammed the boilers to run on the new differentials given to me by Lochinvar. The way the control algorithms are written we are using a OA setpoint with 10 degree offset above SP a 10 degree differential back down to SP and then the boiler should restart. To prevent nuisance trips I have reset the OA reset schedule to 0=160 and 60=110 with the 10 degree F.

02/24/06 – Mike reported that the boiler timing circuit was set up to 2 minutes because the valves take 1:40 seconds to stroke completely. On the reverse side the chiller is going out on freezestat because the minimal water flow on the slow opening diverter valves is creating too cold of inlet water temperature. JB Schmitt called today to report that their change order was $100 off.

02/22/06 – The boilers are going out on high limit safety so TTC visited the site and sent this email: Grady, I met Matt and Mike Jackson out at the site yesterday and am actively trying to resolve these issues with the boiler plant.

* after we added the common HWS temperature probe the boilers can run in lead/lag as we wanted but the probe can be as much at 18 degrees off what the water temp really is. this forces the boilers to high fire too long and they go out on a manual reset for high limit. I believe we will need the common HWS temperature put into a thermowell into the water stream to get a more accurate supply water temperature quicker to the boilers. the strap on location is okay it just needs to be immersed. can this be done on this 3″ pipe? * the boilers are locking out at 190 degrees hot water temp and this seems low even though it is their default. I have a two fold question about this and they are, is the factory setting 180 degree with a 10 degree deadband or is the autoreset actually 190 degrees with 0 degree setpoint? I am asking that this be reprogrammed up to 200 degrees F as this still provides plenty of safety before we steam at 212 and will allow us to reach our max system temp of 180. * how come the boilers can’t operate in lead/lag fashion when the common HWS temperature is not fed to the microprocessor? as soon as we disconnect the common the boiler both come on and fire at the same firing rate – is this field convertible? if so, we may be able to forego the above two steps and still meet my sequence requirements on this job but I think matt said that the factory said that we have to have a common T sensor point into the boiler to correctly do the lead/lag. * the outdoor sensor is still 10 degrees off so I instructed matt to move the new sensor over the old existing OA location in the area well and re-use existing wiring that the owner had in place to refeed the OA signal to the boielr panel. it is now near the bsmt ahu inlet and should be very well shaded all the time. please check with denny and the factory and let me know.

for now we are keeping both boilers running on the local outlet temp to prevent nuisance tripping but they are running in tandem all the time. no real lead/lag features even though they back each other up.

02/17/06 – since matt moved the hot water supply temperature we are seeing some funky conditions at the comm center as we discussed previously today by phone. mike jackson did a lot of troubleshooting for me today at the site so I want to relate everything he saw there and I am sure that another trip out there is warranted by matt. the boilers were off on flow when mike first checked them. he reset them manually as is req’d and set the delay timers up to 1 minute to allow the 3-way valves to stroke. in about 10 minutes the building temp was rising up to a reasonable rate but the boilers went out on high limit with an error message that says “Auto Reset – High Limit” our first thought is that this is certainly related to relocated the common HWS temperature and that the boilers were overfiring and going out on local high limit while the loop temp remained below its SP. we also checked actual pressure at the pumps in case the flow at the boiler is lower than is necessary. the outlet psig is 30 so that looks fine. boiler #1 appears to still be in the lead position and during the day mike continued to check on the boilers and reported this condition: at 40 degree OA the HWS setpoint should be 140 degrees. the boiler plant brought the boilers on at 139 degree F and the boilers again went out on high limit with the outlet temperatures at 190 degree F on the inlet at 158 degree F. at this condition it is understandable that the high should engage but why are the boilers still even firing at 18 degrees above setpoint? the LED panel has an point reporting as System Temp and it was 146 degrees. is this the reading at the strap-on sensor or is it the setpoint we are shooting for based on the OA temp? if it is the setpoint it is off by 6 or 8 degrees and I would question whether we are using 0-180 to 60-120 or the old reset of 0-180 to 60-140? can matt verify this for us. if having the remote sensor on the common supply pipe is going to cause this much trouble, I may just go back to using the outlet of each boiler to control its local firing rate and get rid of all these nusicance trips we saw today, but I tend to think that maybe a parameter is currently misprogrammed. as you suggested we should certainly check the flow through each boiler to make sure we are removing the correct amount of heat from the boiler while it is firing and the water supply is sufficient. without any real water sitting in the heat exchange these boilers will always tend to heat up fast on the outlet while the system loop lags behind. my final request was to isolate boiler #2 and turn off boiler #2 so that #1 handles the load all weekend. with all the flow going through one boiler there should be no mixing and the outlet of the boiler should be the same as the strap-on sensor and we shouldn’t have any problems this weekend. can you schedule matt to meet me out there with jackson on tuesday to go over all of this? I have to take my father in law to the hospital on monday and my wife to the dentist for dental surgery so that is going to be sucky day for me all the way around. please set up tuesday at 9am at the comm center

02/15/06 – TEI, ICS, Triton, Facilities and PW met on site with Bldg Dept and Fire Dept for final inspection and testing. After an initial roadblock, Buckeye Power to come over and simulated a electric failure in which the building passed. The Colerain Fire Dept contact, Jim witnessed and will report to the County Bldg Dept. The generators came on in under 2 seconds and restored power to the building in under 10 seconds. TEI also verified the operation of fuel oil pumps on both the supply and return system for the generators. The boilers were tested and they backed each other up properly. The electric boiler provided manual backup of the gas boilers. The pumps provided backup for each other within 20 seconds of failure. TEI has instructed Triton to move three temperature sensors. The OA is going to be moved to the area well and they can reuse existing wiring for that connection. The HWS temperature will be moved inside the new boiler room to after the electric boiler location in the common HWS header. The chilled water temperature strap-on should be moved to the common outlet of the 3-way valve connection (currently it is about 10 degrees off so we set the start temperature of the chiller to 80 instead of 80). We will allow facilities 2 weeks of working with the boilers before we have final training on operating the Lochinvar’s. The boilers are scheduled to rotate daily for lead at this time. The master controller is located in side Boiler #1 and if for any reason the power to this boiler is turned off or failed then Boiler #2 would have to be removed from cascading control to operate in Boiler #1’s place. The gas line still needs to be painted. The fuel oil pumps always switch lead after about 10 seconds and Triton will fix this. The County would like to have Triton put reinforcing bars put behind the louvered openings for security and stability. Facilities will have the smoke head remounted in the new boiler room. TEI want like JC Schmitt to do a final cleanup around the building as TTC noted a lot of debris still laying in the field (metal rods, sheet metal pieces, wood, studs, canvas, plastic containers, etc). Triton should update the sequence to reflect backup and alarm sequences and submit to County along with final boiler programming settings and include this information in the O&M. Krebs came out after the testing was complete but did not have to do any work as TTC met them at the gate and told them we were complete. We may have to pay a service call for that arrival.

02/10/06 – IBI gave final approval to the building electrical and now we are ready for final mechanical and building inspections.

01/23/06 – Lochinvar provided the final programming instructions for the boilers. Triton has every intention of completing the punchlist and programming this week. Jeff Jones is supposed to provide the UL listing on the fuel oil pumps. We are shooting to have all final work and inspections completed this week on this project. TTC will try to coordinate final inspections this week. JB Schmitt entered a allowance usage request of: cut out scuppers: $42 + $191.84 remove concrete piers: $50 + $40 + $130 +$191.84 lock conversion: $227 + $335.72, total: $1329.24. TTC forwarded to KM, TA and TS for approval.

01/20/06 – John Bates emailed TTC today to report that Sean has looked at the boilers and AO Smith should have an answer early next week.

01/17/06 – TTC emailed ICS to inquire about electrical status on this project. ICS reported that the fire alarm test passed. Vic Spang will email everyone the status of the UL listing. Vic also said that O&M manuals should arrive today. ICS should be done with our punchlist items about 2 days after the control panels are UL listed.

01/16/06 – TTC spoke to John Bates last Friday and emailed our these notes today. TTC talked to Grady and got this update on the punchlist status. Triton has gotten the collars, valve tags and miscellaneous punchlist items into their shop and will continue to finish the punchlist this week. They will clean up the generator room this week as well and fix the two leaks that Greg called TTC about. The control programming codes are expected in this week from Lochinvar and Triton will finalize all control work this week and next at the Comm Center. Final completion date should be no later than 01/27/06. TTC will contact ICS to coordinate the final building inspection on this project.

Kevin and Grady,

John Bates and I finally connected via the telephone late last Friday afternoon. It was a good conversation and he apologized to everyone for it taking so long to get back to us on this issue. I recapped everything that has happened on this project beginning in March of 2005 when we were finishing the construction documents up to the partial installation. Suffice to say that he said he believes what I have told him is the order of events and the phone calls I made to the local rep and the factory and that although it is not the AO Smith normal policy to take back opened boilers, he will begin the return authorization process by sending an AO Smith representative to Hughes supply to confirm the condition of the existing boilers and take some digital photographs. The restocking fee will have to be paid but I believe he believes he will be able to get the factory to take the boilers back.

I have called Gary Tedesco of Hughes and advised him that Shawn from AO Smith will be stopping by to look at the boilers. As I get further information I will pass it along to you guys.

Right now the boilers are being stored at Hughes Supply.

01/13/06 – TTC called and emailed John Bates again about returning the boilers.

John,

I have called a couple of more times yesterday and am on the phone right now trying to get a hold of you and leaving you another message. This issue has been lingering since the first week of December. I understand that you must be very very busy but I have scheduled meetings with the contractor to discuss change orders and closeout for this whole project – the job is complete and we still have you boilers on site, so you can see I have a dilemma – we can’t closeout this project and I believe that Mr. Maue is desperately trying to get this project wrapped up.

This is only my second time working with Mr. Maue of Hamilton County Public Works and I have no doubt that he has serious concerns about my ability to handle the construction issues on a project like this so I desperately need your help. I don’t know that I have ever had something stall for so long or been so worried that there may not be an equitable resolution on the horizon – I am still confident that if you call me back we can work something out.

As I have specified AO Smith boilers for so long – 13 years now (I personally enjoy using the cyclone water heaters as they are a fantastic product – I spec’d them as part of an energy savings project, we use them in all the hotels we design and that’s about 5 a year and the County also used them at a recent renovation at their sheriff patrol hdqtrs), I am finding it difficult to understand our current dilemma. Your former local rep built a great relationship with ThermalTech and your company has always been foremost in our specs and schedules – I am sure that neither of us wants that to change, nor does it have to, please call me back or email me the return authorization and procedure.

If this is a decision that you cannot make, please send me the contact information of you supervisor or someone in customer service who can make the authorization.

Thanks again and hope you have a great weekend and please let me know by the end of business today?

01/12/06 – Kevin emailed Grady directly to inquire about the progress of this project. TTC informed him that the email server may be down.

01/11/06 – Greg Chambers called TTC confirmed today’s 1:00 p.m. test is only a Fire Alarm test. TTC called John Bates two more times this morning about returning the Legend 2000 boilers. TTC called back at 3:00 and left another message. TTC got John’s email address and emailed him the same request that he has been calling about:

Dear Mr. Bates,

We have missed each other in phone tag and I know you are on the road a lot for your job. I am hoping it will be easier to give me a RMA process and number via this email.

In March 2005, I spoke with your local rep Disney-McClain and called your Corporate Sales department in search of boiler that we could use as base bid in our Dual Temperature Water system at the Hamilton County Communication Center, my first inclination was to use the intelli-fin boiler but you don’t manufacture those in a 500,000 btuh size so after speaking to sales staff at your companies and vendors, we spec’d the Legend 2000 with the bypass pump option to keep the incoming water temperature at 140 inlet.

We bid the project, accepted the submittals and received two boilers on site. They were uncrated, placed on the housekeeping pads and one boiler was actually piped in. Electrically, a junction box was mounted on the side of the boiler for controls. At that point I was called down to discuss the bypass pump. In the arrangement and in your documentation the pump was piped in series with the water flow and a bypass pipe around the boiler was on the outside. This is not what I had envisioned as I was lead to believe that he bypass pump would have self contained controls that would modulate in the bypass to return enough water to keep the inlet at 140. In actuality that is not the case and after speaking with Kevin Binkley at length, I could see these boilers do not meet the spec or requirement of this job. The alternate boilers on this project are all condensing boilers and would not have an issue with incoming water temperature. This dual temperature water system can be switched from chiller to boiler several times a week so you can see the Legend 2000 boilers will not work well without a storage tank and recirc pump which is exactly what I was trying to stay away from on this project.

At this point the boilers HAVE NEVER BEEN TURNED ON or used in any way. What I would like is a return authorization so that the local contractor (Triton Services) can return the boilers to local warehouse (Hughes Supply) and they can send them back to AO Smith.

There may very well be a restocking fee that I am willing to work with you on that but in my humble opinion, I believe I talked to everyone that I needed too during the design phase of this project to let AO Smith base bid on this project – I just got some bad information on application data for this boiler. Maybe you guys thought the dual temperature water system meant it would only be switched to heating once a year and that the boiler heat exchanger could handle that??? I never said that, but there was definitely a communication error.

I am sure that these boilers can be resold to someone – they are in like near perfect shape and never started even though they have been uncrated. They have been stored indoors even after we removed them from the boiler room. Please give me an return authorization approval, an RMA number, an address and a procedure to return these boilers.

The County has used many AO Smith products in the past and when they build their new jail complex in the next few years, many more AO Smith could be used in that project so I am sure we are all striving for the same goal here.

Please call me or email as needed.

Thanks again, ttc

01/10/06 – TA distributed the electrical punchlist for the job. TTC distributed a revised mechanical punchlist for the job. Triton sent payapp #3 in for pencil copy and question payment of payapp #2. Kevin submitted payapp #2 for payment per Grady’s inquiry.

1/09/06 – Kevin called today because he is concerned about Jeff Jones UL listing of the generator. TA talked to ICS to tell them to get something resolved or the County will hire Jeff Jones directly and back charge the contractor. TTC talked to Triton about controls and emailed everyone that the controls are semi-automated. The new actuator is installed and the summer/winter switch now strokes the valves just like they use to work. The system is currently at a state where it was before. The Comm Center can manually change from heating/cooling and the system automatically adjust and powers up the correct equipment. The new lead/lag controls are not installed yet nor is the OA reset on the boilers as they are set to 160 F until next week where the controls will be finalized. Triton still has to change the wiring on the fuel oil pump package to get the UL label.

01/04/06 – Triton called to report that the boiler circuit boards appear to be out not because of water issues but voltage issues. the transformers inside the boilers are bulged and burned, the DC power inverter on the circuit board was blown. Buckeye reported that there have been a couple of brown out issues and once occurred for one second on 12/26 and the generators were tested on 12/30 but they don’t see how this could be related to the boiler problem. No other components have failed in the building on any computer circuits if there was some sort of massive power spike. Matt from Triton talked about putting the new circuit boards on the boiler and monitoring the power into the boilers to ensure they are getting clean power. The IBI inspector, Earl Moon, requested to see UL labels on the fuel oil pumps, tank controllers and the electric boiler. TE investigated and determined that the electric boiler is UL listed and Triton needs to show the inspector where that label is, the fuel oil pumps will require a 3rd party certification from Jeff Jones.

12/28/05 – The mechanical punchlist was distributed. PDF. The electrical punchlist was distributed last week via a verbal conversation from Terry Allgeyer. The final building inspection and testing with the Fire Department is scheduled for Wednesday, January 4th at the site.

12/08/05 – The electric changeover went very well. TA attended for ThermalTech. The building is on new power. Training was completed on the same day for the people that stayed throughout the work and training day.

12/06/05 – TTC sent out CM notes #11. A one week meeting is scheduled for 12/07 to coordinate final changeover of building power to new system. Training is scheduled for 10am on Thursday per TA’s email. Blr-2 is on site. Triton has installed the louvers for the new generators but a final plenum piece is required to finish up. TTC discussed progress with Grady and questioned how the hot water control would be handled. TTC wants a common HWS point to feed the loop temperature to the boilers.

11/28/05 – ICS and Buckeye are onsite preparing final connections to the generators. Triton has finished the muffler install and are working on the final louver install. Kohler is scheduled for next Monday. TTC sent out const mtg #10 meeting minutes. Const Mtg #11 is set for Wed at 2:00 p.m. TTC and TE are working on boiler scheme at 237 WHT. The 3-way valve has been installed and is up and running. Triton provided a cost to the project of Material $162.40 Labor $1,564.00 New valve $1,131.00. This may be slightly higher if charged to the project.

11/23/05 – TTC & TA coordinated with ICS, Triton and Kevin about generator start schedule. It appears that Kohler will be onsite on 11/28 & 11/29 to finalize installation of generators and pretest before Kohler come out to the site. TTC will try to reset the meeting for next weekend.

11/17/05 – TTC called Grady today to confirm this evenings work with Triton and the 3-way valve changeout this evening. Pat and Matt from Triton will be onsite this evening about 11:30 p.m. for this work. Mike Jackson met with Pat from Triton today and went over which breakers will be shutdown tonight to turn the AHU’s off for this work. Matt will take care of the controls for this work this evening and if anything doesn’t work the system will fail into the heating mode for now through manual settings. TTC called the AO Smith Regional Manager, John Bates at 770-841-1305 (off) 770-521-4244 (cell) to discuss the return of these boilers to the factory, I had to leave a message on his voicemail. TTC may stop in tonight to review the work in progress.

11/08/05 – TTC called Hughes supply today trying to get authorization to return the unused water heaters. We still have not been able to talk to the regional representative.

11/03/05 – TTC has been talking to Triton and Hughes supply locally to get authorization to return the boilers to the factory and work on the restocking fee. Gary Tedesco at Hughes has been putting in calls to the regional sales person and the new rep in town LIBB. To date we have had no success in talking to anyone of consequence to help up return these boilers. We haven’t even received authorization to return the boilers to the factory yet, let alone handled the restocking fee and this is mostly due to the fact that A.O. Smith has severed representations with Disney-McClane locally. We probably won’t talk to AO Smith until Friday when they are out of conferences.

11/01/05 – The generators were delivered to the site on Monday. They are in place. Cable is pulled but not terminated. Cinergy will provide final inspection later this week. Power may be up and running by 11/14/05. TTC to send out mtg notes today or tomorrow.

10/27/05 – After the construction meeting yesterday, TTC and Triton went over the boiler workings, final hookups, controls and flow settings. We decided to start the boiler today and as of 2:00 p.m. the boiler is running perfectly and producing 140.5 degree hot water at 51 degrees F. TTC will try to stop out on Friday to check boiler over before weekend. Triton is going to verify that boiler turns off when the switch is changed from summer to winter position automatically. We want to verify this to ensure the boiler turns off whenever there is not flow into the boiler heat exchanger.

10/25/05 – The new boiler has been shipped. It has arrived in Fairfield at the FedEx terminal. It should be delivered this afternoon the Comm Center. Triton will be there to take delivery of the boiler and begin the install of the new boiler. TTC will help coordinate the install as needed.

10/24/05 – TTC emailed the whole team today reporting the following about the revised boiler design.

I want to document all that has happened on the boiler plant since Friday in this email.

I have decided that there is no “best” way to use the AO Smith non-condensing boilers at the Comm Center. My discussions with the factory, who have been very responsive, still have not offered a solution that is easy to implement or easy to maintain. The controls would be cumbersome and the energy usage would go way up since the boiler plant would have to run all year long once the heating season started. Short cycling could not be avoided without the introduction of a storage tank which was never part of the project in the first place. I am not sure what the factory was thinking when they told me this boiler could work with its bypass pump back during the design phase of this project, but the final word from Kevin Binkley at AO Smith is that it cannot do what I am asking it to do in its current design.

It is my opinion that the BEST and the CORRECT way to design this dual temperature system is to use a fully condensing boiler just like Alternates #1 and #2 in the original bid and my original design. This fully condensing boiler is not subject THERMAL SHOCK like other boiler and the STAINLESS STEEL HTX is not subject to corrosion like a standard heat exchanger causing the premature failure. This is accomplished by providing a STAINLESS STEEL heat exchanger with the boiler as with the KBN-500 boiler by Lochinvar. The boiler that I am now having Triton provide for this job is a Lochinvar KBN-500 boiler, Knight Model at 90.3 efficiency with a fully modulating burner with 5:1 turn down ratio, Energy Star qualified, ASME stainless steel heat exchanger (12 year limited warranty) , direct vent with sealed combustion (meaning PVC vented), direct spark, 0-10 VDC input for burner control, alarm contacts on any failure, 4″ air inlet and exhaust vent and low water cutout.

Other design notes: These boilers are rated for 50 gpm max and our pumping system is sized for 80 gpm so as it was originally intended the boilers can work in unison to meet supply temperature or one boiler can handle the whole load if needed but the water flow should go through both boilers all the time unless you have to isolate one for maintenance and at that time, the bypass should be opened if the 2nd boiler is going to be offline for a considerable period to keep the internal flow from getting too high in any one boiler. We will manually open the bypass partially while we are in one boiler mode on this project – your heating loop will still get plenty of hot water to keep the building warm in this temporary arrangement.

For the time being, I am going to have the hot water loop maintain 180 degree F until all the controls are installed and ready for operation with both gas boilers and the electric boiler in the plant (the second gas boiler should arrive on or around November 1st), the electric boiler is already here but there is no 208 Volt power for it yet. Each of the new gas boiler are going to have a 3/4 tygon tube that will discharge a little condensate into the existing floor drain the boiler room whenever they are running. The condensate discharge from these boiler is safe to the plumbing system and should have no “ill” effects on the drainage of the building or the floor drain in the room.

The new control system will monitor the dual temperature water loop temperature so that when you switch from winter mode to summer mode (140 degree supply to cooling 45 degree supply) instead of waiting three days for the loop to dissipate heat, the boilers will be turned off but the heating hot water flow will continue through the boiler system and out the building through the air handlers discharging all remaining heat from the DTW loop into the space until the loop reaches 90 degrees. At that time, the 3-way valves will changeover and go to cooling. This is a strategy that should be used with 2-pipe systems that often isn’t because it will allow you to get to the cooling cycle must faster than usual. The boilers should never be “on” without flow going through the heat exchanges – that is requirement of the factory. Inlet water temperature and water PH is not an issue with the stainless steel HTX. These boilers have intelligent controls that do everything the original sequencer was supposed to do and they communicate directly with each other in case of failure in a master/slave arrangement.

And finally – ONE KBN-500 BOILER will be on site on Tuesday. It is being shipped directly to the Comm Center from Nashville, TN today for the project.

That’s it for now. I plan on being out there tomorrow after the boiler arrives to work with Triton on installation, but I do not plan on being there today as originally intended because we are not setting the electric boiler in place at this time. I am not calling AO Smith about the 3rd party UL licensing at this time either.

The temperatures are supposed to stay in the mid 50’s all week with low’s in the mid to high 30’s so I am working to get this boiler online tomorrow or Wednesday.

I will give you another status update later today or tomorrow as more information arrives at my desk.

Kevin, Mike Jackson would probably be very interested in having all this information, please forward it on to him if you deem it is good info to have.

10/18/05 – TTC has contracted Lochinvar for more information on the “Knight” series condensing boiler to take care of problems at the Comm Center Project. TTC will call Kevin Maue to discuss results of speaking with AO Smith about DTW issue and will explore possibility of installing electric boiler now in Blr #1 equipment pad to alleviate any boiler issues due to cold weather. This may be the only viable option if we switch boiler types.

10/14/05 – TTC is working closely with AO Smith to get the control of the boilers correct before they are started at the site. Condensation and control is a huge issue.

10/06/05 – Grady reported today that the gas meter pad is being poured on Friday, the electricians have power to boiler #01, the gas line should be hooked up and meter placed by Monday, October 10. There will most likely not be boiler operation until that time. Triton is meeting their controls company on site Thursday afternoon for temporary hookup of boiler #01 to existing summer/winter control switch. It will remain hooked up like this until the new controls are put in place the 3rd week of November. This basically follows the original scheme except that we wanted boiler #01 operational by 10/01 with 10/15 as the drop dead boiler startup date. ICS contacted blacktopping company to resolve the roadway hump from the horizontal boring. This will hopefully mitigate the problem we are having with the roadway bump.

10/05/05 – Const Mtg 07 has been distributed. TA discussed shaving the roadway down to reduce the hum but that is not an option. TTC and TS are still working on louver details. TTC and Grady are trying to get boiler #01 online by Friday or Monday at the latest.

10/04/05 – Motorola confirmed that we just need to provide a ground rod from each generator to grade. No additional grounding ring or grounding methods are required for this building. ThermalTech will advise the contractors and send out the meeting notes later today including this new information.

10/03/05 – Motorola gave us an answer about the building ground. The new building requires a grounding ring or a separate ground rod. TA is currently investigation this item for the County.

09/28/05 – Const Mtg 07 was held on site. Several major issues surfaced that need to be addressed by ThermalTech and the Owner. Motorola is going to require additional grounding on the building metal (TA to investigate), Boiler #1 must be online by October 15th and the sooner the better (Triton to provide a 2 week schedule to accomplish this), gas meter pad has to be poured and set in place and tested before boiler can start, backfill must be completed, boilers are seismically braced yet.

09/23/05 – HamCo was required to sign an IBI temporary electric meter release stating that electric work is ongoing at the site. Greg Wenz stated he would take care of this for IBI. ICS sent TE the letter and we passed it along to the Comm Center.

09/22/05 – This week we have been working on scheduling since the generators are very late. We have also been working on louver details with Tom Speer and Triton as they are changing heights and design. TTC faxed over information to TS, GR and KM for review and approval. Slabs have been poured on site and work is ongoing.

09/14/05 – Triton reported that the pumps will be arriving later in the job rather than earlier. The pump inertia bases will sit a new housekeeping pad that will encompass both of the pumps and may surround the existing pump pad. All new anchors will be into the new housekeeping pad. JB Schmitt turned in payapp #2, TTC will deliver to Kevin at Wednesday’s meeting.

09/01/05 – TTC, Mike Cavanaugh and the County are trying to coordinate sending the demolished chiller to New Orleans for the relief effort. TTC sent out Const Mtg 05 notes to all the team members and TA must talk to Buckeye Power about a late delivery schedule. Buckeye Power reported that generator will be here mid-October but Vic will talk to factory and get back to us mid next week.

08/29/05 – TTC stopped at the site. The foundations are poured. A box was left for fuel oil and electric. Apparently, the electric had an issue with IBI and they will need one more underground inspection before acceptance. JC Schmitt worked diligently to get foundation in before Tuesdays rainstorms. TTC approved payapp #01 for JC Schmitt and #01 for ICS. TE has not received a payapp from Triton services yet.

08/17/05 – Const Mtg 04 today. We discussed and update the schedule quite a bit. JB Schmitt can still meet the anticipated schedule based on today’s schedule modifications. The CM # 04 notes were sent out for review. Triton brought Ketchum & Walton out to the site to resolve the gas line mounting issues that ThermalTech noted on the submittals. It was agreed during the meeting to allow the gas piping to be routed on the backside of the building wall at the parapet level of the rooftop. Triton went on to say that won’t change the permit submissions and it will still met seismic requirements. The County preferred the gas line to stay routed above the rooftop as it was designed on the drawings. Kevin and Terry are to check with County Examiners on releasing part of the permit set next Tuesday. TA has to answer an RFI noted in the meeting minutes for conduit inside switchgear on Citadon. TTC will send out an updated schedule this week.

08/16/05 – Construction Meeting # 03 is finished. TE check on permit progress. TTC talked to Disney McLane about requirements for electric boiler and told them it is only for heating hot water and its working pressure is 60 psig and it should have an output reset schedule of 0-180 degrees F/60-140 degrees F. Triton turned in two RFI’s to Citadon that TE is trying to resolve. We are trying to get more information from Buckeye power for answers. TTC will send out meeting notes and remind contractors of the Wednesday meeting.

07/21/05 – Construction Mtg 02 held. Triton to make pump tie-ins overnights and allow Geiler to do chiller tie-ins as well. Seismic calcs are not ready. ICS provided a checklist for consultants to fill out for this job. TE said they would try to get it back on Thursday. TE will answer all the questions they can. TTC will type of meeting notes on Friday for distribution. Tom Speer reported that the county is going to required 6 stamped stets. TS will have Ohio Blue make sets and send to TE for stamping. TE will return to Tom for permit. Schedule was discussed and a mid August start date on the new buildings was agreed to without a schedule slip. Triton should begin excavating next week.

07/12/05 – Construction Mtg 01 distributed. Work has begun. Seismic Calcs are behind. Triton schedule is slipping. TTC to supervise and get Triton on board and up to speed. Electrical equipment has been ordered and should arrive in late August. TTC to coordinate valve installation at site soon. TTC emailed JB and Speer about missing GC submittals. TTC emailed Triton about getting back on schedule and tried to setup a field trip for Thursday or Friday of this week. TTC emailed Grady to setup a field trip for controls and site work.

06/0605 – Pre Construction Mtg notes distributed.

06/03/06 – Electrical submittals are in the works. General submittals are uploaded to Citadon.

05/26/05 – Pre Construction Meeting at Site.

04/22/05 – All contracts arrived by 3:00 p.m. TTC will review and have to Public Works by 5:00 p.m. hand delivered.

04/21/05 – Pre Award Meeting is complete. Bid Tabs are accepted. Contractors have contracts and they are due back to TE by Friday at Noon. TE to deliver to KM by EOB on Friday.

04/19/05 – TE setup for Pre-Award meeting on Wednesday. Allgeyer is pushing Citadon for the whole project.

04/06/05 – Cinergy doesn’t have bid numbers to the vendors yet hence causing a bid extension of one week to the project. Addendum 02 was distributed. PDF

04/01/05 – Addendum 01 was distributed for Project. PDF

03/23/05 – TTC and HamCo Facilities visited Glen-Este Middle school to inspect a Fulton Boiler application installation. Basically this boiler has been in service for 7 years with little or no maintenance at this site other than the changing the spark plug. Turton showed the boiler, explained that it was solid, that it pulsed, had very few moving parts, and could keep a facility at a solid temperature no problem. Facilities has heard that Fulton are maintenance headaches and that parts are not kept locally. Jim Turton of Ballenger told us that all those parts are kept locally in his office. TTC added that the statement that everything was proprietary is certainly not true because the local controllers are standard Honeywell and the gas modulation valve is standard Honeywell and the only things that TTC saw as special could be the fireye which is a Fulton model of a Honeywell controller and the gas pressure switches but basically everyone’s are proprietary anyways. Facilities called back to inquire about the Weil-McClain Ultra series boiler but TE stated that max btuh is 310,000 so that boiler is too small and more residential grade boiler. Lochinvar Intellifin has built in recirculation loop but their smallest boiler is 1,500,000 which is 3x too big but they have a 14:1 turndown ratio but using them would mean the boiler is going to spend most of its life in the 20%-60% firing rate. TTC called the AO Smith factory and the local rep Disney McClain and discussed other options. Apparently the Legend 2000 boiler series IF it is ordered with the bypass option can handle cold water inlet conditions.

03/22/05 – TTC authorized Ohio Blue to use AIA documents to insert into spec book and then send to all personnel, later TE delivered the electronic forms for xeroxing to Ohio Blue for future use. SBO delivered a CD for purchasing to upload the entire project to Demandstar. This was completed.

03/21/05 – Bid Set is at Ohio Blue. TE delivered in morning.

03/10/05 – 90% Review Set and Review Meeting at Comm Center. TTC needs to find 2 more Pulse type boilers for bidding. KM requested updated Cost Estimates, Comm Center agreed to one or two 8-hours shutdowns for new 3-way flanges and Comm Center agreed to a 4-hour switchover on rented generator to go to new power from new source and new generators.

01/26/05 – TE sent out DD dwgs for review in anticipation of this Friday’s Meeting with the client.

12/27/04 – TTC and Kevin Maue discussed in detail the savings associated with a non fuel oil boiler and chimney. Kevin is going to take the scheme to Facilities for approval and give TE direction by end of week. Kevin is wondering where the Schematic Design documents are and would like to see them soon.

12/24/04 – Schematic Design Due. TTC turned over cost estimate for revised boiler design using 2 gas boilers and 1 electric boiler.

Communication Center – Electric Building and Boiler Plant Upgrade Read More »

COMMUNICATION CENTER – LOCKER ROOM EXPANSION

03/15/07 – TTC hand delivered closeout documents to MD at Room 468 closeout meeting. This project is complete.

03/02/07 – NR left another message with A&M Contracting letting Mark Molinaro know that the form he mailed is a draft copy and not acceptable. NR mailed that actual form to the contractor so that all they would have to do is sign and stamp it. TE is still awaiting this form.

02/19/07 – A&M Contracting has one form left to turn in then project will be complete.

01/31/07 – NR left a message with A&M Contracting concerning the close out material. TE is still awaiting all documents from them in order to close out this project. J.B.Schmitt has delivered all necessary documentation for the general contractor of this project to be complete.

01/22/07 – The close-out meeting was held last Friday, January 19. All of the items on the punch lists have been completed. The only remaining open item is the as-built drawings. The are set to be delivered this week from both A&M Contracting and J.B.Schmitt.

01/17/07 – Change order #3 for A&M Contracting has been voided. Change Order #2 has been rewritten to show the usage of the allowance taken off of the total change order amount. NR sent the new change order document along with the Allowance Clarification #1 to Mark Molinaro at A&M Contracting with instruction to return the signed documents with the adjusted final pay application.

01/16/07 – NR spoke with J.B.Schmitt about the locks. The locks were installed at the end of last week. A meeting has been scheduled for Thursday at 2:00pm. The attendees include Tom Speer, Mark Donnelly, and NR. This is intended to be the final walk through before closing out the project.

01/10/07 – TTC & NR typed the JB Schmitt deduct change order for this project for closeout.

01/08/07 – NR spoke with J.B.Schmitt this morning. The locks were sent from the factory on the 2nd of January. The estimated arrival is 3-5 business days. The locks should be installed by Wednesday.

01/02/07 – The locks were delayed due to a mix-up at the factory. They are due to ship today and will be installed as soon as they arrive. The walk through with ThermalTech and Mark Donnelly of Hamilton County of Facilities has been postponed due to this delay. The final pay application from A&M Contracting has been received and will be forwarded to Hamilton County on January 3rd.

12/22/06 – The painting of the existing wall and all punch list items have been completed. The only work remaining on this project is the installation of the locks on the lockers. The locks were shipped from the factory on December 21 and will be installed by J.B.Schmitt as soon as they arrive on site. The final pay application from A&M has not been received. The previous application was returned due to the deduction of the remaining electrical allowance not being taken off of the original contract amount. NR left a message with Mark Molinaro letting him know of this discrepancy and has not had a return phone call from him. I will contact A&M again the first week of the new year to ensure they understand what needs to happen.

12/19/06 – There is a painter scheduled to be on site today to finish touching up the existing work and to paint the existing wall behind the vending machines. The locks for the lockers remain to be delivered as previously scheduled.

12/14/06 – J.B.Schmitt said that the locks are scheduled to be delivered on December 21st. They will be installed shortly after they are delivered. The wall is scheduled to be painted next week.

12/12/06 – It has been decided that the existing wall shall be painted to match the new wall color. This will be paid for with a portion of the remaining allowance. Keyed locks for the lockers (including 2 master keys) have been ordered and should be installed before the end of December. This will also be paid for with a portion of the allowance. The allowance clarification has been signed and submitted to J.B.Schmitt and will be signed and forwarded to Hamilton County, Attn: Mark Donnelly.

12/6/06 – The architectural punch list has been completed. The items on the list have been turned over to Mark Donnelly for review. Mark said he had nothing to add. There is an issue with the color of paint on the new wall vs the existing color on the adjacent wall. This has been resolved by having J.B.Schmitt paint the existing wall to match the new wall. Also, there has been a request for key locks to be installed in the lockers. These locks are to be ordered and installed by J.B.Schmitt. I am awaiting the paperwork from Joe Kihm so that I can process the allowance verification.

12/01/06 – NR visited the site. The lockers were being installed during the visit. The electrical punch list is complete and there are no open issues. There are a few minor general issues that have been discussed with the architect. These issues should be taken care of today and Monday. The project closeout meeting date is Wednesday, December 6th.

11/30/06 – Lockers have arrived on site and will be installed tomorrow. Joe Kihm of J.B.Schmitt will have his crew stay until the installation is complete. N. Richmond will be on site either tomorrow afternoon or Monday, December 5th to do the punch list. If the project is complete per Hamilton County expectations the close-out meeting will be scheduled for next week. NR will be in touch with everyone involved to schedule this meeting. J.B.Schmitt sent NR an allowance clarification which was for the door closer. This clarification was put in the Hamilton County format, signed, and sent back to J.B.Schmitt to be signed and forwarded to Hamilton County Facilities Attn: Mark Donnelly.

11/10/06 – Lockers due to be delivered early next week. Project is on target to be completed before scheduled date.

11/03/06 – Electrical and above ceiling inspections were completed this week. Awaiting arrival of lockers to complete project.

10/27/06 – Painter has been on site and still awaiting delivery date on lockers.
10/24/06 – The block wall and door frame have been installed. The concrete basins for the metal lockers were poured yesterday. The painter will be on site either later today or tomorrow. Joe Kihm of J.B.Schmitt is talking to the locker vendor to see if he can get the arrival date moved up to the end of this week or early next week instead of waiting until the week of November 12th like the schedule shows. If he can get this done it will knock a couple of weeks off of the finish date. Nick Richmond left a message with A&M Contracting and will relay any information he gets from them when they call back.
10/06/06 – Nick Richmond spoke with A&M Contracting this afternoon and was told by Mark Molinaro that they were on site today working on re-routing the conduits and circuit as described in the change order. The paperwork for the change order has been signed and mailed out. Although we have had a short delay while waiting on the door frame we have moved ahead with other areas on this project. I will keep you informed with updates as I receive them; or call and bug the contractors to get them.

10/06/06 – The EC has been on site re-routing the conduits as described in the change order. Project is moving along despite the slowed delivery of door frame.

10/02/06 – I received a fax from the EC on this project asking for clarification on the existing receptacle that was to be relocated. The receptacle is fed from conduit routed under the slab. The conduit also feeds vending machines down the line. I instructed Joe Molinaro of A&M Contracting to pull the wire back to it’s source and cut the conduit flush with the existing floor. The new receptacle will be re-fed from overhead utilizing the same circuit. The vending machines are also to re-fed from overhead. I told Joe to send me a change order for the added work.

10/02/06 – I spoke with J.B. Schmitt about schedule. Joe Kihm informed me that the door frame is a special order item and will take about a week to come in. I instructed Joe to continue with demolition and get everything completed that he could while waiting on the door.

09/25/06 – Work on site began today.

09/22/06 – Scheduled to start 9/25/06. Drawing have been forwarded for fire alarm permit.

09/15/06 – Permits have been obtained. Construction should start 09/25/06

09/11/06 – Received schedule from J.B. Schmitt. Schedule did not follow contract dates. I made a phone call to Joe Kihm at J.B. Schmitt and reworked the schedule. Joe said he will fax me a copy of the new schedule tomorrow. I also contacted A&M about the electrical permit and background checks. Mark Molinaro of A&M said that both issues will be taken care of this week.

09/08/06 – Awaiting scheduling from J.B. Schmitt.

05/22/06 – Bids came in on this project. JB Schmitt won the GC bid. A&M won the EC bid. Contracts have been written and given to TA for review.

04/05/06 – Final drawings and specs are being completed right now.

03/10/06 – TTC did not make the meeting but discussed with Mark Donnelly the need to not do any HVAC work and incur code changes when the HVAC system is slated for an complete overhaul in the coming year. We both agree that letting the GC move over the one diffuser that might interfere with the new wall is the best course of action for the mechanical work.

03/03/06 – Kickoff meeting slated for 03/10/06 at the Comm Center. TTC & TA will attend.

COMMUNICATION CENTER – LOCKER ROOM EXPANSION Read More »

COMMUNICATION CENTER – HVAC UPGRADE 2006

03/12/08 – TTC modified the final punchlist again and sent it out to JCI and Triton along with the final as-built drawings TEI had on the project. TEI email Banta to see about the final as-built drawings that were received on this project from Banta on this job. Punchlist 3 & 4 uploaded to the web.

12/19/07 – TEI called for an owner witnessed fire alarm test for MJ. Banta said they could provide this. JCI won’t pick up the fire alarm but Facilities can see how the unit will go into alarm when the smoke pulls out. John Sanders he will work on finishing all the work on this project and stop by today. Boiler 2 had a loose ignition wire and Ken Morris fixed that last Friday but will send the service ticket to the County.

12/17/07 – Triton and JCI were on site last week trying to closeout the project. Today MJ reported that smoke detectors appeared jumpered out on the system and one was missing. Banta said they know this not to be the case when they tested them and will send Ed Ginter over to verify operation of the smoke detectors. TTC forwarded the Dowtherm white paper to MJ & KM showing the 30% provides burst protection down to -31degreeF so 30% ethylene glycol should be okay.

12/12/07 – JCI was onsite today to provide final training on the DDC systems on the project. TTE showed John Sanders some items that were not complete on the project. The freezestats were un jumpered but now the units are going to have trouble running through the cold weather because of the freezing cold air coming into the unit in the economizer mode. JCI reported that the freezestats cannot be set below the 35F factory setting but TTC will check to see about another setting or different equipment. The glycol mix did not prove to be protected down to -20F nor does the concentration seem to be at 30%. The Chardon lab chart says 30% will get 5F for this system. TTE to reconcile.

12/04/07 – TTC has been working with Triton & JCI to get the project completed and commissioned. TTC told KM today that he believes all the contract work is complete for all contractors and that we can move to just warranty issues. TTC asked JCI to schedule final training on DDC system for this Friday but this date is not confirmed. TTC has scheduled the final back punchlist visit for this Thursday. TTC contacted Banta about missing information in the O&M manuals such as warranty letter, contact info and all closeout documents. KM asked for final Banta payment today and TTC called Banta and told them to send both final payapps to TEI today for approval. TTC subsequently spoke to Banta about final change order cost (3 changes listed below) and update the website. Banta appears ready to send over the payapps for this job. TTC reported all of this to KM. MJ has asked several times about the glycol % concentration in the loop and TTC has sent he spec required 30% back to KM each time. This is what TEI told Triton to buy and they provided premixed glycol and put it into the system. Banta sent the payapps over and TTC signed them and sent them via City Dash down to KM at the CH.

11/16/07 – TTC issued the second mechanical and control punchlist today to Grady and Brett for immediate completion. PDF

11/13/07 – Tim Centers called today to report that Habegger will be on site tomorrow to check the toggle position of the incoming voltage. If we set it to 208V he believes that a lot of our over starts will go away and our long wait time in the summer for chiller restarts on power loss will also be very diminished. He was still willing to meet Facilities at the site to discuss the chiller programming next week. KM sent in many questions about the chiller plant and programming and TTC forwarded these to JCI for answers. Most of the final details lie in the alarm programs which JCI is willing to extend to 5 minutes to reduce alarm reports on the pumps, chiller plant and boiler plant. TEI has asked that low level alarms be removed from AHU-3 because it is scheduled off almost all the time.

11/02/07 – TEI sent the Engr Change Order to Kevin for finalization. MJ emailed today to report the compressor are banging on/off way too much. TTC has not witnessed this under the latest sequence and the timing seems to be about once every 15 minutes in the field. We will however bring Carrier over in 2 weeks to review with owner.

11/01//07 – Triton finished up all the paperwork and delivered it to TTC at TEI. TEI sent to Kevin via City Dash. The O&M’s were delivered but Grady and TTC will send to County for testing. All final inspections have been passed for both Building, HVAC and Seismic.

10/17/017 – TTC sent out a large email outlining the items left at the CC. Grady reported that final balance reports will be here by Friday. Some mechanical work remains like OA boots, insulation and inspections but the project is almost complete. It is just programming that needs to be ironed out at this point.

10/01/07 – TTC complete 2.5 days of commissioning at the Comm Center. JCI was not ready for CX and TTC could not back check the reports they filled out. We worked out many issues with the boilers and air handlers but still have more issues to resolve. TTC asked CC about leaving the ladder and door arrangement as it is right now after the ladder was moved. TTC contacted Triton and JCI about finishing the project ASAP. TTC requested trend reports for verification of working systems.

09/24/07 – Kevin reported the room was overheating much of Friday and JCI was on site today attempting to speed up the sequences. Kevin said it was 73 F which I don’t consider overheated but it will shake out in the commissioning reports. TEI is scheduled to back commission the project starting Tuesday afternoon. TTC approved and sent out Triton payapp 5. Cousins inquired about their payapp 3 which TEI said they sent to PW in August. Banta has never billed us. TTC asked for the new receptacle for the water softener again.

09/19/07 – TTC sketched up the new control scheme for Return Fan and Relief Fan operation for AHU-2. TEI sent the sketches to JCI, Triton and the County for implementation into the project.

09/12/07 – TTC performed the mechanical punchlist yesterday. Most equipment looks as though it is in very good shape. The insulation on AHU-2 looks fantastic. TTC wants to submit the punchlist to Triton today.

08/28/07 – Training is schedule for tomorrow. The boiler boards did not arrive yet. Denny said maybe tomorrow. Airflow stations are not in yet but they are being ordered. Triton updated their work to do list and TTC sent it to KM and TM. Triton asked for written confirmation on moving the ladder in the storage room.

08/23/07 – KM stopped by this morning and reported that space temps were 72-75 but humidity was up in both areas. Trend data shows humidity rises during shift changes. JCI said they are providing a laptop for interface into the JCI system on site and we discussed agenda items for training. A new boiler control panel board must be ordered to give the boilers a firing rate contrary to what Denny Lammers told me on the phone yesterday. The new boards will be here on Monday and installed immediately by Scott Black. Denny Lammers called to say that the comm ports on the boards in the boilers at the Comm Center have been shorted out and new ones will have to be ordered. The should be here today or tomorrow.

08/22/07 – KM stopped by this morning and humidity was up at 9am but came right back down after the doors were closed and the shift change was finished. KM asked for a trend point to track the humidity to see when it is rising up so high (66% in Admin area). The 911 center was fine but Greg said the temp was 72 even though the stat was set at 68. These are averaging stats and this makes sense. Each stat can be overridden with its control knob. Bill thought his office was a little stuffy but his temp was 72 while the other office was 68 in AHU-1 zone. We could change the setpoint of this space down to 70. TEI asked for a copy of current sequences to be given to the owner. Training has been scheduled for next Tuesday at 8am. Denny Lammers confirmed that the boiler firing rate can be fed directly to the boiler with a 0-10V signal from the JCI system. The DDC system will also select the lead boiler and let the County manually rotate the boilers. JCI said that graphics might be installed by today on the Comm Center computer.

08/21/07 – KM called after he stopped out on site. Temps are good. JCI has everything programmed in automatic at this point except the boiler control which is being finalized and worked on with Denny Lammers. Greg said everything was delightful and Triton was working to finish everything up.

08/20/07 – TTC stopped at the site over the weekend to adjust temperature controls because the space was too hot and too cold and humidity was up. TTC sent an email last Sunday outlining all that was done over the weekend to make the systems work in a more automatic control.

I am writing this to outline what all happened at the Comm Center over the weekend and since last Thursday when JCI uploaded the new programs. You may need some of this information to release overrides when you program the system in its totality on Monday (tomorrow).

We have had a lot of overcooling since the new programs were put into place last Thursday and the only real control that I know we have is to manually adjust the chilled water valve to compensate for space temperature. Obviously this is not a good solution because we either overcool overnight or undercool in the morning. There is no one setting to keep the building temperate all the time.

On Friday, Kevin Maue went to the site and made some changes because the main area (AHU-2) was overcooling. With a little investigation, I believe we found that the supply air reset temperature was again programmed backwards meaning that as the space got cooler the discharge air temperature got lower. Mike Jackson noted this on the original JCI control submittals and it was caught again by John at JCI who went into the program and changed the supply air reset schedule when he was there one day according to a voicemail from Tim Myers to me. The headings on the JCI sequence of operation are backwards and the space temperature numbers are labeled as discharge air temperatures of the unit and vice versa. I believe when the new program was uploaded we went back to the old wrong way because the space was 64 degrees on Friday and the cooling valve was open 100% the humidity was below 55% so I don’t believe the unit thought it was in the dehumidification cycle. I had Kevin back the cooling valve down to 25% for the day. In the short term, this works but not overnight when it cools down.

On Saturday when Tom Rice from Triton was on site the space temperature rose to 76 degrees and the humidity was high. I stopped in about 1:30 p.m. and opened the cooling valve to 50% and drove the space temperature back down before I left. I also checked the supply air fan and return air fan speed which were okay but were manually set at 40 Hz and 30 Hz. I told and showed Tom how to adjust the cooling valve back to 25% before he left to prevent overnight overcooling (I believe he forgot to do this).

On Sunday, Mike Jackson called me at 9:30 a.m. to say it was 60 degrees in the space. I got the message at 4pm and drove to the Comm Center and arrived about 4:30 p.m. They reported that the coldest it got was 64 degrees and I found the chilled water valve still open at 50% which explains why it was so cold. I believe I was the only one to come out on Sunday to address this problem. Figuring this isn’t going to work overnight again, I decided to see if I could get the boiler system running on manual while I continue to wait for the final controls to be installed. On the boiler control panel it appeared to be locked out on outside air temperature. I got the user manual off the table, entered the passcode, browsed to the OAT disable point and raised it to 100 degrees F. I went into the AHU-1 room and put the hot water pump in hand. I check all the HW valves and they appeared to be open. I went to the front end and commanded the boiler on. It went into alarm. I walked back to the boiler and saw the LCD said LWCO lockout. I checked the new recirculation pump and it was off. I went back to front end and commanded the boiler pump # 1 on. I went back to the boiler and hit the reset switch on the boiler and it post purged, pre purged, ignited and started making hot water. I check the AHU-2 conditions and the space was still too cold and the humidity didn’t seem to be getting any lower either. I commanded the OA dampers closed and I finally commanded the cooling valve to 90%. After that I saw the heating valve start to crack open so I figured it was responding automatically to the space conditions. After about 45 minutes, the AHU-2 unit had 72 degree space conditions and 51% RH AND IT SEEMED TO BE OPERATING IN A SOMEWHAT AUTOMATIC SEQUENCE because the hot water valve kept stroking based on space conditions. I am hopeful that this will prevent overcooling/overheating until tomorrow when our contractors will be back to finish up.

I couldn’t get the hot water valve to open automatically on AHU-1 so I left the CHW valve at 20% chilled water position. The SF VFD is not reporting any speed and the VFD is actually in the hand position at 35%. The RELIEF fan is still OFF the way it should be. I closed the OA dampers on this unit too for now.

The AHU-3 unit cycles on about every 10 minutes. I don’t think that is necessary in the final program but we will see if it acts the same when we are finished programming it.

One thing is for sure, I am not comfortable, nor do I believe, that I should be the one making these changes in the field to this equipment. We, as a team, have to get this job completed immediately. What is it going to take to wrap up all the controls except for the air flow stations? Please do that immediately. If Denny Lammers has to come out to reprogram the boilers and coordinate with JCI, why hasn’t he been out there yet? We have given him work and spec’d his boilers on jobs in the past year. At the MRDD I accepted three of these boilers this summer. Please tell him that I expect him to be at the Comm Center on Monday with JCI getting the heating system running in automatic mode per our latest sequence. WE have to get this system running in automatic mode and eliminate these wide temperature swings. The 911 center is a 24/7 operation. Please keep coming out each day until it is finished.

Here are other comments that I have from the weekend:

Triton worked on Saturday and I saw Tom had the new water line routed from the basement to the upstairs bathroom for the humidifier. I don’t know if he got that finished as I left before he was done.
The water softener was not there. When is this coming in?
The insulation on AHU-2 looks worse then even. Now there is a big air pocket bubble where the ductwork isn’t sealed under the insulation and the air must be pushing the insulation out. This is near the top elbow going into the building. The insulation job on this unit is not acceptable. Rip it all off and replace it with the same type that I have the MRDD building. Please have them do a neat professional job when they replace this stuff so there will be no question about accepting it on the punchlist.
The supply air temperature on AHU-1 has a minimum setpoint of 55 degree F on one of the variable near the bottom of the JCI points list but the DAT was 53 degrees today. How can that be?
The AHU-1 VFD speed says 0% but the unit is running at 35 Hz in the Hand position. Is this a status point or a signal we are feeding the unit? If the unit is occupied as it said it was why is the SF speed at 0? I could not figure that out.
Why is the OA temp unreliable? Why is it reporting different temperatures on AHU-1 and AHU-2? One said 75 and one said 95. Don’t we have a global OAT sensor?
The hose bibbs are complete. One was rebuilt, the other is new.
How come we don’t have manual overrides at the JCI control valves for all coils? I have to check again but I am almost positive that GD always gives us this option in his specs. I could not find anywhere on these valves that I could do that.
When are we going to get the t-stats with overrides in the space? Maybe they are there – if so, just let me know. It would be a way for day shift/night shift to make small adjustments to setpoint.
When are the new diffusers going into the Radio Room area?
When are the going to insulate the remaining basement ductwork?
When is Tom going to cap off the abandoned ductwork? Reroute the existing?
Any word on why the chiller seems to take 15 minutes to restart on power failure? Tom said the other day he was just scrolling through the menus when it came back on full time. That is kind of what happened the other day too.

And finally, Tim I was glad to hear that the premix glycol is here. Please give me the change order cost to put the thermometers on each side of the coils like we discussed in my email. I want that work done ASAP as well and do it when the system is down for glycol. Troubleshooting will be a lot easier when those thermometers are installed. We don’t want to commission anything until the system has glycol in it because the system efficiency changes.

08/16/07 – Duke had another power outage at the Comm Center today. Triton & JCI were onsite. Tom Rice did not about the chiller not having to be locked out during generator operation any more. MJ contacted TTC and TTC emailed MJ and KM back about the situation explaining Tom just hasn’t read the meeting minutes from our control meeting.

08/13/07 – Today the spaces are comfortable. Triton came in over the weekend to work on the relief damper for the AHU-1 relief fan. They turned and left off the return fan to the unit. They could not confirm when JCI was going to finish their work on this job. TTC & MJ turned the fan back on and slowed both the supply and return back down to 35% and 25%. TTC issued meeting #12 today to Triton and the Owner. PDF

08/08/07 – MJ reported some cooling issues in the Admin wing. JCI and Triton check onsite for problems. TTC sent the following email to surmise the happenings:

I got a call yesterday that the Admin offices are warm at the Comm Center. Mike Jackson reported that the RF was shutdown, the cooling valve was only at 20% open and we are not sure how fast the SF is running. MJ stopped by for me and put the RF back into 50% speed, opened the CHW valve to about 50% and the space started to cool down. I called JCI and dispatched a service tech to the site this morning to check over the controls and they reported that the space and the trend data showed the space setpoint temp was set to 73 degree F and that the AHU was keeping that temperature okay. We had them reset the unit down to 70 degree F before they left. The space still seems warm today by local accounts. I called the comm center and talked to Lisa this morning who said the general feeling was that there was low air and it was stuff and warm. I called JCI and Triton and they agreed to send a JCI tech out to the building again to check the status of the unit and call me back. My goal is to increase the airflow and cool the space down a bit more. I also want to see what the actual space temperature is independent of the temperature sensors (MJ said he might be able to put a chart recorder in the space for me). I also asked JCI what the status of the existing controls are and although they could not say for sure 100% but they did say that the system is automatically responsive to the temperature sensors in the space. Based on the TEI sequence if the space is really overheating, both the VFD would normally be indexed to a higher speed and the SA discharge temp on the unit would be decreased. We do not have automatic control of the VFD yet (that happens next week) but we do have control over the CHW valve. The only reason it is not opening more is that the averaging t-stats in the admin wing are saying that they are meeting their setpoint. The chart recorder to tell us different or I may need to have JCI relocate one of the sensor to more representative are. We will know a little more in a bit and by the end of August we should be under 100% control with everything working automatically.
08/06/07 – Banta reported today that they have finished their punchlist including gate bonding. All documents are being sent to TEI for approval and closeout. Triton continues to work on the airflow monitoring stations for this project.

08/02/07 – Due to another power outage, JCI has to reset AHU-3 again at the Comm Center. They will be out there today to do this work. TTC & KM talked about completing this work ASAP. TTC sent out Electrical Punchlist today. PDF

07/19/07 – TTC called Cousins about Payapp #3 and #4.

0718/07 – AHU-3 had a power outage and would not stay running last week. Banta was able to provide a new conduit and feeder to the unit to fix the problem. Triton gave us a commitment of balancing to being on July 30 and TEI schedule a design meeting on July 25 for controls and owner training. Triton still owes TEI and Kevin Tom’s Work to Do List for Comm Center.

07/03/07 – TTC schedule the DDC meeting for July 12th for everyone to attend. TTC spoke to the water softener vendor about the specs on our new water softener in the change order for the project. Greg Wenz had some questions and comments about the system and power outages which are a problem now but will be taken care of upon completion of the DDC system. TTC reiterated to the County that JCI fully meets the spec and that the equipment is actually an upgrade to what Mike Jackson asked about being in the base bid. There are still some issue to resolve on this project. TTC owes Triton a sketch for the water softener installation and the new insulation scheme for the ductwork in the basement. We are not sure how far the balancers are don with their job so far and we need a decision on how we are replacing the diffusers in the ceiling of the 911 center.

06/26/07 – Tim is on vacation. We are trying to get the project wrapped up. Balancers will be on site tomorrow. Tom Rice is on site doing finishing work for the project. TTC contacted JCI to try to force them to get the project finished on the control side. TTC has a boiler RFI to answer for JCI at both buildings.

06/07/07 – Triton is scheduling the balancers for the main building. TTC is scheduling the punchlist for Friday at 2pm. TTC found payapp #2 from Triton and is going to hand deliver tomorrow morning.

06/04/07 – ttc approved triton’s payapp #4 for comm center. tom rice reported that chiller flow switch is now installed on chiller. fencing is installed but not the netting. gates are up around the equipment. ttc visited site on Saturday morning to check on progress from parking lot.

05/31/07 – All units are up and running. HHW piping is being completed this week. Duct cleaning is finished. Roof exhaust, relief and powered exhauster are installed but not finished. Insulation is not complete. Triton owes me a revised price on minimal ductwork insulation for old HV ductwork. We have not resolved the new diffuser install issue with round necks vs square necks but Tom and Tim are working on that. TEI plans on doing their initial punchlist early next week on site. The fencing is installed and the fabric is getting set to be installed. Space conditions seem to be quite well for the outdoor air temp. TEI issued meeting notes for Const Mtg #11. The next mtg is TBD. Triton submitted payapp #3 and ttc approved and sent to km.

05/17/07 – AHU-1 was shutdown and replaced and turned on today at 1:00 pm. Duct cleaning is schedule to be completed tonight at 10pm. TTC setup a Const Mtg next Wed at 2:30 p.m. Facilities asked about he quantity of isolation valves on the project and TTC said we have one at every unit and a manually s/d on the control valves.

05/15/07 – AHU-1 shutdown & replacement is scheduled for Thursday 05/17. Everyone seems to be on board with the switchover on that day. TTC will confirm with Triton before final shutdown of HVAC-1. Hose bibb change order was processed PDF

05/14/07 – AHU-2 and AHU-3 have been started and are currently running at the building along with the Chiller. We are planning on turning over AHU-1 this Thursday and starting at 6am with that shutdown and rework. TEI has been on site many times over the last two weeks to facilitate the final switchover and changeout of units. AHU-2 was down for nearly 8 hours as the switch took place. JCI has temporary controls on the building for now.

04/18/07 – TTC distributed last week’s meeting minutes. Tim distributed the schedule for the project. The AHU are being set on the curbs today. AHU-3 will have a field erected curb. Const Mtg is this afternoon. TTC has turned in all paperwork for special inspections. Marty Simon said he would review it today or tomorrow and get back to me on it.

04/11/07 – Concrete pour was coordination for today. Kevin check the site yesterday and it appears to be ready. TTC talked to HamCo Inspections today and they still have not approved the Special Inspection part of the permit app. David Puthoff is faxing a sample over to TTC to mimic. TTC distributed meeting minutes with sketches today. PDF

03/30/07 – Triton reported that the units will be delivered on 04/02 at 9am. TE emailed everyone to let them know. Const Mtg 5 was held last Wednesday. Tim Myers was announced as the new PM. Major timing issues were discussed along with the revised schedule which TE will post on the web soon.

03/26/07 – Triton informed TE today that Brian Pastura is leaving the company on Friday March 30. Tim Myers is taking over the PM for Brian on this project. Tim reported that the AHU’s have shipped out of Mexico and should arrive on site this week or next Monday at the latest. TTC will check the schedule for correctness on this situation. TTC contacted Triton and GB Houliston today again about finalizing a change order for the humidifier and getting this piece of equipment on order. TE wants to do this immediately.

03/21/07 – Triton and EAP emailed today discussing RF-1 actuator voltage and damper size. 24 volts and 30×30 was the consensus. Triton to verify. TTC owes 2 const mtg notes to the team and Kevin an explanation about the 2 week scheduling delay in the project. TTC negotiated a revised price from Houliston on the Dri-Steem humidifier. TTC is awaiting confirmation from Triton on the order.

02/19/07 – Last week TEI finished the air device submittal and the EF submittal and sent them back to Triton for ordering. Triton provided an update for the demolition HVAC and plumbing work being completed last week. Tim is now beginning HVAC demo and the duct cleaning is complete in the lower level of the building.

02/02/07 – TEI requested seismic calculations again from Triton (they were due in Feb). Kevin gave Cousins pay application to TTC to approve and TTC sent out an email summary of his field trip with Triton on 02/01/07:

Gentlemen,

My field trip with Triton to discuss ductwork modifications and submittal status revealed several items to share with you. Check my follow up email to this because I want to schedule a regular Const Mtg #04 in a couple of weeks from now. Last Wednesday did not end up as a mtg, sorry for the confusion….

1.) I discussed ductwork changes on AHU-2 (the outdoor 911 unit) and the new layout is going to reduce the downtown when we switch units which is a wonderful thing. We review the unit location on the pad in regards to the interior location and penetration of the wall and distance from the new fence that will eventually be in place. I am really happy with the new layout and approved Triton revised approach for several reasons. 1.) The ductwork routing is simplified. 2.) The downtown between unit changeover is reduced. 3.) The hole in the side of the building is no longer required. 4.) The new AHU-2 can be online while we demolish HVAC-2 and that doesn’t have to happen simultaneously. We are proceeding with the order of this Carrier Unit.

2.) I gave Triton the okay to start limited demolition on HV-1 and HVAC-1 in the basement to the extent that it won’t keep the unit from working but to meet my schedule, they have to start seem demolition of the return ductwork and HV-1 unit.

3.) We have asked for a change order price to raise the AHU-5 condenser up to our new pad level from Triton and will take care of this inside our project budget if the price is acceptable.

4.) The duct cleaning company is scheduled to begin some work in the admin section on 02/12/07. I have asked for this work to be done after hours as the staff is gone at that time and we can judge how loud this cleaning process is going to be before we attempt it in the 911 center.

5.) I am discussing access to the mezzanine with spencer johnson of Cole Russell as I may or may not modify the access door in this project when we are done. I will coordinate that with my architect and the facility safety director (please have steve sears send me the verbiage of what is required IF I decide to put a man door back in the breakroom).

01/17/07 – Chiller sub is 50% reviewed and looks correct. Refrigerant is not as specified in specs.

01/15/07 – After speaking with Majid and Brian at last Friday’s Const Mtg, Triton has provided Carrier Submittals via email for this project. York has lodged a complaint into my voicemail about not being selected and TE has scheduled a meeting with Christian at TE for Wed. TTC will print out the submittals and begin reviewing them immediately.

01/12/07 – Const Mtg with Triton. Concern about equipment and schedule discussed

01/10/07 – Const Mtg was rescheduled to 01/12/06. TTC sent out Const Mtg 01 notes today PDF. Triton called today to report that York equipment is 14 weeks out for delivery.

01/09/07 – IBI permit was not enough for inspection. Banta is taking revised permit app down to IBI to schedule the underslab. Triton met with Banta and confirmed conduit locations up to equipment so that flex tight could be route to the final control locations. Pad pour is scheduled for Thursday/Friday.

01/08/07 – Submittals arrived at 4:45 p.m. last Friday and were logged into the TE system. TTC & TJ are reviewing. The York unit for AHU-2 is not configured correctly and would normally be rejected but we don’t have time for that on this project. TTC to discuss with KM. TEI has faxed IBI dwg review form to IBI for Comm Ctr review for underslab inspection for pad being poured by Cousins.

01/03/07 – Const Mtg 02 was held. Pad pouring were the order of business of the day along with finalizing the schedule. Triton did not have the schedule ready for approval. TTC was frustrated and gave Triton one more week to organize the schedule and ask Triton to take ownership of the project and get submittals into TEI for review.

12/26/06 – TTC and Triton discussed York submittals today. Grady has reported that the factory has already slotted our entire order and that submittals will be here the first week of Jan 07. TEI will review them immediately.

12/07/06 – TA finished electrical submittals. TTC distributed Pre Const Mtg minutes PDF. Triton has to meet owner and TEI on site to discuss pipe routes. Cousin is to provide a change order cost for the fencing on the project.

12/06/06 -Pre Construction meeting was held. TTC to type up notes. Electrical submittals were given to TA. Options for piping was discussed with Facilities about routing more through the building. Building Inspections provided a letter of additional requirements for project.

09/16/06 – TEI is set to have a review set ready for HamCo to review on Wed 09/20. TTC to deliver to County with specs and cost estimates. We are scheduling a review meeting on September 26th.

COMMUNICATION CENTER – HVAC UPGRADE 2006 Read More »

COMM CENTER Underground Fuel Oil Tank Replacement Project

05/05/10 – As-Built not openable by County, need to reduce it to Acad 2008 version.

04/26/10 – As-Built drawing completed. Once we send this to Bert, the project will be complete.

03/22/10 – Closeout documents and final payapp received and sent to County. Roether finished punchlist items and got County approval on work from Jackson.

02/23/10 – TTC issued punchlist to contractor & owner.

02/19/10 – Punchlist field trip.

02/04/10 – TEI is working on the pay application for Roether. They don’t have the papers or the software. Roether agreed to put on a anti-siphon valve on the piping at n/c to protect the new tank from interior leaks. They agreed to do the additional piping on the fuel oil skid per the Addendum. TEI approved the factory mounted deadman system during bidding so that is what Roether is installing. This came up as a concern during the work at the Comm Center this week. Reinstallation work continues.

01/26/10 – Roether has removed the tank and is back on site preparing to install the new tank. Change orders have been submitted. The County will accept the piezo alarm and the heavy duty piping upgrade on the fuel oil fittings on this project. There is no allowance for this work so it will be a change order to the project.

12/31/09 – Permit has been approved by State. TEI requested a project schedule from Roether.

09/04/09 – Contracts submitted to the County.

08/24/09 – Roether won the bid. TEI interviewed them and all seems fine with the bid. TEI is writing the contract.

07/29/09 – Project manuals arrived from Queen City today. The project is on the street for bidding. THP owes TEI an excavation drawing that will have to include in the Addendum on this project. Prebid scheduled for 08/05. Bid Opening 08/24.

07/20/09 – Final design begins for this project. Tim Jones and George Mullins are lead engineers on this project. It is set to go to Purchasing on 07/27/09 for bidding.

COMM CENTER Underground Fuel Oil Tank Replacement Project Read More »

COMM CENTER Lighting Repair

Partner Lead: ThermalTech

02/26/13 – Kick-off Meeting with Comm Center and Facilities Department. ThermalTech to develop SOSS.

03/01/13 – SOSS issued to Bert Watts. ThermalTech waiting on approval and PO.

04/24/13 – SOSS approved and PO issued to ThermalTech. ThermalTech to schedule kick off meeting with Bert Watts to discuss schedule.

06/26/13 – Project currently out to bid with bids due back to ThermalTech on July 2, 2013 at 4:00 PM. Prebid was held on 6/25/13.

08/28/13 – DK has returned all contracts fully executed, waiting on NTP.

09/25/13 – DK has notice to proceed, scheduling work on site with building maintenance. John Nester sent DK email with additional work that the county would like them to price. Waiting on DK to send in pricing.

10/30/13 – DK has installed all pole lights and repaired the lighting on pole #3. DK has gone to other facilities to work until final parts arrive, and plan to be back to finish out the changes on 10/31/13.

01/24/14 – TEI and DK did punchlist back-check on 01/24/14. DK to submit closeout documentation and then project can be closed and archived.

02/25/14 – TEI received closeout documents for project. TEI reviewing and will turn over to HamCo upon completion of review.

05/29/14 – Project complete and ready to Archive per Partner Mtg discussion.

COMM CENTER Lighting Repair Read More »

COMM CENTER Furniture System Power

Partner Lead: TEI

02/24/15 – Mike Barth and Terry Cannon met with Jayson and Ron at the Communications Center to discuss furniture systems replacement. TEI submitted SOSS for furniture system upgrade, including Arc Flash, project to Bert Watts. TEI waiting for signed SOSS/PO from HamCo.

03/25/15 – TEI received PO and signed SOSS to begin project. On 03/25/15 TEI preformed site visit to locate all existing electrical panels and switches for Arc flash portion of project. TE to coordinate with Furniture installer on schedule of installation to incorporate into electrical construction documents for coordinated package. BW requested coordination meeting with Jayson and Ron Bien during week of 4/1 with Progress set of documents for review and coordination.

04/15/15 – Drawing were issued for bidding under a small projects style format.

04/22/15 – Addendum 1 has been issued.

04/28/15 – Addendum 2 has been issued.

04/29/15 – Final addendum issued – bids due to ThermalTech by Friday 05/01/15 – no later than 12:00 PM (Noon). ThermalTech to issue Bid Tab to Facilities by End of day 5/1/15.

05/26/15 – Pre-Construction meeting occurred with Facilities Department, Jayson Dunn, ThermalTech and Phasor on 5/21/15. Phasor work to begin on 6/1/15 with the air test. Electric panels to be installed and ready to Xybix to be on site on 6/9/15 to begin Phase 1. The schedule is approximately 6 weeks in duration, and all parties will need to remain in constant communication during all phases of the work. Kelly plans to have (2) 40’ containers for tool storage delivered to the Comm. Center on June 8th. He may not need these depending on the size of our conference room. Ron, we’ll need to get him the conference room dimensions early next week. Hey may only need (1) container or neither depending on the space in the room. We are also having a roll off dumpster delivered the week of the 8th for disposal of the old furniture. We’ll have to coordinate locations for it as well as the forty footers somewhere on Comm. Center grounds. Marty, let me know what date we can get the roll off. We’ll also have to request staff to park in the gated area the day the trailer, the roll off, and the storage containers arrive. Shawn, Joe, Deb, Ron – We’ll need to line up Telecomm, Mobilcomm, and our staff to be ready to tear down and re-assemble TTY, the CAD, Radio, and Phone positions before Xybix tears down the positions and after they re-assemble them. The tentative plan is to move TTY back behind 45 before they start so the teletype area can be broken down first. Deb/Brian – We’ll have to brief the Supervisors on the schedule and make sure we are ready for noise in the room on a few days during the first week of June. Also, we need to make some decisions about the papers, folders, and binders at the positions and Supervisor desks before Xybix breaks them down. Also Deb the class is going to have to re-locate the 9th and not the 15th.

06/24/15 – Xybix has arrived on site and is proceeding according to the their original schedule (with the exception being that they are not working 12 days on and 2 days off as Kelley Smith had originally indicated.) On schedule to complete phase 3 this week. Met Ron Bien on site this week, and Ron indicated that the project is running great – all contractors are doing what they need to to make this a smooth project. Arc Flash model is completed and Mike Barth is scheduling with Mike Jackson a time to have Kendall get access to all spaces to apply labels.

07/22/15 – TEI installation of Arc Flash labels and new panel labels is complete. During install of Electrical panel labels – Kendall indicated that there was some post-punchlist items that needed addressed (fire stop material working its way out and falling on floor). TEI contacted Phasor and asked them to follow up.

09/23/15 – TEI in receipt of close out documents for Hamilton County, pending final inspection certificate from IBI. Phasor has contacted IBI requesting the certificate – final inspection approved 2-3 weeks ago.

12/08/15 – Project complete, ready to archive.

COMM CENTER Furniture System Power Read More »

COMM CENTER – Lobby Bullet Resistant Glass

Partner Lead: GBBN

11/16/16 – GBBN attends kick-off meeting onsite. Photos and dimensions taken for field verification.

11/17/16 – GBBN sends manufacturer’s data and literature on glass, Kevlar wall panels and pass through drawers to Facilities for Owner Review.

11/30/16 – GBBN submits SOSS to Facilities.

12/07/16 – GBBN receives approved SOSS

03/21/17 – GBBN sends email, with design questions, to Facilities. Answers are returned that same day to GBBN. GBBN has started estimating input on Archibus, Project Request #1892.

03/23/17 – At Partnering Meeting GBBN is requested to generate an Elevation Study of the existing Lobby Window wall to express the locations of the replacement equipment.

04/21/17 – GBBN and Facilities meet with Communications Center Staff to discuss Study and Estimate for the Bullet Resistant Glass Replacement. The Window Wall Elevation Study was reviewed.

COMM CENTER – Lobby Bullet Resistant Glass Read More »

Comm Center – Emergency Power Study

Partner Lead: TEI
02/25/17 – TEI receives call from AKM that the power system at the Comm Center is having glitches – where the building has lost power and emergency generators have not started twice since last summer. TEI, AKM, Mike Jackson, Duke, and the generator reps and maintenance contract companies are all meeting on site on 02/24/17 to analyze the cause and develop corrective actions.
05/25/17 – Estimate is on 2018 project list for entire power assessment for this site.
02/22/18 – Ready to archive.

Comm Center – Emergency Power Study Read More »