Hamilton County Facilities

2020 – Fire Alarm System Upgrade

PM – John Nester, Mike Barth

01/28/20 – TEI authors and submits SOSS for the project requested by Facilities.
02/26/20 – TEI receives PO and signed SOSS. TEI and Jessica Powell request design kickoff meeting with 2020 staff. Project kickoff meeting to be scheduled ASAP and design to commence thereafter.
03/26/20 – TEI, County Facilities, and building manager meet to kick off the project. Due to the COVID-19 restrictions, design meetings and field work at this facility have been placed on hold until all restrictions are lifted.
04/30/20 – Project Pending COVID-19 restrictions.
05/27/20 – Project pending COVID -19 restrictions.
06/23/20 – Project Pending COVID-19 restrictions.
07/29/20 – TEI meets with Rycca and Joe Houlihan to re-kick off the project. TEI re-booted the design process. Design fieldwork to be scheduled in the next 2 weeks or so.
08/21/20 – TEI completes field work and is working on completing design. TEI reaching out to Darryl Meadows (CFD) to schedule 85% complete review meeting with CFD and Bldg Department to get buy in on design with the AHJs prior to sending to HCFD for design review.
09/23/20 – TEI meets with Darryl Meadows, at the facility to review the design documents. Darry indicated that there is no BDA in the building presently, and that the City Ordinance requires a 3rd Party company (i.e. MobilCOMM) perform a spectrum analyzation of the building. TEI contacted MobilCOMM to obtain a quotation for the analysis. TEI will schedule a meeting to review design documents with HCFD – discuss option of Mass Notification, and latest Code changes that have been issued by NFPA 72, but that have not been adopted by the City of Cincinnati to date.
10/27/20 – TEI receives quotation from MobilCOMM for spectrum analysis for the building. TEI to schedule the test at a date that is approved by building manager. Upon receipt of the results of the testing – documents will be finalized and a review set will be sent to HCFD once funding for the project is secured.
12/09/20 – Spectrum Analysis scheduled for 12/15/20 with MobilComm. Upon receipt of results of analysis, TEI can send 99% set to HCFD for review in preparation for a January 2021 issuance.
01/26/21 – MobilComm provides spectrum analysis of the building, and a BDA for the project is not required for the building. TEI requests final design review meeting, and upon notification that funding is secured for project, will finalize ITB and issue for bidding.
02/23/21 – Project has been issued for bidding as ITB# 029-21. Pre-bid meeting scheduled for 03/09/21 and bids are due to purchasing on 03/24/21.
03/24/21 – Bids opened on 03/24/21 – and apparent low bidder is DeBra Kuempel, Inc. ThermalTech is vetting bids at 1:30 on 03/25/21 and will make recommendation ASAP to facilities upon completion of vetting process.
04/28/21 – Construction pending approval of contract by BOCC.
05/26/21 – PO and contract sent to DK on 05/25/21 – kickoff meeting to start submittal process requested with DK.
06/23/21 – JCI/Simplex developing submittals for the project. Upon approved submittals, construction will commence.
07/28/21 – TEI rejects (revise/resubmit) original submittals for the project. TEI receives revised submittals on 07/28/21. TEI to re-review and send approved submittals to DK for project. Project construction kickoff meeting can be schedule in next 2 weeks.
08/26/21 – HCFD and TEI host pre-construction meeting at the project site with Bldg Mgr, Brian Bell and Wayne McFarland. DK has PO and permits have been submitted for at are pending review comments from JCI Simplex. Materials from JCI have been released and are pending mid September delivery. DK tentatively scheduling mid/late September mobilization to the project site.
10/26/21 – TEI requests timeframe from DK for mobilization. Accoriding to JCI and DK, nearly all materials have be shipped to DK and work can commence.
01/25/22 – Project is in construction.  Backbone installed and DK has been working to pull second conductor to the notification appliances.  Work continues and in the next couple weeks will be working in the housing areas where residents will need to be temporarily relocated.
02/23/22 – Construction continues.   There are issues with the current Siemens smoke control system that the building manager is working with Siemens to resolve.   by first of next week, will be ready to start cutting over the units to the new system.  Meeting scheduled on 02/28/22 with housing unit staff to discuss and plan for relocation of residents during the installation.
04/28/22 – Met this week on site to do more fieldwork, Project should be complete in June 2022.
05/26/22 – Project nearing completion.  Inspections will be scheduled mid-late June for CFD and building department.
06/28/22 – Pretesting of smoke control system scheduled on 06/29/22.  Upon successful completion of smoke control system, inspections to be scheduled.
07/27/22 – Inspections to start next week.  Smoke control system work completed and tested.
08/24/22 – Inspections going well.  Building Department on site 08/25/22 (during this meeting) finishing inspections.  Will need to return once sampling tubes are replaced with correct tubes.  Then training and closeout can occur.
09/26/22 – All inspections complete and passed!  Finalized.   Upon completion of installation of access panels in the ceiling, project will be complete.
10/26/22 – Project completed.  Project pending close out documentation.
12/15/22 – TEI performs punchlist.  Still pending closeout documents.
01/25/23 – TEI receives close out documents from DK and reviews.   TEI requests minor updates.   Upon receipt of minor updates, Closeout documents will be submitted and project will be complete.
02/23/23 – Project ready to archive next month.

Scroll to Top