PM – John Nester, Mike Barth
01/28/20 – TEI authors and submits SOSS for project upon request of Facilities Department.
01/30/20 – This in in the approved projects list.
02/26/20 – TEI receives PO and signed SOSS for project. TEI to schedule kickoff meeting with facilities and building manager to kick off the project.
03/26/20 – TEI, County Facilities, and building manager to kick off the project. Due to the COVID-19 restrictions, design meetings and field work at this facility have been placed on hold until all restrictions are lifted.
04/30/20 – Project pending COVID-19 restrictions.
05/27/20 – Project pending COVID-19 restrictions.
06/23/20 – Project pending COVID-19 restrictions.
07/29/20 – TEI met with Bryan Collins and Ian Zellner to re-kick off the project. TEI contacting Joey Downs at Buckeye Power to re-evaluate the proposed solutions and add any updated recommendations/parts-pieces to develop the drawings and specifications.
08/21/20 – TEI contacts Buckeye Power to follow up on the initial quotation that Buckeye submitted. Design has commenced and coordination with EMI equipment supplier. We will notify HCFD once design review is ready.
09/23/20 – TEI, HCFD, and Ian meet with BPS, review the two options for the HMI replacement that BPS submitted. TEI and HCFD requested Sole Source letter from BPS. TEI developing Construction Documents for permitting and construction.
10/27/20 – TEI receives Sole Source letter from BPS. Working on permitting package – will provide draft of package for HCFD review once funding is released for the project.
12/09/20 – TEI wrapping up permitting package, and will send HCFD a review set prior to holiday break for review and to prepare for a January 2021 issuance.
01/26/21 – TEI sends JN at facilities a review set for the project. Upon facilities department review – TEI to finalize bid package and send to get costs.
02/23/21 – TEI and JN establishing final design review meeting with Ian Zellner and Comm Center Staff (within the next week), and will discuss dates for walkthroughs, etc at the meeting, then the project will be sent out for bidding.
03/24/21 – TEI receives sole source letter (modified as requested by Hamilton County). TEI and HCFD meet with the staff at Comm Center, and can issues the project once the procurement method is determined (sole source or ITB). purchasing approves sole source letter on 3/24/21. TEI and HCFD to conduct final meeting to finalize bidding documents ASAP.
04/28/21 – Per HCFD request – TEI requests a current quote from BPS, that has not expired. BPS confirms on 4/28/21 the latest version that we have recieved. Project to be issued upon receipt of this information from BPS and HCFD approval.
05/26/21 – TEI Submits Package to HCFD – who sent to prosecutors office for review and comments. Will issue to BPS upon prosecutor approval.
06/23/21 – Contracts mailed to BPS for signature and return to HCFD. Upon receipt of signed contracts, project will be approved and PO issued.
07/28/21 – PO issued to BPS for project. TEI and HCFD to schedule meeting with BPS to kick off construction and get leadtimes, etc.
08/26/21 – Construction pending procurement of equipment.
10/26/21 -Construction pending procurement of equipment. Anticipated to be Nov/Dec work.
12/13/21 – BPS on site starting today to install upgrades in the gear. Anticipate project work completed by end of the week.
01/25/22 – Work completed on the original contract work. HCFD requests quote from BPS for a replacement breaker to use incase of a breaker failure. BPS issues the quote and HCFD issues a PO for quote. BPS to purchase breaker.
02/23/22 – Upon receipt of breaker from BPS, project will be complete.
04/27/22 – Breaker received. Training completed. work from BPS completed. Upon receipt of closeout documents (AIA) from BPS – project complete.
05/26/22 – Upon receipt of closeout documents (AIA) from BPS – project complete.
06/28/22 – Project complete.