PM: Rycca Thacker, Paul Bellman
02/01/24 – Hamilton County requested slab project be rebid based on previous project.
02/12/24 – THP published review documents to the County.
02/16/24 – Hamilton County provided review comments to the documents.
02/16/24 – THP published bid documents to Hamilton County.
02/20/24 – Hamilton County advertised project for bid.
02/27/24 – Prebid meeting occurred.
03/11/24 – Addendum 1 issued to Purchasing.
03/14/24 – Addendum 2 issued to Purchasing.
03/15/24 -Addendum 3 issued to Purchasing.
03/28/24 – Bids due date April 8, 2024.
04/12/24 – Reviewed Bid with Browning Chapman.
04/19/24 – THP issued Bid Summary Letter to Hamilton County.
05/02/24 – Hamiliton County issued Contract Documents to Browning Chapman.
05/10/24 – Browning Chapman returned signed documents.
05/30/24 – Hamilton County Board review on 06/06/24.
07/19/24 – Browning Chapman working on pricing estimates for floor finishes, submittals, and background checks.
07/23/24 – Hamilton County requested to schedule a kick-off meeting.
08/15/24 – Preconstruction meeting completed.
08/19/24 – THP issued meeting minutes.
08/28/24 – Browning Chapman issued revised flooring options estimates. Browning Chapman’s submittals approved. Project to be scheduled.
09/25/24 – Browning Chapman submitted new flooring proposal for polished concrete. Approved and BC will need to develop Change Order.
10/28/24 – THP returned submittals to Browning Chapman.
10/31/24 – Final Pre-Construction meeting scheduled for Friday 11/01/2024.
11/01/24 – Kick-off meeting.
11/04/24 – HC sent Notice to Proceed.
11/07/24 – Progress Construction meeting.
11/14/24 – Progress Construction meeting.
11/20/24 – Progress Construction meeting.
11/20/24 – THP Signed Pay App #1 and sent to HC.
11/27/24 – Progress Construction meeting.
12/05/24 – Progress Construction meeting.
12/10/24 – THP signed Change Order #1.
12/12/24 – Progress Construction meeting.
12/13/24 – THP Signed Pay App #2 and sent to HC.
01/09/25 – Progress Construction meeting.
01/16/25 – Progress Construction meeting.
01/23/25 – Progress Construction meeting.
01/23/25 – THP Signed Pay App #3 and sent to HC.
01/30/25 – Progress Construction meeting.
02/13/25 – Progress Construction meeting.
02/20/25 – Punchlist Walkthrough.
02/26/25 – Browning Chapman finalizing punch list items. Final walkthrough scheduled 03/06/25.
03/06/25 – Final Walkthrough and signoff of completed items.
03/07/25 – THP signed Pay App #4 and sent to HC.
03/26/25 – Email sent to Browning Chapman requesting Closeout documents. BC indicated Closeouts will be ready for review on 3/28/25.
04/11/25 – BC sent closeout documents to THP for review.
04/18/25 – THP sent reviewed closeout documents and comments back to BC.
04/22/25 – THP sent HC signed Pay App #5 – Final Retainage.
04/24/25 – BC sent HC Final Closeout Documents.
05/29/25 – Can THP archive project?
06/25/25 – Project Archived.