Hamilton County Facilities

JC – Skywalk Roof Replacement & Exterior Repairs (F002)

PM: Bert Watts, John Millar

02/01/24 – Hamilton County requested an SOSS for roof replacement of Skywalk bridges.
02/29/24 – THP reviewed roof approach with Contractor and roofing manufacturers. THP working on proposal.
03/14/24 – THP issued DD review set of roof replacement with the Skywalk Exterior façade repair.
03/28/24 – THP working on bid package.
04/25/24 – Project combined with F077. THP working on documents.
05/30/24 – THP working on documents and targeting a bid set for June.
07/19/24 – THP issued Bid Documents to the County and Arc.
07/22/24 – Bid Documents Released on Bid Sync.
07/25/24 – Prebid meeting scheduled for July 30th and Bids due September 12th.
07/30/24 – Prebid meeting completed.
08/29/24 – Addendum No. 1 to be published.
08/29/24 – Addendum No. 1 published.
09/09/24 – Addendum No. 2 published.
09/19/24 – The bids were received from Browning Chapman and Buckeye Construction and Restoration. Both bids were under budget and within 8% of each other.
09/25/24 – THP and Browning Chapman had bid review meeting. BC appears to have all major scope items covered, including site logistical needs. The group discussed extending the contract to include time this winter to allow for shop drawing and window fabrication. BC is reaching out to the subcontractors to determine feasibility and needs. THP to publish summary letter after BC determines the needs.
10/08/24 – THP published the bid summary letter recommending Browning Chapman based on the bid amount.
10/31/24 – Hamilton County working on the AIA contract.
12/11/24 – Contract before the BOC for execution.
12/11/24 – Contract before the BOC for execution.
12/17/24 – Contract approved and sent to BC.
01/30/24 – Project status – BC finalizing submittals and background checks. Preconstruction meeting scheduled for 2/18/25. Anticipated construction starting end of March.
02/17/25 – Browning Chapman sent submittals for THP’s review.
02/18/25 – Preconstruction meeting completed.
2/27/25 – Browning Chapman finalizing background checks, submittals and permitting. THP working on submittals.
3/11/25 – Progress Construction Meeting.
3/18/25 – Progress Construction Meeting.
3/24/25 – Browning Chapman mobilized.
3/25/25 – Progress Construction Meeting.
3/26/25 – THP finalizing revised submittals and reviewing pencil Pay App #1.
04/01/25 – Progress Construction Meeting.
04/08/25 – Progress Construction Meeting.
04/09/25 – Permit Issued.
04/15/25 – THP finalized all submittals.
04/15/25 – Progress Construction Meeting.
04/21/25 – Roofing demo and window removal on East Skywalk began.
04/22/25 – Progress Construction Meeting.
05/06/25 – Progress Construction Meeting. East Skywalk roofing.
05/13/25 – Progress Construction Meeting. East Skywalk roofing complete. Steel Installation. North Skywalk mobilization.
05/20/25 – Progress Construction Meeting. East Skywalk steel painting, window flashing, painting mock-up. North Skywalk stair scaffold and roofing on east portion.
05/27/25 – Progress Construction Meeting. East Skywalk window installation. North Skywalk roofing and window removal/temp. panels on east portion.
06/03/25 – Progress Construction Meeting. East Skywalk Window install complete. North Skywalk Roofing east half complete and window removal/angle install in progress.
06/10/25 – Progress Construction Meeting. East Skywalk Façade painting in progress and North Skywalk roofing west half in progress.
06/17/25 – Progress Construction Meeting. North Skywalk Roofing west half complete and window removal complete. North Skywalk window install in progress. Punchlist started.
06/24/25 – BC sent Pencil Pay App #4 for review. THP to return shortly.
07/15/25 – Progress Construction Meeting. North Skywalk Façade painting.
07/29/25 – THP issued punch lists for North Bridge roof work and East Bridge. North bridge roof work was completed.
07/29/25 – Progress Construction Meeting. North Skywalk Façade Painting complete. East Skywalk Punch Complete. EJ Work in progress. BC sent Pencil Pay App #5 for review. Final Punch scheduled for 8/14/25 @ 1pm.
08/15/25 – THP investigated reported leak condition on the east end of the north bridge.
08/18/25 – BC, THP, and County completed water test and confirm leak was from roof drain line in the cavity below the bridge slab at the east end of the bridge.
08/19/25 – BC and THP used a camera to scope the drain line and found two breaks in the drain line that corresponded to the leak location.
08/21/25 – BC, THP and County completed punch trip for north bridge.
08/28/25 – THP exploring different plumbing repair options and developing opinion of probable costs.
10/29/25 – BC to begin Roof Drain line repair on 11/03/2025. 2 week schedule.
11/06/25 – THP completed site visit to review completed drain line.
11/14/25 – THP reviewed hatch mockup. Proposed hatch too big for panel. Updated panel size ordered. Weather permitting panel work to start in December.
12/11/25 – BC is installing the access hatch in the panel at the shop. Painter is scheduled to paint the panel in the shop. Once complete, BC to schedule panel installation.
01/28/26 – THP is reviewing BC’s Closeout Documents and should be returned 01/30/26.
01/28/26 – BC is currently estimating repairs for Concrete truck damage to North Skywalk.
02/05/26 – THP returned all Closeout Documents with comments to BC for final submittals to HC.
02/25/26 – THP to reach out to Imbus regarding mental panels and bending 20′ lengths.
03/25/26 – North Skywalk leak – BC indicated they are in contact with Delaware glass.
03/25/26 – Concrete truck panel damage – BC reaching out to metal panel manufacturers to get custom panel pieces and working up pricing. BC would like to coordinate panel repairs with leak.
04/20/26 – BC sent proposal to THP for Metal Panel Repairs. THP to review proposal with HC and schedule the work.
04/28/26 – BC is working with Delaware Glass on the leak at the North Skywallk and is working on scheduling them next week. A lift is required and will need to be delivered.
05/11/26 – Lift Plan submitted for Metal Panel work and glass warranty work.
05/19/26 – BC submitted cost breakdown for skywalk repairs to HC.
06/25/26 – Delaware Glass has completed warranty work for leak in North Skywalk. BC has completed metal panel work at North Skywalk and has processed all requested closeout documents.
07/30/26 – Verify with County if project can be archived.
09/23/26 – THP completed a site visit on 9/16/26 to review paint peeling on exterior skywalk façade. Field report to follow shortly.
10/26/26 – BC scheduling a site visit with Painting Contractor to review paint Issue.
10/28/26 – HC received letter from City of Cincinnati Permit District Inspector regarding open inspections for the project. BC was notified.