Hamilton County Facilities

230 – 10th Floor Marriage License Reno 2024

PK = Matt Butz, Mike Barth, Eryn Thamann
05/29/24 – TEI submits SOSS for approval.  Project pending PO and signed SOSS.
06/05/24 – Elevar submits SOSS for approval. Project pending PO and signed SOSS.
06/26/24 – Project pending PO and signed SOSS.
07/24/24 – TEI, Elevar and HCFD meet on site with end user. Scope changed and SOSS’s to be resubmitted for new revised scope.
08/27/24 – Elevar submitted new SOSS on 07/26 and awaiting approval.
08/28/24 – TEI receives signed SOSS and PO.
09/24/24 – Elevar scheduled a design kick off meeting for 10/01.
10/30/24 – Concepts provided to Probate for review.
12/09/24 – Finalizing concepts this week.
01/27/25 – ThermalTech awaiting schedule from HC/Elevar, HVAC SD level completed. In CD phase with 75% review in next few weeks. Electrical to finalize field confirmation after the partner meeting on 01/30/25.
02/25/25 – 75% review set sent to Probate for review and schedule of onsite meeting. Elevar still owes additional SOSS for lift removal/office add.
03/26/25 – Team met with Probate and has a few revisions. Still need finishes from HCFD. Elevar still owes additional SOSS for lift removal/office.
04/23/25 – Team is awaiting approval of lift/office SOSS to complete CDs.
05/28/25 – Progressing with CD drawings while waiting on final finishes approval.
06/26/25 – CD set was reviewed Probate and approved. Final finishes and systems furniture selected. Waiting for Probate to approved final SOSS for lift removal and additional office at which time they will be added to the drawings.
07/31/25 – Probate set to issue PO for additional work last wee/this week. Elevar to coordinate additional work and provide backgrounds. Need final approval for bidding from HCFD.
08/05/25 – THP received project authorization and signed agreement.
08/22/25 – THP – Elevar, County and THP reviewed field conditions for infill project.
08/28/25 – Additional SOSS approved and THP made site visit to field verify existing lift. Project will be ready to start HC review/bidding prep after this final scope is completed.
09/08/25 – THP issued infill repair detail for review.
09/25/25 – Drawings 95% complete and likely ready for a final review. ROM cost estimate sent to Probate for review.
10/21/25 – THP issued structural bid documents for project package.
10/30/25 – Project out to bid as of 10/22. Pre-bid mtg scheduled with team for 11/05.
12/11/25 – Post-bid vetting meeting scheduled for Alpha on 12/10 with Triton as next lowest.
01/29/26 – Permit/revisions applied for at City. Waiting on final contracts thru Purchasing.
02/26/26 – Contract awarded to Alpha on 02/19. Elevar to schedule construction kick-off mtg.
03/26/26 – Elevar to schedule construction kick-off mtg after Alpha provides construction schedule; expect this soon. HCFD to award special inspections SOSS.
04/30/26 – Construction kick-off meeting scheduled for end of May.
05/28/26 – Construction kickoff mtg occurred 05/27. Eryn to issue mtg mins and setup recurring progress mtgs. Construction to start June 1.
06/25/26 – Construction ongoing.
07/30/26 – Construction ongoing. Approx. carpet delivery is Aug 4. Phase 1 is waiting on carpet install prior to shifting to Phase 2.
08/27/26 – Construction ongoing in phase 2. Working on HVAC duct issue.
09/24/26 – Punch list for Ph. 2 occurred and contractor moved to Ph. 3.
10/29/26 – Approx. 2 weeks from Phase 3 completion. Furniture move is scheduled for 10/28. Closeouts will also remain.