PM: Matt Butz, Mike Barth
05/29/24 – TEI submits SOSS for approval. Project pending PO and Signed SOSS.
06/26/24 – TEI receives signed SOSS and PO for project. Study initiated and TEI is prepared to schedule meetings with the correct stake holders at the HCSO.
07/24/24 – TEI and HCFD discuss scheduling kick off meeting the week of 08/05.
08/28/24 – TEI meets with system suppliers to discuss latest industry trends and current offerings. Report is in development.
09/25/24 – TEI reviewing report and will send to HCFD for comments.
10/30/24 – TEI sends report to HCFD for review and comments.
12/11/24 – HCFD and TEI meet with HCSO to review report. HCSO asks if the Telecor cell intercom system is compatible with a new PLC. The PLC system will accommodate, TEI to investigate any potential modifications to the Telecor system that would be required and the potential cost implications, then the report will be finalized.
01/29/25 – TEI contacts ICS multiple times to get cost schedule implications. ICS not responding. Per Matt – we will issue the final report after 02/01/25 if no response from ICS by then.
02/26/25 – TEI submits final report to HCFD. HCFD sends additional comments to TEI to incorporate. TEI to resubmit upon completion of updates.
03/26/25 – TEI working with suppliers to get budget numbers for alternatives that were included.
04/23/25 – TEI receives budgetary numbers on 04/21/25 from suppliers. Final updates to be completed and returned to HCFD.
05/28/25 – TEI submits finalized reports to HCFD.
06/25/25 – Finalized reports are submitted. HCFD asks for an approx cost for engineering. Not an official SOSS at this point.
07/30/25 – DEG submits estimated design engineering costs to HCFD.
08/27/25 – No updates.
09/24/25 – No updates.
09/25/25 – OK to Archive.