12/28/17 – THP publish SOSS to Hamilton County as requested.
01/25/18 – Hamilton County approved SOSS.
04/19/18 – Completed visual survey from grade.
04/20/18 – Rappelled all four elevations.
04/26/18 – Report under development.
05/21/18 – THP completed draft of Cincinnati façade ordinance report.
05/22/18 – THP developed Opinion of Probable Cost for recommended repairs specific to Cincinnati façade ordinance review.
05/24/18 – THP finalized Cincinnati façade ordinance review report and application form.
5/31/18 – County provided verbal comments. THP reviewing comments.
7/26/18 – CORRECTION, comment on 5/31/18 for 800 Broadway assessment. Report approved as submitted.