01/13/21 – SOSS requested by Hamilton County.
01/20/21 – THP completed a site visit to determine scope.
01/28/21 – THP developing the SOSS. OK to combine bids as long as the bids can be separated or itemized.
02/25/21 – SOSS submitted to THP for internal review. Proposal should be issued on 2/26/21.
03/24/21 – SOSS submitted for review.
05/27/21 – Project update County located existing drawings which included a previous THP design. THP plans to issue review drawings by June 2.
06/25/21 – THP to send review set next week to County.
07/26/21 – THP issued “For Bidding” submittal with drawings and project manual.
08/03/21 – THP hosted pre-bid meeting at HC Courthouse and 230 WHT Center.
08/06/21 – THP issued Addendum #1.
08/17/21 – THP issued Addendum #2.
08/24/21 – Bid opening. Received 2 bids from Triton and ZSR. THP to begin vetting process.Bids under advertised budget.
08/26/21 – THP has meeting schedule with Triton on 8/27/21 to review bid proposal.
08/27/21 – THP has phone call with Triton to discuss/review bid. THP sends Hamilton County bid summary/award recommendation letter for Triton.
10/27/21 – THP to schedule kick-off meeting with Triton and Hamilton County.
10/28/2021 – Kick off meeting scheduled for November 4 at 11am.
11/4/21 – Pre-construction meeting with THP, Hamilton County, Triton, William Lang & Sons Co, and Neiheisel Steel.
11/12/21 – THP submitted building permit application.
11/15/21 – Hamilton County Courthouse Boiler Room Safety Platform Shop Drawing Submittal Reviewed and Returned.
12/6/21 – 230 WHT Roof Stair Shop Drawing Submittal Reviewed and Returned.
12/7/21 – CO#1 executed authorizing use of project allowance funds and increase to existing allowance funds to furnish a replacement kitchenette at Courthouse 6th floor.
12/7/21 – Planning for January 2022 for installation of Courthouse Boiler Room Platform.
1/26/22 – THP began process for William Howard Taft Center building permit application. Construction for WHT Center Roof Maintenance Stairs to commence after HC Courthouse
1/26/22 – THP began process for William Howard Taft Center building permit application. Construction for WHT Center Roof Maintenance Stairs to commence after HC Courthouse Boiler Room Platform project. Schedule and start date TBD. Most likely March/April time frame.
2/21/22 – Triton to mobilize to site to field measure site conditions.
2/23/22 – Waiting to hear back from City on the Permit Application.
3/2/22 – Permit application has been approved. Approved drawings and approved project manual has been sent to all parties involved.
4/25/22 – Triton submitted crane lifting plan. Hamilton County asked for additional information be provided for County review. Plan is still to crane material to roof on Saturday, May 7th. Roof stairs installation to begin following week.
5/10/22 – Stair posts installed by Neiheisel and roofing repairs performed by Tremco this week before crane lifting the rest of the material onto the roof.
5/14/22 – Remaining stair material crane lifted onto roof and installed onto posts.
5/16/22 – Neiheisel performed final stair installation and detailing. WHT roof stairs installation completed this week.
5/25/22 – THP and Triton to coordinate final cleanup and paint touch up before the final walk through. THP to coordinate final inspections with Terracon and City.
06/24/22 – Terracon completed steel inspection.
07/28/22 – Triton finishing punch list work this week.
08/02/22 – Walk through with Hamilton County and Triton to review punch list items. Hamilton County satisfied with completion of the project.
08/24/22 – Final inspection with City of Cincinnati Building Department completed. City to close permit.
09/27/22 – Final Inspections have been completed. Waiting for City Inspector to close Permit. Called City Inspector on 9/27/22 to get update. City Inspector said he was going to close Permit.
10/12/22 – Permit has been closed by City of Cincinnati. Triton is working on finalized pay app and required closeout documents.