Hamilton County Facilities

CH – Boiler Room Exhaust Fan Platforms (F024)

01/13/21 – SOSS requested by Hamilton County.
01/20/21 – THP completed a site visit to determine scope.
01/28/21 – THP developing the SOSS.
02/25/21 – SOSS submitted to THP for internal review. Proposal should be issued on 2/26/21.
03/24/21 – SOSS submitted for review.
04/01/21 – SOSS approved.
04/19/21 – THP completed field work.
04/27/21 – THP sent SD drawings with draft platform options.
04/29/21 – THP and County to schedule review meeting.
05/11/21 – THP and County met to review SD plan.
05/21/21 – THP DD review drawings and OPC published.
07/26/21 – THP issued “For Bidding” submittal with drawings and project manual.
08/03/21 – THP hosted pre-bid meeting at HC Courthouse and 230 WHT Center.
08/06/21 – THP issued Addendum #1.
08/17/21 – THP issued Addendum #2.
08/24/21 – Bid opening. Received 2 bids from Triton and ZSR. THP to begin vetting process.Bids under advertised budget.
08/26/21 – THP has meeting schedule with Triton on 8/27/21 to review bid proposal.
08/27/21 – THP has phone call with Triton to discuss/review bid. THP sends Hamilton County bid summary/award recommendation letter for Triton.
10/27/21 – THP to schedule kick-off meeting with Triton and Hamilton County.
10/28/2021 – Kick off meeting scheduled for November 4 at 11am.
11/4/21 – Pre-construction meeting with THP, Hamilton County, Triton, William Lang & Sons Co, and Neiheisel Steel.
11/12/21 – THP submitted building permit application.
11/15/21 – Hamilton County Courthouse Boiler Room Safety Platform Shop Drawing Submittal Reviewed and Returned.
12/6/21 – 230 WHT Roof Stair Shop Drawing Submittal Reviewed and Returned.
12/7/21 – CO#1 executed authorizing use of project allowance funds and increase to existing allowance funds to furnish a replacement kitchenette at Courthouse 6th floor.
12/7/21 – Planning for January 2022 for installation of Courthouse Boiler Room Platform.
1/12/22 – THP submitted permit response letter and supplemental documentation to the City for Building Permit Application. Waiting for response from City.
1/25/22 – Building permit application for the Hamilton County Courthouse has been approved. Hamilton County suggests another pre-construction meeting with Hamilton County, THP, and Triton to go over schedule/details before starting work on the boiler room platform. Schedule pre-construction meeting as soon as possible.
2/10/22 – THP, Hamilton County, and Triton had another Pre-Con meeting at Courthouse to go over schedule.
2/16/22 – Triton mobilized to Courthouse to begin site layout and scanning existing boiler room floor.
2/21/22 – Triton to begin sawcutting existing floor for new footers.
3/15/22 – Existing slab sawcut for (4) new column foundations. Other two column foundations will be anchored to existing concrete.
3/18/22 – Terracon onsite to inspect existing soil conditions. To achieve the necessary bearing capacity for the new footings, Terracon recommended to excavate another 6”-8” of material, add a little water, and then tamp the soil for compaction.
3/19/22 – Platform steel delivered to Courthouse Boiler Room.
3/30/22 – Triton starts to pour concrete for (4) new column foundations. Terracon was onsite for special inspections (soil, rebar, concrete). Other two columns will be anchored to existing concrete. Platform installation, steel erection to follow.
4/26/22 – Courthouse platform installation is complete. Triton to coordinate final cleanup and paint touch up before final walk through. THP to coordinate final inspections.
5/25/22 – Courthouse platform installation is complete. THP and Triton to coordinate final cleanup and paint touch up before final walk through. THP to coordinate final inspections with Terracon and City.
06/24/22 – Terracon completed steel inspection.
07/28/22 – Triton finishing punch list work this week.
08/02/22 – Walk through with Hamilton County and Triton to review punch list items. Hamilton County satisfied with completion of the project.
08/24/22 – Final inspection with City of Cincinnati Building Department completed. City to close permit.
09/27/22 – Final Inspections have been completed. Waiting for City Inspector to close Permit. Called City Inspector on 9/27/22 to get update. City Inspector said he was going to close Permit.
10/12/22 – Permit has been closed by City of Cincinnati. Triton is working on finalized pay app and required closeout documents.

Scroll to Top