PM: Sarah, Eryn
10/30/24 – SOSS in final review prior to sending.
12/09/24 – Pending approved PO.
01/29/25 – Pending approved PO.
02/25/25 – Pending approved PO.
03/26/25 – PO approved and initial site walk scheduled for 03/27 with JN.
04/24/25 – Walk-thru occurred and drawings have progressed. Elevar to coordinate with Champlin on design in near future.
05/28/25 – DD-level drawings are prepared. Elevar needs to review with Champlin/HCFD for general design intent; need bidding info.
07/31/25 – Ready for review with Champlin/HCFD.
08/28/25 – HC/Champlin/Elevar review meeting scheduled for 09/02 to review current sets and decide on bidding strategy.
09/25/25 – Finalizing cost estimates now. Drawings to be updated with any cost estimate comments. Specs to be completed after final project design review.
10/30/25 – Initial cost estimates complete and ready to review with HCFD. Need mtg scheduled to review estimates and what scope is base bid vs alternates. Also under review by separate hardware consultant.
12/11/25 – 95% review set provided to HCFD with costs. Elevar working on bid breakdowns now for the various buildings, alternates, and unit costs and will review with HCFD once complete.
01/29/26 – On Elevar’s current workload to write bid form breakdown.
02/26/26 – Elevar provided bid form breakdown. Rycca requested summary and Evan/Matt to setup meeting with Sheriff’s to review JC.
03/26/26 – Elevar to hold on design as-is. Evan/Matt to setup meeting with Sheriff’s to review JC in future. Work order in process for removing paint that may impact bid form.
04/30/26 – SOSSs approved for additional CA work. No update on whether paint removal from stickers was successful.
05/28/26 – No update. Need to know if paint removal was successful on stickers.
06/25/26 – No update.
07/30/26 – No update.
08/27/26 – No update.
09/24/26 – Awaiting paint removal status.
10/29/26 – No update.