Hamilton County Facilities

Colerain – Animal Shelter Boiler Replacement

PM: Tony Matre, Terry Cannon

09/26/24 – After SD and pricing efforts, we have decided to bid this project via Small Project bid with one for one like boiler and no recirculation pump replacements in the Base Bid.
10/30/24 – Drawing are modified and ready for bidding. NKY will be but no word back from DK and Geiler on their willingness to give us a price for this work.
12/12/24 – No updates since last meeting. BW said to go ahead and get three prices for the boiler replacement but they are not moving on doing the work this year. One price received so far.
01/28/25 – No updates.
02/26/25 – No updates.
03/25/25 – No updates.
03/26/25 – Tony confirmed this project on hold. No work for TEI at this time.
04/23/25 – Project on hold.
05/28/25 – Archive until further notice.