PM: Rycca Thacker, Eryn Thamann
02/26/26: Added as new project. Need meeting with COA/Probate/HCFD to review scope.
03/26/26: SOSS provided for concepts/SD phase.
04/30/26 – No update.
05/28/26 – Will wrap into elevator project. Elevar to provide new SOSS and will work on design options.
06/25/26 – SOSSs in process for approval with HCFD now.
07/30/26 – Concepts reviewed at initial meeting and working thru final concept now. Will review with HCFD prior to scheduling full group meeting. 230 Court Admins wanted this work to be completed faster than if combined into 230 Lobby Security project.
08/27/26 – A third option for the rear secure elevator area was discussed with Rycca and will be provided this week. Another meeting with the main group will then be scheduled. Exterior Lighting portion broken back out to separate project.
09/24/26 – A third option was provided to the entire group and another meeting was held. Another revision was sent to entire group for input and potential third meeting.
10/29/26 – Another mtg was just held and option 7 is under design.