PM: Megan, Terry Cannon,
04/30/26 – Project opened on website. DEG started fieldwork and is working on bid CD documents. Need to check on SOSS approval.
05/27/26 – Need to request meeting with new building manager before proceeding. Meeting June 4 at 9am for design meeting with Jesse.
06/25/26 – First review set probably ready in July.
07/30/26 – Plumbing ready for review, electric will be ready soon then to County for Owner review.
08/26/26 – Review sets sent to County and limited comments received back. Floor plans updated. The project will be ready to bid soon.
09/15/26 – Prebid
09/18/26 – Addendum 1 issued.
09/22/26 – Addendum 2 issued.
09/24/26 – Bid due Friday.
09/25/26 – Bids received. Triton and QCM Mechanical submitted bids. DK and others did not bid the project.
10/22/26 – Facilities notified DEG that the bids are not awarded due to contract technicalities. TTC informed Triton in person.
10/27/26 – TTC & Rycca discussed how to rebid the job with a few small changes and make it suitable for award. DEG will update the bid documents adn send back out for a price refresh from the same vendors.