Hamilton County Facilities

Comm Center – BE Assessment (F041)

PM: Rycca Thacker / Ian Zellner, John Millar
03/06/26 – HC requested an assessment SOSS.
03/13/26 – THP provided an SOSS for review.
04/09/26 – HC approved SOSS.
04/30/26 – THP working on Assessment. Roof testing/thermal scans 4-6 weeks out from April request. Testing contingent on weather conditions.
06/16/26 – THP completed field survey and roof scans.
08/05/26 – THP published the final report.
08/27/26 – Put into Archibus. THP has full restoration and partial, agreed to enter full cost and in notes put reduced scope.