Hamilton County Facilities

230 – Sewage Ejector Replacement

PM: John Nester, Terry Cannon

03/31/22 – County reaches out for SOSS for this job.
04/02/22 – ThermalTech reached out to Derek Koogler to get a submittal and quote for the job.
05/24/22 – ThermalTech on site for fieldwork.
05/27/22 – First set of plans created for job.
06/02/22 – Markups complete, given back to TTC.
07/20/22 – Markups returned to TTC again.
07/26/22 – TTC returned dwgs with additional markups. New lid information requested, use the same style as A&D.
08/05/22 – Page created and back-filled with project data. Progress drawing sent to County. We need preferred floor drains for replacement from John or Ernie.
08/22/22 – Met with John and Ernie on site and finalized scope. One new
08/24/22 – Final markups sent in for Cad. Bid in September, maybe August.
09/22/22 – Bid opened, DK apparent low bidder. Pre-Award meeting scheduled for next Tuesday. We have the budget to take all the Alternates on this job.
10/26/22 – Waiting on final contract and PO to begin work.
12/15/22 – Submittals returned for correction, new submittals should be here any day. Pre const meeting was held with Debra and everything went well.
01/24/23 – Pushing the manufacture hard to update submittals with the correct voltage. Other than that the submittal looks great.
02/20/23 – New submittals were returned FAC so the equipment should be on order this week. We still need external disconnects and transducer submittals. DK getting new delivery schedule.
03/29/23 – Pumps are ordered, assembled scheduled to be complete by the end of April. Tigerflow ship date not confirmed.
04/25/23 – Weekly check-ins with the vendor and contractor has not gotten us a firm date when the package will ship from Tigerpaw.
05/12/23 – Schedule of Values submitted, reviewed, and returned for changes.
06/28/23 – Schedule of value resubmitted for approval. Equipment scheduled to arrive at Tigerflow second or third week of July.
07/26/23 – Pump package will be here in August. Pre-Const meeting will be scheduled in August.
08/07/23 – Pre Construction Mtg #2 was held with Debra and the County. Meeting minutes will be distributed later this month. DK supposed to start in August.
09/27/23 – DK will send Dirk to do this job after they wrap up PBS Ice Machines which will be complete by the end of MNF week (this week). They should be mobilizing in next two weeks. I will check on paperwork again.
10/23/23 – Met Dirk onsite for project kickoff. Mobilization and tools today. DK started disassembly of sewage ejector system. Water filled sump about noon from fire pump test, but was pumped out before DK left for the day.
10/24/23 – Work continued on pump replacement no more water issues.
10/25/23 – Pumps are installed and operating. DK jet cleaning floor drains but finding clogs. Floor was hand scanned before saw cutting. DK used jack hammer to install new floor drain near blow down tank. New line and floor drain installed, concrete poured back into placed. We will meet on Friday for punchlist. Corporate equipment coming Friday for startup.
12/06/23 – Work is complete. Punchlist was issued. Backpunch and training completed. The system is up and running. DK to label each pump in field. DK to provide all closeout paperwork for this job.
01/31/24 – Project is complete. Discuss contractor and allowance with John Nester before accepting final payapps ($5k vs $12k).
02/23/24 – Review closeout documents with John.
03/22/24 – Ready to Archive this job but DK has not provided all closeout documents yet.
06/01/24 – Working with DK on closeout.
09/01/24 – Working with DK on closeout.
12/01/24 – Working with DK on closeout.
01/25/25 – Received Consent of Surety for final closeout today, sent that and final payapp to Hamilton County for closeout and processing.