Hamilton County Facilities

230 – Summer Boiler Replacement

PM: Tony Matre, Terry Cannon
07/31/25 – SOSS approved. ThermalTech is conducting fieldwork to see if we can fit a boiler into the elevator and down to the in a size matching the KN boiler 2000 MBH. We did confirm that the boilers intended to be used on the Ameresco will not fit into the elevator, but they are 2500 MBH.
08/20/25- Final review drawings ready to review. TTC will send to County for review.
08/25/25 – Boiler selection is waffling, not sure where guys are going to fit a boiler in the elevator and down to the basement. We decided to have a base bid boiler and an Alternate boiler that matched future boilers.
09/24/25 – Review will be sent to Tony Matre for his review today.
10/29/25 – TTC preliminarily setup prebid meeting but did not get confirmation from bidders except one bidder (Triton) who showed up. TTC to reschedule.
11/14/25 – Prebid meeting with four vendors.
11/26/25 – Bids received, tabulated and sent to County. All bids were overbudget.
12/12/25 – TTC repackaged drawings and sent to DK for State Term pricing.
01/25/26 – County deciding if they want to award this project via State Term to Emcor and Debra Kuempel.  It does sound like it is going that way.
02/25/26 – No update on moving forward on this project yet.
03/25/26 – No update, still awaiting green light from County to move forward with state term work.
04/26/26 – DEG and Ameresco working on new boiler plant, this project can be archived.