PM: Rycca, Mike, Sam, Eryn, Terry, Mike, John
07/31/25 – We discussed the quantity of 2026 projects coming our way and we think about 20 project are new. The County will self-inflate the refresh cost estimates. Rycca will print and share the original list with us soon.
08/20/25 – ThermalTech received approved SOSS received from County.
08/28/25 – TTE Internal kickoff start, completion matrix created, Champlin assignments accepted and the TEI MBE partner engaged for work this year. Elevar SOSS submitted to HC 08/27.
09/24/25 – ThermalTech DEG working on estimates, most are done. Fieldwork in JC scheduled for this week. Gazelle will start uploading to Archibus this week.
09/25/25 – Elevar estimates ongoing and meetings with tenants scheduled.
10/30/25 – Elevar complete with estimates. ThermalTech complete with estimates.
12/11/25 – Complete. Davies partner creating binder PDF of each estimate before module is closed.