Hamilton County Facilities

250 WHT – First & Second Floor Construction

PM: John Nester, Lead: Sam Hofmann

10/28/21 – Create project for tracking construction progress.
12/14/21 – Project waiting on contract finalization. Permit filed.
01/25/22 –  Construction Kick-off meeting held.
02/24/22 – Notice to proceed issued. CA in progress. RFI submitted on t-stat and answered to leave where is. HVAC submittals received and returned.
03/31/22 – CA on going. Demolition complete, framing in progress.
04/28/22 – CA on going.
05/26/22 – CA on going. Still on target to complete on schedule.
06/30/22 – CA on going. IBI inspections this week. City TCO next week. Move 2nd floor into new space in time for meeting.
07/28/22 – Second floor punchlist scheduled for 8/4. Door delivery for first floor is delayed. Triton to install temporary doors to receive occupancy.
08/04/22 – Second floor Punch list completed.
08/24/22 – First floor punch list completed.
09/29/22 – Second Floor punchlist completed. First floor backpunch to be scheduled.
10/27/22 – Back punches complete. waiting on confirmation that items have be12/15/22 – en completed.
12/15/22 – Second floor sign off received. Still waiting for cores for the first floor doors. PO being held open for TPC 6th floor ceiling work.
01/26/23 – Cores completed. Cypher lock had to be reordered. should be installed in next couple days which is the last item. Close out documents requested.
02/22/23 – Closeout documents and final pay app received.
03/30/23 – Still need physical binders from triton.
04/27/23 – No update.
05/25/23 – Have reached out to Triton several times regarding binders and final pay app, still have not received them.
06/29/23 – Closeouts and final pay apps received.

08/31/23 – No update.

09/28/23 – No update.