Hamilton County Facilities

A&D – Sewage Ejector Pumps

PM: Terry Cannon, Tony Matre

10/28/21 – Sewage ejectors not working correctly. Tony called for replacement work on them. Prebid set for today 2pm today.
11/30/21 – Bids received, QCM apparent low bidder. Pre Award meeting held virtually and QCM recommend for work.
12/14/21 – Tony getting PO for work to QCM for job. TTC to setup a pre const meeting late Dec 2021.
01/18/22 – Pre Const Mtg with QCM. Equipment approved and on order. The meeting went well, Drew and his foreman looked the job over. We are shooting for a Feb or March start date.
02/24/22 – No update on equipment delivery yet. QCM talking to Corporate Equipment every day to finalize a delivery date.
03/31/22 – Changed to submersible pumps, approved new submittals, created new dwgs and sent to vendor, should be installed mid-April.
04/18/22 – New pumps were installed and completed. MC and EC are done, and controls are coming to hook up the alarm points.
04/28/22 – The system is working well, pump #2 is going out on overload. EC dispatched to look at on Wednesday, they called Streamkey to look at the issue on Thursday. ALC controls are not hooked up yet, need additional wiring for the interface.
05/25/22 – Project complete and punchlist distributed to QCM. Emcor ALC waiting on badged low voltage electrician to run their alarm wiring before we close out. I sent all closeout docs to QCM. The system is working well.
06/30/22 – Just waiting on controls to finish DDC work, closeout documents from QCM.
07/27/22 – Controls work is complete. TEI requested O&M and Closeout documents from QCM.
08/24/22 – Project complete, we’ve requested closeout documents.
08/26/22 – All closeout and final payaps received. Project ready to closeout.

Scroll to Top