Hamilton County Facilities

CH – Gas Booster Pumps

PM Tony Matre, Terry Cannon
10/28/21 – Project is issued for bidding. Bids received and are awardable. Queen City Mechanical (QCM) is the apparent low bid. TEI conducts the pre-award meeting and provides recommendations to award. AKM indicates that he has PO and the project is moving forward.
12/13/21 – Bids received.  QCM is the apparent low bidder.  Post bid interview went well.  TTC setting up pre const meeting and reviewing submittals for the job.  Trying to coordinate electric with CH shutdown for the Server room which is the MCC in the boiler room where the booster is also fed from.
01/25/22 – Gas pumps are on order. Electrical permit drawings sent to QCM for permitting last Friday. We are trying to get the transfer switch in place during the CH Server shutdown.
02/24/22 – No major updates yet, QCM says the delivery date has been pushed back to April 2022.
03/31/22 – Electric submittals are reviewed, EE permit next. Booster will be here late April or mid-May.
04/28/22 – Stoermer stated the gas booster will be here mid-May to June now. The electrical submittals are returned with limited comments. IBI permit drawings were sent to QCM. They will schedule the work as soon as the equipment this in town.
05/25/22 – QCM and Stoermer have updated the equipment delivery date to be mid to late June. When the equipment gets here, the project will be started.
06/30/22 – Equipment not here, waiting on an update from Stoermer. Gas booster delivery delayed until end of July.
07/27/22 – Gas Booster pump delayed to mid-August. TEI reached out for an updated delivery date.
08/24/22 – Gas booster delayed until the end of August. All other facets of the job are read to go.
09/22/22 – Gas booster delayed until the end of September per Stoermer.
09/28/22 – Gas booster is here. Pad being poured this week, booster will be mounted next week then piping can begin.
10/26/22 – QCM submitted RFI for new piping arrangement with pump rotated 90 degrees to provide clearance around new disconnect in basement.
12/15/22 – Work is complete. First testing was not successful, we are waiting for a warm afternoon day to verify rotation of the new booster before we try again. QCM bringing extra fuses down to replace blow fuse during testing.
01/10/23 – Field rotation was verified and the gas booster started up with factory support. The backup gas booster is ready to go. There is a question about secondary gas pipe heat sensor.
01/24/23 – No closeout paperwork has been received yet on this job.
02/23/23 – No closeout paperwork has been received yet on this job. TTC checked back with QCM as certified PW keep coming in.
03/29/23 – Reached back you to QCM for all closeout documents.
04/26/23 – Closeout documents received.
05/21/23 – Closeout documents reviewed and approved. TTE processing final pay application.
06/28/23 – Final closeout documents delivered to County with Final Payapp. Ready to Archive.