PM: John Nester, Terry Cannon
04/28/22 – SOSS received and approved.
05/25/22 – It’s on the radar but not started yet.
06/30/22 – No updates.
07/27/22 – We visited the building for our first field trip. We’ve researched HVAC solutions for the space and will probably recommend splitting the existing HVAC unit into two systems one for the first floor and one of the second floor, adding a thermostat for better control, modifying basement ductwork to create two zones and adding one condensing unit for split system control.
08/24/22 – No significant progress this month.
09/25/22 – Draft reports should be done in early October.
10/26/22 – Electric reporting has been started, mechanical items are not so much. Soon…soon.
11/30/22 – Final report was turned over for final review and use. A few edits were made and the final report was resent to County amid several email blunders by TTC.
01/25/23 – No updates.
02/23/23 – Ready to Archive