Hamilton County Facilities

JC – Underground Fuel Tank Replacement

PM: Matt Butz, Terry Cannon
04/26/22 – SOSS has been received. TTE met with County on kickoff meeting earlier this month. We met with the Fire Marshal and discussed scope of replacement, FM requested double containment piping on both the FOS/FOR piping. TTE on site with Duke to get into the vault and verify pipe routing and type. FOS/R is all double wall contained so we should meet code and fire marshal request for this project. THP not required on this project yet.
05/25/22 – CAD drawings and backgrounds are mostly updated, we are working on specifications and awaiting TTC markups for next step.
06/30/22 – CAD markups are back to designers. This job should be out for bidding by end of July.
07/27/22 – Review drawings are ready. We will submit them for review next week.
08/24/22 – Final markups in for updating. Bid in September.
09/25/22 – JN has provided contracts, TTC putting together bid documents. The project should bid end of Sept/early Oct timeframe.
10/26/22 – Out for Bid. Prebid complete, Addendum 1 ready for issuance. Bid Opening on Nov 4.
12/15/22 – No bids were submitted after extending the bid for local contractors. The job was repackaged as a Rebid and a new prebid was held last week. The local contractor still is not comfortable bidding the work, we have an Alternate design to send out for Addendum today for consideration. Job set to bid on 12/21/22.
01/24/23 – No bids submitted on rebid either. We will try to roll this scope into the Emergency Generator upgrades.
02/23/23 – Project combined with JC Emer Gen project in 2023. Archive this report.

Scroll to Top