Hamilton County Facilities

Champlin – General Services

02/14/19 – County invites Champlin for MSA agreement
02/21/19 – County sent MSA Contract to Champlin
03/13/19 – County sent revised MSA Contract to Champlin
03/18/19 – Champlin sent proposed revisions to MSA Contract
03/29/19 – County sent final MSA Contract
05/23/19 – General Services P.O. approved
05/30/19 – Kru and Mike from Champlin attended Monthly Partners Meeting
06/03/09 – Bert requests code interpretation for safe room locks on certain areas within the 911 Communications Center.
06/07/19 – Champlin provides 2017 OBS interpretation for safe room locks on certain areas within the 911 Communications Center
06/14/19 – Champlin provides further clarifications on 2017 OBS interpretation for safe room locks on certain areas within the 911 Communications Center
06/27/19 – Kru from Champlin attended Monthly Partners Meeting
07/31/19 – Christy from Champlin attended Monthly Partners Meeting.
08/29/19 – Kru from Champlin attended Monthly Partners Meeting and updated website.
09/26/19 – Kru from Champlin attended Monthly Partners Meeting and updated website.
10/30/19 – Champlin visited Auto Title and currently working on space layout.
12/12/20 – Mike and Sam from Champlin attended Monthly Partners Meeting and Updated website
01/02/20 – Bert reached out to Mike and Kru for CAB signage replacement
01/10/20 – Kru and Sam from Champlin visit Taft Center for potential Alley Door Upgrade
01/24/20 – Champlin reached out to multiple vendors for information on existing conditions
01/28/20 – Champlin received CAD files of CAB elevations from THP.
01/30/20 – Mike and Sam attended Monthly Partners Meeting and updated website.
01/30/20 – CAB signage project to be added to an existing facade repair job currently active at the CAB
02/04/20 – Signage drawings sent to THP to give to AFR
01/27/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
02/25/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
03/25/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
04/08/21 – Sent County options for casework refresh.
04/29/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
05/27/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
06/25/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
07/29/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
08/26/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
10/25/21 – Final Facilities kitchenette drawings sent to County for review.
10/28/21 – Sam Hofmann attend monthly partner meeting.
12/03/21 – SOSS approved for Design and consulting services.
12/14/21- Mike Murphy, Sam Hofmann attend Monthly Partner Meeting.
01/26/21 – Mike Murphy, Sam Hofmann attend Monthly Partner Meeting.
02/09/22 – Met with County, Triton, Thermaltech and Champlin to review scope of TPC 6th Floor ceiling replacement.
03/31/22 – Sam Hofmann attends Monthly Partner Meeting.
04/28/22 – Mike Murphy attends Monthly Partner Meeting.
05/26/22 – Mike Murphy and Sam Hofmann attends Monthly Partner Meeting.
06/30/22 – Sam Hofmann attends Monthly Partner Meeting.
07/28/22 – Mike Murphy attends Monthly Partner Meeting
08/25/22 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
12/15/22 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
01/26/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
02/25/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
03/30/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
04/27/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
05/25/23 – Sam Hofmann attends Monthly Partner Meeting
06/29/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
07/27/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
08/31/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
09/28/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
10/25/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
12/07/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
12/07/23 – Evac plans for TPC 10th Floor returned . Champlin to correct 250 WHT plans.