Hamilton County Facilities

[General Services] – Champlin

General Services – Champlin

Champlin – General Services

02/14/19 – County invites Champlin for MSA agreement
02/21/19 – County sent MSA Contract to Champlin
03/13/19 – County sent revised MSA Contract to Champlin
03/18/19 – Champlin sent proposed revisions to MSA Contract
03/29/19 – County sent final MSA Contract
05/23/19 – General Services P.O. approved
05/30/19 – Kru and Mike from Champlin attended Monthly Partners Meeting
06/03/09 – Bert requests code interpretation for safe room locks on certain areas within the 911 Communications Center.
06/07/19 – Champlin provides 2017 OBS interpretation for safe room locks on certain areas within the 911 Communications Center
06/14/19 – Champlin provides further clarifications on 2017 OBS interpretation for safe room locks on certain areas within the 911 Communications Center
06/27/19 – Kru from Champlin attended Monthly Partners Meeting
07/31/19 – Christy from Champlin attended Monthly Partners Meeting.
08/29/19 – Kru from Champlin attended Monthly Partners Meeting and updated website.
09/26/19 – Kru from Champlin attended Monthly Partners Meeting and updated website.
10/30/19 – Champlin visited Auto Title and currently working on space layout.
12/12/20 – Mike and Sam from Champlin attended Monthly Partners Meeting and Updated website
01/02/20 – Bert reached out to Mike and Kru for CAB signage replacement
01/10/20 – Kru and Sam from Champlin visit Taft Center for potential Alley Door Upgrade
01/24/20 – Champlin reached out to multiple vendors for information on existing conditions
01/28/20 – Champlin received CAD files of CAB elevations from THP.
01/30/20 – Mike and Sam attended Monthly Partners Meeting and updated website.
01/30/20 – CAB signage project to be added to an existing facade repair job currently active at the CAB
02/04/20 – Signage drawings sent to THP to give to AFR
01/27/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
02/25/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
03/25/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
04/08/21 – Sent County options for casework refresh.
04/29/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
05/27/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
06/25/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
07/29/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
08/26/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
10/25/21 – Final Facilities kitchenette drawings sent to County for review.
10/28/21 – Sam Hofmann attend monthly partner meeting.
12/03/21 – SOSS approved for Design and consulting services.
12/14/21- Mike Murphy, Sam Hofmann attend Monthly Partner Meeting.
01/26/21 – Mike Murphy, Sam Hofmann attend Monthly Partner Meeting.
02/09/22 – Met with County, Triton, Thermaltech and Champlin to review scope of TPC 6th Floor ceiling replacement.
03/31/22 – Sam Hofmann attends Monthly Partner Meeting.
04/28/22 – Mike Murphy attends Monthly Partner Meeting.
05/26/22 – Mike Murphy and Sam Hofmann attends Monthly Partner Meeting.
06/30/22 – Sam Hofmann attends Monthly Partner Meeting.
07/28/22 – Mike Murphy attends Monthly Partner Meeting
08/25/22 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
12/15/22 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
01/26/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
02/25/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
03/30/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
04/27/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
05/25/23 – Sam Hofmann attends Monthly Partner Meeting
06/29/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
07/27/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
08/31/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
09/28/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
10/25/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
12/07/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
12/07/23 – Evac plans for TPC 10th Floor returned . Champlin to correct 250 WHT plans.

Champlin – General Services Read More »

Master Planning 2019

04/09/19 – Champlin receives request for Master Planning proposal
06/24/19 – Master Planning Kick-Off meeting held at Courthouse
07/02/19 – Champlin sends initial Master Planning Form to County Facilities
07/22/19 – Champlin sends revised Master Planning Form to County Facilities
08/05/19 – Master Planning Form and Master Planning Department Meetings reviewed at meeting held at Courthouse with County Facilities
08/20/19 – Champlin met with Moira Weir and Michael Patton, JFS
08/20/19 – Champlin met with Todd Lang, County Engineer
08/22/19 – Champlin met with Greg Brush, Clerk of Courts
08/23/19 – Champlin met with Dave Pittinger, Recorder
08/27/19 – Champlin met with Michael Lonneman, Treasurer
08/27/19 – Champlin met with Ray Faller, Public Defender
08/29/19 – Champlin met with Adult Probation
08/30/19 – Champlin met with Frank Spatero & Sarah Irwin, HR
09/03/19 – Champlin met with Trina Jackson, Re-Entry
09/03/19 – Champlin met with Paula Drake, Auditor
09/05/19 – Champlin met with James Noyes, Planning & Development
09/05/19 – Champlin met with John Hetzel & Dale Wittmer, Sheriff (800 Broadway & JFS)
09/06/19 – Champlin met with Carla Guenther & Steve Rokich, Juvenile Court
09/06/19 – Champlin met with Lisa Gorrasi & Bev Davis, Domestic Relations Court
09/12/19 – Juvenile Courts tour as follow up to 09/06 meeting
09/12/19 – Champlin met with Joann Cramer, Purchasing
09/13/19 – Champlin met with John Hoffman, Telecommunications
10/25/19 – Master Plan Draft Presentation and Review with Master Planning committee
11/12/19 – Champlin met with Bert Watts and Tony Matre to discuss Master Plan Draft.
11/26/19 – Champlin submitted Master Plan Document. Financial review section still under review.
12/08/19 – Champlin received comments on the 11/26 document from Bert Watts.
12/13/19 – Champlin submitted final version of Masterplan to County
02/20/20 – Champlin received final comments. Updated master plan accordingly
05/12/20 – Final draft submitted to Bert.

Master Planning 2019 Read More »