Hamilton County Facilities

A&D – JFS Internal Door Replacement

06/17/19 – County requests JFS Internal Door Replacement Project Scoping Meeting
07/02/19 – Meeting with Facilities (Tony Matre, Steve Sears, Cloude Toulson, Bert, Kru and Jeff)
07/11/19 – Champlin submits SOSS
09/11/19 – Champlin received approved SOSS and PO.
09/13/19 – Champlin performs site visit to verify all office door locations to be included.
10/28/19 – Champlin performs site visit with Hardware Consultant to confirm door hardware. Hardware consulting on going.
12/10/19 – Bid set sent to county
01/07/20 – Addendum #1 sent to County
01/16/20 – 5 bids were submitted to County.
01/22/20 – Champlin met with Megen Construction.
01/27/20 – Champlin sent official recommendation to award bid to Megen Construction.
03/26/20 – Waiting on official Contract to be given to Megen to return their door submittal
04/17/20 – Scope of work reduced to egress and security doors only.
05/04/20 – Megen given contract.
05/13/20 – Zoom meeting between Champlin and Megen to discuss scope changes.
05/28/20 – Waiting on revised estimate from Megen to proceed
06/24/20 – Waiting on revised estimate from Megen to proceed
06/29/20 – Megen provided revised estimate and other pre-construction information necessary.
07/21/20 – Pre-construction meeting attended by Champlin, Megen and County to further discuss the project. still waiting on project schedule and schedule of values from Megen.
07/28/20 – Door and Frame Submittal returned to Megen.
07/31/20 – Site visit scheduled to walk through areas of additional scope.
08/07/20 – Megen sent Safety materials.
08/18/20 – Schedule of Values and Project Schedule received from Megen construction. Megen has provided construction schedule showing NTP of August 3 and completion on December 7. On site work scheduled to start October 9. Mark-up of doors to be added sent to Claude/Steve for review and confirmation prior to creating a bulletin for contractor pricing. Waiting on direction to proceed.
08/24/20 – Change order for decrease in scope sent to Megen.
09/09/20 – Add services for Thermal Tech sent to Rycca.
09/21/20 – Megen workers complete background checks. Megen visits site to confirm existing conditions
10/09/20 – Scheduled start date.
10/29/20 – Construction started. OAC meetings scheduled for every Friday through end of construction projected by Megen to be December 7th.
12/10/20 – Working on new RFI for this project. Work on answer after tomorrow’s meeting.
01/15/21 – Restarted weekly construction progress meetings.
01/25/21 – Megen provided construction completion dates as follows: Basebid 2/23/21 bulletin 2 work. 03/02/21 Bulletin 1 work 3/22/21.
01/26/21 – Champlin returned comments requesting accurate pricing for 2 potential change orders.
02/08/21 – Progress Walk-thru attended by Sam Hofmann, Randy Johnson, John Nester, Steve Terheiden, and Rycca Thacker
02/19/21 – Bulletin #03 issued for replacement of existing closer/holders. RFI approved for supplier change from Interior Supply to LaForce.
03/19/21 – First Punchlist by Sam Hofmann, Mike Murphy, Rycca Thacker, Steve Terheiden, and Steve Kenneda.
03/26/21 – Second punchlist scheduled.
04/29/21 – Final punch scheduled for 4/30.
05/07/21 – Verified operation of closer/holders with fire alarm system. (attendees include, Rycca, Steve T, Mike B, Mike M, Sam)
05/10/21 – Champlin sent Rycca contractual dates and sequence of events as a word document.
05/12/21 – Final punch by Rycca, Steve T, Mike B, Mike M, and Sam.
05/14/21 – Punch list issued to Randy and Steve K.
05/18/21 – Rycca receives invoice from Phazor for replacement of fire alarm relays. Champlin send invoice to Megen. Randy acknowledges receipt and indicates he’ll forward it to accounting for payment.
05/25/21 – Contacted Megen regarding schedule of completion of punch list items.
06/24/21 – Megen notified us remaining materials received. intend to install on June 28th.
07/28/21 – Megen issued completion date of 7/28
08/26/21 – Waiting on Medeco Cores to be delivered.
11/08/21 – Final punchlist with County and Champlin. Still waiting on Medeco Cores from Megen.
11/17/21 – Finished second half of final punchlist
11/30/21 – Sent finalized report to Megen. Gave deadline of December 31. Requested filled out responsibility columns and schedule. Have not received either
01/21/22 – Final punchlist finally received from Megen.
01/25/22 – Backpunch by Sam and Rycca.
02/10/22 – Backpunch items completed. All construction services complete.
03/31/22 – Close out documents to be complete by friday.
04/28/22 – Close out documents received from Megen. Under final review.
05/26/22 – Close out documents to be reviewed.
06/30/22 – O&M manual reviewed and returned comments to Megen. Awaiting corrections
08/25/22 – Still waiting on Payroll information.

12/15/22 – All closeout documents and payroll information received. PROJECT COMPLETE

Scroll to Top