PM: Bert Watts, Mike Murphy, Paul Bellman, Terry Cannon
01/25/23 – SD and Cost complete. Created new category and started tracking EMA renovation. CD documents have been started. THP and TTE starting overhead door early project. BW sent information for design.
02/22/23 – User meetings complete. DD in progress from user meeting changes.
03/30/23 – Met with JFS last week. Need to get approval on design from users.
04/27/23 – Meeting on site with JFS scheduled for 5/5. Design development to proceed after that. Update old estimate with new cost for revised design. Cost is due in two weeks. Champlin to send revised plans. Include owner required items in the new cost including blue brick screen wall that is coming down, new sidewalk, plus other owner items.
05/11/23 – Champlin requested updated opinion of probable cost with updated scope of work.
05/17/23 – THP provided updated opinion of probable costs for structural scope of work.
05/17/23 – THP provided SOSS for DD through CA services based on new scope of structural work.
05/21/23 – ThermalTech DD cost updated in Archibus and shared with the team. Drawings are being updated this week.
05/25/23 – Drawings and estimate have been uploaded to Archibus. Landlord improvements have been marked with a (C).
06/12/23 – THP – Champlin returned executed Contract for DD-CA Services.
06/29/23 – No updates from THP.
06/29/23 – Final plans have been approved by users. follow up information to be provided to County this week. CDs in progress.
07/27/23 – 95% Review set submitted to County. Page turn with users to be scheduled.
08/09/23 – THP updated structural work and fees to the Archibus project estimate.
08/31/23 – Updated department breakdown plans and estimate. User page turn to be scheduled in near future.
09/27/23 – THP waiting to hear from Champlin about the page turn meeting with Hamilton County.
09/28/23 – Review meeting held with EMA. minor changes to plans made. JFS and 513 meetings to be scheduled.
10/25/23 – THP sending bid set to Champlin. Meetings held with all users. Final owner review sent to County for landlord approval.
11/22/23 – Building owner has approved the Phase 2 renovation plans. THP to send Bid Set to Champlin once bid date has been set.
12/06/23 – THP to send Bid Set to Champlin for 12/15/23 issuance.
12/07/23 – Received final approval from landlord and County. Bid issuance on 12/15.
01/04/24 – Project advertised to Bid.
01/18/24 – Pre-bid meeting on site.
01/25/24 – Addendum #1 issued.
01/29/24 – THP sent stamped permit set to Champlin.
02/07/24 – THP Addendum #2 issued. Unit prices and details for CMU tuckpointing and CMU replacement were included.
02/22/24 – THP – Bid Opening. 4 bids received (Alpha Construction, John P. Tumlin & Sons, Leo J. Brielmaier, and Triton Services). Champlin to evaluate bids.
03/28/24 – Contract phase ongoing.
04/19/24 – THP – Approved construction contract approved by the Board of County Commissioners and sent to project team.
04/23/24 – THP – County issued PO for the project to the team. Pre-construction meeting tentatively scheduled for 05/03/24 afternoon.
04/25/24 – Contracts finalized. Project kickoff tentatively scheduled for 5/3.
05/03/24 – Pre-construction meeting with full team at project site.
05/30/24 – Kickoff held. Submittals in progress.
06/27/24 – Pre-mobilization meeting scheduled for 7/12. RTU submittals have been rejected, TEI trying to get submittals on approved manufacturers.
07/12/24 – THP reviewed front entry slab drainage issue with Hamilton County.
07/12/24 – Pre-mobilization meeting with full team at project site.
07/25/24 – Construction to begin Monday.
08/28/24 – THP returned structural shop drawings to Champlin.
08/29/24 – Construction ongoing. More abatement to be completed next week. Demo almost complete.
09/26/24 – Construction ongoing. Main sewer line underslab is damaged beyond use. Tumlin to report on extent of damage. CO2 is being discussed and finalized. THP will return approved Masonry Lintel shop drawings to Champlin on 9/26. Water test is complete and Fire Protection calculation underway.
10/29/24 – THP responded to Champlin regarding Masonry repairs. Hamilton County to determine extent of repairs.
10/31/24 – Construction ongoing. Change order 2 and 3 approved for sanitary line work and fire protection changes.
12/06/24 – THP visited the site to coordinate supplemental steel with Thermal Tech and Tumlin to help with the response to RFI 23. THP issued a field report for review by Thermal Tech.
12/12/24 – Work ongoing. Forest Park has provided report stating that any combustible material will need to be removed. We believe the wood studs would be grandfathered in compliance. Champlin to investigate.
01/27/25 – Work progressing, Tumlin stated they would be complete at the end of February. ThermalTech (TTC) trying to schedule a coordination meeting between Emcor, Bison, and KW about final controls scope between project and state term work. Rooftop units not onsite yet but should be arriving soon. Plumbing rough-in mostly complete. Forest part has approved our fire protection permit and Preferred Fire should mobilize soon to the site for sprinkler work. According to Tumlin, we will not have to move all the trucks parked in the warehouse for the sprinkler work (all sprinklers in the Northeast Warehouse must be replaced with 11.2 sprinkler head).
02/26/25 – Work continues in space. GC, MC, EC, FPC are all on site performing work daily. PC coming back soon when the fixtures will be installed. TTE bringing Wi-Fi plan to Friday meeting. Several COR have come in this week, HC asked for the Fire Pit cost too, the permit needs to be amended for the additional inspection. We will get a scheduled update this Friday.
03/11/25 – HVAC Engineering Change drawing sent to Tumlin for their submission to FP for the return air openings on the first floor.
03/23/25 – TTE returned another set of controls submittals to Emcor for the ALC controls. Bison has not confirmed if we can get BACnet thermostats or now. ALC planning on interfacing through the SystemVu controllers in the RTU units.
03/25/25 – Plumbing Engineering change drawing set to Tumlin to give to Carrigan to give to FP for the natural gas adjudication letter received last week. ThermalTech continues to answer questions from the contractors working towards permit approvals.
03/27/25 – Pricing for Bulletin#3 received. Substantial completion date set at May 9th.
04/24/25 – RTUs delivered a month ahead of schedule and have been installed. Fire pit work ongoing. Railings will not be delivered and installed before May 9. Signage quote approved.
05/19/25 – THP visited the site to review supplemental steel.
05/29/25 – Punch list sent last week. Railing scheduled for delivery this week. Tumlin to schedule final inspection. Signage to begin install tomorrow.
06/24/25 – ThermalTech onsite this week working on HVAC issues. We are scheduled to come back for troubleshooting with MC and CC Friday at 7am. Emcor video was sent out from Ben.
06/25/25 – Final inspection complete. CO will be signed when Rafic returns. Ribbon cutting tomorrow.
07/31/25 – Ribbon cutting ceremony held. Several punch items still outstanding. Tumlin to begin closeouts. As-Builts not received yet. Emcor controls out this week for finalizing the new DDC controls..
08/28/25 – Tumlin confirmed all work is complete. Back puch to be scheduled. Closeouts outstanding.
09/25/25 – Backpunch complete. As-builts received. closeouts outstanding.
10/30/25 – Closeouts outstanding. Official CO received.
12/11/25 – No update.
01/28/26 – Closeouts in review.
02/26/26 – Waiting on closeout corrections.
03/26/26 – No update.
04/30/26 – No update.
05/28/26 – No update.
08/28/26 – Tumlin provided update on missing items.
09/24/26 – No Update.
10/29/26 – Closeouts received