Hamilton County Facilities

230 – Guard Rail – Safety Gate (F068)

PM: John Nester, Matt Rigdon
09/02/22 – Hamilton County requested SOSS.
09/29/22 – THP and Hamilton County walked the sites.
12/08/23 – THP provided SOSS for review.
12/20/23 – Hamilton County approved SOSS.
03/23/23 – THP anticipate to issue design development documents on 03/28/23.
04/25/23 – THP and Hamilton County meeting to discuss work. Hamilton County to perform work in-house. THP to provide material list for Hamilton County’s review.
05/24/23 – THP to send review set of revision drawings that account for existing ductwork interferences. THP to also send review of material lists of products. Work is still anticipated to be performed in-house.
07/17/23 Requested to combine the two safety gate projects for WHT & TPC Buildings into one drawing set. Requested by HamCo to separate Railing at WHT as individual project.
07/26/23 – Documents being finalized and to send July 31.
10/19/23 – THP published review documents for combine 230 WHT rail and TPC stair project.
10/26/23 – THP finalizing documents from County comments.
10/25/23 – THP published gate ordering drawings for Facility department.
11/01/23 – THP published bid documents to ZSR Contracting and Restoration, American Façade Restoration, John P. Tumlin, and Journey Steel.
11/06/23 – Prebid meeting occurred.
11/09/23 – Addendum No. 1 published.
11/17/23 – Bids received from ZSR Contracting and Restoration and American Façade Restoration.
11/21/23 – THP published a bid summary letter for review by the County.
01/31/24 – No updates from THP.
2/23/24 – County sent AIA contracts to ZSR for review and execution.