Hamilton County Facilities

525 – Warehouse Doors and Ramp (F072)

PM: Rycca Thacker, Paul Bellman
12/07/22 – THP submitted SOSS to Hamilton County.
01/08/23 – THP spoke with City and have verbal confirmation a new curb cut is allowed.
01/10/23 – THP proposed initial layout to Hamilton County.
01/19/23 – THP and Thermal Tech met Hamilton County and EMA personnel onsite to review site layout and get field measurements.
02/10/23 – THP sent owner review documents to Hamilton County.
02/21/23 – Owner has approved the warehouse improvements. Hamilton County getting funding put in place.
02/24/23 – THP and Kleingers meeting with Hamilton County and EMA personnel to measure vehicles for final ramp layout and design.
03/16/23 – THP sent bid documents to Hamilton County Purchasing Department.
03/20/23 – Bid Documents released by Hamilton County Purchasing Department.
03/29/23 – Prebid meeting completed.
03/30/23 – Project opening scheduled for 4/13/23.
04/13/23 – Bid opening occurred with John P. Tumlin & Sons being the apparent low bidder and under budget.
04/21/23 – THP published a bid summary letter, recommending the County proceed with Tumlin.
05/21/23 – Permit drawings created and sent last week.
04/21/2023 – THP published a bid summary letter, recommending the County proceed with John P. Tumlin & Sons.
05/15/23 – HC sent contract to John P. Tumlin & Sons and requested their insurance certificates.
05/31/23 – HC waiting on Board of Commissioners for contract approval.
05/31/23 – John P. Tumlin & Sons working on schedule of values, schedule, site specific safety plan, material submittals, background checks, etc.
06/29/23 – THP receiving submittals from John P. Tumlin & Sons.
07/12/23 – HC notified THP that the construction contract will be presented to the Commissioners at their public meeting on 07/27/23.
07/27/23 – TTE returned the PTAC submittals again (second time) for changes.
07/28/23 – HC sent approved contract, PO, and Notice to Proceed to THP and Tumlin.
08/22/23 – Pre-Construction meeting set for Wednesday, August 30.
08/30/23 – Pre-construction meeting with THP, Hamilton County, Tumlin, ThermalTech Engineering, and Kleingers.
09/27/23 – Tumlin submitted construction schedule. Tentative date for mobilization set for October 2.
10/02/23 – Tumlin mobilized to site to begin construction.
10/25/23 – Interior overhead doors installed, masonry repaired at office, PTAC installed in office, interior slab on grade has been removed and replaced, interior man door has been installed, steel framing and masonry work at exterior door openings has started. Gas line has been relocated and additional gas line repairs have been approved via change order.
11/27/23 – Steel framing and masonry work for exterior openings has been completed. Both exterior overhead doors have been installed. Electric work and painting continuing inside. All mechanical/gas line repairs associated with this project have been completed. Exterior ramp (grading, forming, rebar/mesh, etc.) has been started. Concrete ramp pour scheduled for the week of 11/27/23.
12/06/23 – Electric work continuing inside. First two concrete ramp pours completed on 11/30/23 and 12/06/23.
01/02/24 – Last concrete pour for ramp completed.
01/24/24 – THP, ThermalTech, Hamilton County, and Forest Park met onsite to walk through and discuss required life safety items to get temporary certificate of occupancy for Phase 1. Team to address issues.
01/26/24 – Punchlist Walk Through with Bert Watts. Sent list to Tumlin.
01/30/24 – Additional Overhead Doors in back of warehouse started to get installed.
02/26/24 – THP, ThermalTech, and Champlin met onsite to review the vehicle layout. Champlin and ThermalTech to update Life Safety drawings and Electrical drawings, respectively, for in place vehicle layout with egress, emergency and exit lighting, etc to address issues that were discussed with Forest Park Building Department and Fire Department.
04/18/24 – THP received updated electrical drawings with emergency/exit lighting from ThermalTech. Request for change order pricing and updated drawings sent to Tumlin for installation.
04/24/24 – THP waiting to receive change order pricing from Tumlin. Installation of emergency/exit lighting required to close out phase 1 and building permit.
05/10/24 – Change Order for Emergency/Exit Lighting approved.
05/14/24 – Fully executed Change Order sent to all parties.
05/21/24 – Emergency/Exit Lighting submittal received. Waiting on review from ThermalTech to send approval. Installation to follow after submittal approval.
06/26/24 – ThermalTech reviewed Lighting submittal – Approved as Noted.
08/29/24 – Safety electrical items being installed.
09/26/24 – Pay Application #7 received for review.
10/11/24 – THP returned Pay Application #7 to Hamilton County.
10/31/24 – Closeout Process needs to be initiated.
12/11/24 – Closeout Process needs to be initiated.
01/23/25 – Closeout Process initiated with Tumlin.
02/26/25 – Closeout Process in progress by Tumlin.
03/26/25 – THP to follow-up with Tumlin on Closeout.
04/08/25 – THP sent Tumlin email on Closeout documents.
04/22/25 – Tumlin responded to email and indicated another request was sent out to subcontractors for closeout documents.
05/16/25 – Fire Alarm testing caused a short in the new fire alarm control panel. A fire watch was required for this weekend and was provided by a third party firm. TTE helped HamCo on first session until fire watch company arrived.
05/20/25 – Cin-Day installed the new FACP and replaced one address module, tested the existing system and found it to be working with no Trouble. We still need to work out warranty requirements.
05/19/25 – THP received close-out documents from Tumlin.
05/28/25 – THP started review of close-out documents.
06/25/25 – THP to return comments on close-out documents to Tumlin.
07/30/25 – THP reviewed close-out documents and sent Tumlin final comments/documents.
08/27/25 – Tumlin is sending final closeout documents to Hamilton County.
02/20/26 – Preconstruction Meeting held for Generator Plug-In Relocation.
02/23/26 – THP issued Preconstruction Meeting Minutes.
03/11/26 – On-site meeting held to review logistics of panel relocation.
03/24/26 – THP verified panel had been removed from the existing Blue Ash location. Status of permit drawings, IBI Inspection, closeout?
04/28/26 – Tumlin is working on final PW info for HC for Closeout Documents.
05/27/26 – County said do not archive until we get all closeout documents.
06/25/26 – Tumlin submitted requested Closeout Documents.
07/30/26 – Need IBI Inspection report for Closeout Documentation for Plug-in Electrical relocation. Davies to submit.
08/20/26 – THP sent project Meeting Minutes to HC.
08/27/26 – Rycca believes they have paid out this project.