Hamilton County Facilities

JC – Arc Flash Mitigation 2023

PM: Matt Butz, Mike Barth
01/25/23 – TEI Submits SOSS.   Project pending SOSS approval and PO.
02/23/23 – TEI receives signed SOSS and PO.  Project Kick off to be scheduled with HCFD.
03/29/23 = TEI and HCFD to schedule project kick off.
04/27/23 – TEI performs preliminary review of existing model.   TEI and HCFD to meet to discus next steps.
05/23/23 – TEI and HCFD to set up meeting to discuss next steps.  Proposed time of 9:00 AM on  6/2/23.
06/28/23 – June 2 meeting did not occur.  TEI requested availably from building manager.
7/26/23 – TEI, Matt Butz and building manager meet to discuss building electrical issues.  biggest issue is with breakers for floor machines tripping regularly.  TEI looking for ways to mitigate this issue.
08/24/23 – TEI determines that there are 2 options for moving forward.   The existing gear has built in transformers in the panels.  The cost to replace the is approximately 2 times the cost of sperate equipment.   The transformers are at the end of the  manufacturers standard life expectancy.  The transformers are not problematic at this time.   An option would be to install sub panels and pick up the added circuits from them and address the transformers as they become an issue.
09/26/23 – TEI developed drawings with the sub-panel option.  Review drawings to be  sent to HCFD by 09/29.
10/26/23 – TEI issues project for bids.  Prebid meeting for project occurred on 10/25/23.  Bids scheduled to open on 11/22.
12/06/23 – Bids received and Stem Electric is apparent low bidder.  TEI vets the bid and sends recommendation letter.   Contracts at prosecutors office for approval.
01/30/24 – Project waiting BOCC approval.
02/28/24 – Stem Electric receives signed contract and PO.  Preconstruction kick off to be scheduled in next 2 weeks and TEI awaiting submittals.
03/27/24 – Pre construction meeting scheduled for 04/15/24
04/24/24 – Preconstruction meeting occurred.  Project pending material procurement.
05/29/24 – Stem electric has mobilized to project site and construction has commenced.  working on floor to floor core drills and initial installation .
06/26/24 – Stem mobilized on site and work in progress. Vertical raceways installed through buildings. Wiring to begin with anticipated completion of installation end of July.
07/24/24 – Stem anticipates completion of base bid work by 08/02/2024. HCFD asked for CO pricing to add electric for equipment per the request of the HCSO.
08/28/24 – Stem complete with work pending closeout documents. TEI to print out new Arc Flash Labels and label the building.
09/25/24 – Waiting on Closeouts from Stem.
10/30/24 – Project completion pending closeouts from STEM. TEI provides new AF labels in both towers.
12/11/24 – TEI delivers (3) copies of Arc Flash report to HCFD with tables and single lines in the report.
02/26/25 – Project complete pending closeout.
03/26/25 – Project complete pending circuit breaker that was ordered with allowance $$. Can not close until breaker is delivered.
04/23/25 – Project waiting on breaker delivery.
05/28/25 – Project back punchlist walk scheduled for 5/30.
06/25/25 – Project backpunch completed. Stem completes items and sends pics to TEI and HCFD of completed items. Pending Closeout documents.
07/30/25 – Closeout documents submitted and provided to HCFD. (3) hard copies and (3) Thumb drives.
08/28/25 – Ready to Archive.