PM: Matt Butz, Mike Barth
05/27/21 – Project created.
06/23/21 – Project kick off meeting attended by TEI, HCFD, DK and HCSO. DK has began moving the doors over to the Vax system. Project construction continues.
07/28/21 – DK states that the project is substantially complete. TEI and HCFD provide punchlist site visit. TEI issues punchlist. DK addressing punchlist items.
08/26/21 – Punchlist items are picked up. TEI receives O&M manuals for review. No punchlist or warranty in O&Ms. Upon receipt, TEI will forward to HCFD.
10/26/21 – O&M Manuals delivered to HCFD. Project is complete.