05/21/21 – Hamilton County requested SOSS for the roof replacement of two roofs with alternates.
06/03/21 – THP provided SOSS for roof replacement project.
06/15/21 – County approved SOSS.
08/02/21 – THP visited site to survey and document existing conditions.
08/16/21 – THP issued Opinion of Probable Costs to Hamilton County for project budget approval.
08/20/21 – THP issued progress drawings and project manual for Owner Review.
08/25/21 – THP visited site to review condition of exposed decking in office and verify conditions at Entry canopy.
09/01/21 – THP received and reviewed AIA contract documents for project manual.
09/02/21 – THP met Hamilton County at site to review drawings and confirm scope of work items and Alternates.
09/03/21 – THP finalized and issued documents for bid.
09/09/21 – THP received and replied to substitution request email from roofing supplier and updated specifications.
09/14/21 – THP led pre-bid meeting at Animal Shelter.
09/15/21 – THP developed pre-bid meeting notes and issued Addendum 01.
10/05/21 – Bid opening. Received bids from Ace Exteriors, Wm. Kramer & Son, and Imbus Roofing.
10/06/21 – THP had conversations with Ace Exteriors to qualify bid, discuss pricing for canopy replacement, and request references and manufacturer’s certifications.
10/08/21 – THP finalized letter to Hamilton County summarizing bid process and recommending award to Ace Exteriors, including Base Bid and Alternate 1 scopes of work.
10/08/21 – THP responded to email from Hamilton County summarizing reasons bids received for canopy exceeded original estimates.
10/18/21 – THP received and began review of roofing products received from contractor as substitutions due to material availability.
10/20/21 – THP had conversation with Contractor and emailed Hamilton County about status of registering Ace Exteriors as a vendor.
10/21/21 – THP received from Contractor and forwarded to Hamilton County completed Substitutions form missing from bid proposal.
10/28/21 – THP issued revised title sheet with wind load information for Office/Admin. and Cat House roofs and requested Contractor review with manufacturer the potential implications on warranty and adhesive requirements.
11/05/21 – THP had conversation with Hamilton County to discuss material substitutions proposed by Ace Exterior due to material availability and schedule issues.
11/05/21 – THP had conversations with Wm. Kramer & Son about material availability and confirmed they would not be able to provide the specified roof insulation and cover board by spring 2022.
11/05/21 – THP emailed Hamilton County recommendations to proceed with the project using the substitute materials proposed by Ace Exteriors.
11/10/21 – Hamilton County emailed contract to Ace Exteriors.
11/23/21 – Ace Exteriors emailed Hamilton County the signed contract, worker compensation certificate, and a project-specific certificate of liability insurance.
12/23/21 – Hamilton County emailed the signed contract and PO to Ace Exteriors and requested development of required preconstruction documents.
01/28/22 – THP emailed Contractor about status of materials order, development of required pre-construction documents, completion date, and additional details to be developed.
02/01/22 – THP emailed Contractor draft of revised roof plan and details showing contract scope and new details at interface between project scope and canopies to remain.
02/04/22 – THP finalized and issued revised documents for Permit and Construction.
02/10/22 – THP reviewed and returned product submittals for roofing materials.
03/08/22 – THP received and reviewed Contractor’s pricing and lead time information for aluminum v. galvanized edge metals.
03/10/22 – THP had conversation with County about approval of proposed metal substitution due to increased costs and lead time issues, and re-reviewed submittals for roof specialties.
04/05/22 – Preconstruction meeting.
04/12/22 – THP issued minutes from preconstruction meeting.
04/12/22 – THP reviewed submittals and requested revised insulation layout.
04/13/22 – THP had conversation with Contractor about discrepancy in slope of tapered insulation between documents and submitted revised insulation layout, and retuned submittal with exceptions noted.
04/13/22 – THP had conversation with Contractor about installation issues and additional cost of taller fascia that would be required with 1/4″ slope tapered insulation v. 1/8″ slope indicated in documents. Contractor to request updated/revised tapered layout to reflect the 1/8″ slope.
04/19/22 – THP received, reviewed, and returned re-revised insulation layout submittal.
04/22/22 – THP had conversations with Contractor and Hamilton County to discuss delayed start date due to weather and insulation slope issue, and emailed team about rescheduling first progress meeting.
05/02/22 – THP met project team at site for progress meeting and site visit to document progress.
05/02/22 – THP emailed Contractor a link to a shared folder containing original construction drawings.
05/02/22 – THP developed and issued minutes from progress meeting #1.
05/03/22 – THP issued field report 01 from 5/2 site visit.
05/03/22 – THP reviewed pencil copy of Contractor’s first application for payment and replied with comments.
05/03/22 – THP reviewed and approved notarized copy of Contractor’s first application for payment and forwarded to Hamilton County.
05/12/22 – THP met Contractor on site to review and document progress.
05/15/22 – THP issued field report 02 from 5/12 site visit.
05/16/22 – THP met project team at site for progress meeting and site visit to document progress.
05/20/22 – THP developed and issued minutes from progress meeting #2.
05/20/22 – THP issued field report 03 from 5/16 site visit.
05/24/22 – THP visited site to review and documented completed installation of EPDM.
05/26/22 – THP issued field report 04 from 5/24 site visit.
06/01/22 – THP reviewed Ace fascia and coping profiles submittals.
06/29/22 – Progress meeting and site visit scheduled to review installed drains and progress of edge metal installation.
07/22/022 – THP visited site to do final inspection of completed work and identify punchlist items.
07/25/22 – THP published field report and punch list for roof work from 7/22/22 visit.
08/09/22 – THP emailed Contactor about status of completing punchlist items.
08/09/22 – THP developed Change Order #1 for unused Cash Allowance and Unit Price credit and forwarded to Contractor for signature.
09/21/22 – Contractor emailed team about status of completing punchlist.
09/26/22 – THP emailed Contractor about acceptance of remaining two punchlist items, status of second application for payment, closeout documents, and approval of Change Order #1.
10/28/22 – THP visited site to confirm completion of punchlist items, and emailed Contractor about the status of closeout documents, approval of Change Order #1, and the application for payment #2 for substantial completion.
11/09/22 – THP replied to email from Contractor rejecting request for additional use of Cash Allowance.
11/18/22 – Contractor provided preliminary closeout documents for THP’s review.
11/21/22 – Change Order #1, a credit for unused Unit Price Repairs and Cash Allowance, was signed by Contractor and Hamilton County.
12/01/22 – THP reviewed Contractor’s preliminary closeout documents and replied with revisions to be made and additional documents to be provided.
12/07/22 – Contractor provided revised closeout documents for THP’s review.
12/12/22 – THP reviewed revised closeout documents and emailed Contractor to proceed with providing hard copies, including notarized legal documents and the project binder.
01/03/23 – THP reviewed Contractor’s hard copies of closeout documents and project binder and requested revised as-built drawings using permit set as basis for markups.
01/04/23 – THP received revised as-built drawings, emailed Hamilton County a link to a shared folder containing digital copies of all closeout documents, approved Contractor’s second and final application for payment, and delivered project binder.
02/23/23 – OK to Archive.