06/25/21 – ThermalTech has been working on project over the last few weeks. New equipment was added to the worksheet, TTC to review final list.
07/29/21 – Susan contacted me about completion and I suggested that we could get these done by August 13. She reviewed our test work in DEV and had some questions. Ryan and Nathan will help me complete this work.
08/12/21 – Discussed progress with Susan and committed to a 8/31 completion for 9/1 PM’s. TE has updated Coroner’s Equipment list to check one more time before completion. We are verifying no duplicates exist.
08/25/21 – TTC sent in final list for equipment creation with 3 or 4 questions. Talked to Susan, Steve and Bert about process to finish. I received codes and values back from Facilities to use on our equipment creation list.
10/01/21 – Final equipment list sent to County for upload to Archibus.
10/08/21 – Needed to add asset column for equipment list and warranty item needs to be added.
10/19/21 – Revised worksheet and equipment list sent back to County. I still have to create warranty information for equipment when we enter the PM’s.
12/01/21 – Crime Lab PM’s entered minus a couple of extraneous electrical PM that TTC is checking the needs on.
12/13/21 – Electrical PM not needed for exit signs, security gate, or power conditioner. Steve checked in on warranty items and TTC reported that TTE can enter these manually, I just need a review on how to enter the warranty items. We are meeting this week on how to do this work.
01/22/22 – All equipment and warranties are entered and up to date.
05/25/22 – Ready to Archive.