PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
06/12/23 – Hamilton County approved SOSS.
08/31/23 – THP plans to complete work from October through November.
09/28/23 – Rappelling of façade scheduled for October 10th.
10/10/23 – Rappelling survey of Tower completed.
10/17/23 – East wing loose debris survey started.
10/19/23 – East wing loose debris survey completed.
10/26/23 – THP working on summary report updated.
02/29/24 – Report complete. THP finalizing project budget.
03/28/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update.
06/26/24 – Monitoring updated report submitted.
06/27/24 – Budget submitted to County.
08/29/24 – THP scheduling façade knock down survey and inspection for 2024.
09/26/24 – THP to review knock down approach with larger repair package.
10/31/24 – Ready to archive.
12/10/24 – THP closing out the project.