Hamilton County Facilities

800 – Façade Repair SD (F022)

PM: John Nester, John Millar
01/02/2 – Champlin reached out to THP to provide SD services for the new Animal Shelter.
02/25/25 – THP provided an SOSS for SD Services.
03/26/25 – Elevar pending approved PO. Truescan started scanning the building from the interior.
04/23/25 – Design team had internal kick off meeting. Project update – Scanning complete and THP working on base Revit model for the project.
05/28/25 – Elevar has site walk scheduled for 05/30 to review windows. THP completed initial surveys and plans to rappel 5/29 and 5/30.
06/26/25 – Elevar investigating window replacement vs restoration and window cleaning products.
07/31/25 – Window drawings are progressing and a set will be provided to THP for inclusion in the next checkset to HCFD.
06/30/25 – THP completed aerial platform surveys of the lower section of the building and interior surveys of the façade 6/30 to 7/3.
07/17/25 – Stone stabilization proposals received and AFR is the low bidder.
07/22/25 – THP sent 800 Broadway review set to County. Set included windows and fall protection.
07/30/25 – AFR installing supplemental anchors on north elevations. Anticipate being complete by 7/31/25.
07/30/25 – AFR completed installation of supplemental anchors and THP confirmed the work.
08/27/25 – THP published share file with SD review drawings. Drawing included stone, window, and safety package.
08/28/25 – Summary documents and initial estimate planned for week of September 2.
08/28/25 – Window SD set provided to THP 08/15.
09/25/25 – Elevar provided ROM estimate to THP.
10/30/25 – Review mtg with HCFD scheduled for 11/06.
10/23/25 – THP issued opinion of probable cost for all work.
10/30/25 – County review meeting scheduled for November 6th.
12/11/25 – Review mtg held with HCFD. Revised estimates and design schedule to be provided.
12/01/25 – Schematic Design meeting occurred. Scope, budget and next steps presented.
12/23/25 – HC requested an SOSS – DD through Bidding.
01/19/26 – THP published SD report for County project planning.
01/29/26 – THP/Elevar working on SOSS.
01/31/26 – THP and County working through project scope and design team services.
02/25/26 – THP published SOSS for review.
04/09/26 – HC approved SOSS.
04/30/26 – THP working through initial design phase planning.
05/27/26 – Design Kick off meeting completed.
06/08/26 – Project summary for security meeting published.
06/17/26 – Project placed on hold.
07/29/26 – THP published summary of conditions for use by the County.
09/24/26 – Project on hold.
10/25/26 – Project on hold

Scroll to Top