12/14/22 – Hamilton County published a project list for 2022. Project to be complete by Fall of 2022.
03/08/22 – THP completed an initial site visit for scope of work.
03/25/22 – THP submitted a SOSS for review by the County.
04/13/22 – SOSS approved.
06/30/22 – THP working on staff background check. Plan to start mid June.
07/27/22 – THP visited site and needs to get a fire rating from the floor which would require a concrete solution. Looking at potential solutions now.
08/19/22 – THP issued review drawings for County review.
08/25/22 – THP working on option pricing for proposed design and removal of the fill.
09/21/22 – THP issued review Bid Set to John Nester for comments.
09/24/22 – THP issued Bid Set drawings and project manual to the county. Scheduled Pre-bid conference for 10/5/22, last day for questions 10/11/22, last day for answers 10/13/22, and a bid opening date for 10/19/22.
10/19/22 – Bid opening for the project. Four bids received all below or within the project published budget. SSRG the apparent low bidder.
10/26/22 – THP conducted bid review phone call with SSRG.
01/03/23 – SSRG sent Workers Comp. Insurance & CGL Insurance to HC
01/06/23 – HC Signed contract and PO
01/09/23 – HC Approved contract and PO and sent it to SSRG
01/13/23 – THP sent sealed conformance documents to HC and SSRG
01/17/23 – SSRG sent preliminary SOV and Schedule
01/18/23 – HC and THP sent comments back for revisions to SOV and Schedule due to long lead times for railings and the background checks.
01/24/23 – SSRG begun background check process
01/24/23 – SSRG sent submittals for steel rebar, steel railing, and anchorage.
02/27/23 – SSRG asked about the removal of existing piping that is in the way of the slab formwork.
03/01/23 – THP visited the site and, along with verification from the county, noted that the pipe was an abandoned fuel line and that it is acceptable to move/remove pipe as necessary for form work. SSRG will do so with no additional cost.
03/01/23 – SSRG noted they need to use permanent forms instead of digging pea gravel trenches for formwork. THP noted this as acceptable.
03/02/23 – Terracon was contracted to be the special inspector for this project for steel reinforcement and concrete.
03/06/23 – Progress meeting attended by SSRG, THP, and Hamilton County was held. It was requested by the county to draft a pump plan for the concrete pour day to notify parking inhabitants before the pour date. This was supplied that same day.
03/06/23 – Fuel tanks were noted to be buried under the pea gravel. This was deemed to not affect our design since the slab is designed to be structural.
03/06/23 – Concrete mix design was sent to Terracon for reference
03/06/23 – THP supplied SSRG with design loads for permit.
03/07/23 – Special inspections were scheduled
03/09/23 – Stamped special inspection form was sent to SSRG for permit.
03/13/23 – Progress meeting 1 meeting notes were distributed to the team.
03/13/23 – Progress meeting attended by SSRG, THP, and Hamilton County was held. Steel inspection and concrete pour scheduled for 03/13 and 03/14 respectively.
03/13/23 – Steel inspection was performed by Terracon, and steel reinforcement was reviewed by THP for consistency with design drawings. No comments were noted.
03/14/23 – Concrete pour was performed. THP on site from 7:45 AM until about 12:00 PM. Concrete pumping, finishing, and the site cleanup was observed by THP as required.
03/16/23 – Terracon sent reinforcing steel observations report.
03/17/23 – THP sent an elevation for SSRG & steel fabricator use for guardrail modifications.
03/17/23 – SSRG sent pricing for stairway move and rebuilding, and excess pea gravel removal.
03/17/23 – Progress meeting 2 meeting notes were distributed to the team.
03/17/23 – Field Report 02 for concrete pour was distributed to the team.
03/21/23 – SSRG sent Pay App #2 for approval.
04/21/23 – Bulletin No. 1 issued for review by the County.
04/25/23 – Bulletin No. 1 issued for pricing.
05/25/23 – Project summary. SSRG provided pricing for Bulletin No. 1 and Hamilton County declined the modifications. SSRG scheduling the final railing install. April pay application placed on hold, because work is for railing and closeout.
05/30/2023 – SSRG sent May Pay App for review
06/01/2023 – SSRG installed the guardrail per original drawings after Bulletin 01 option was rejected by County.
06/08/23 – THP sent the approved May Pay App to the County
06/12/23 – THP sent email to SSRG outlining the documents required for project closeout.
06/15/23 – THP performed a final punch visit, accompanied by John Nester.
06/15/23 – THP sent the final punch report to SSRG.
07/07/23 – SSRG completed punch list items on site.
07/12/23 – THP reviewed, approved, and sent previously-held April Pay App to County.
07/24/23 – THP reviewed SSRG’s completed punch list work and sent out a field report indicating these items were complete.
07/24/23 – THP compiled and sent As-Built drawings to SSRG for closeout documents. Waiting for SSRG to send closeout docs.
07/26/23 – THP published as-built drawings and completed punch list field report.
08/15/23 – THP contacted SSRG regarding an update to the progress of their closeout documents.
08/18/23 – THP received closeout binder electronic documents from SSRG. Documents included are: General 1 year warranty, As-built drawings (provided by THP), and THP’s Field Report 001. SSRG indicated they are still awaiting their front ends team to compile and send forms G706, G706a, G707, and the affidavits. THP reviewing.
09/26/23 – THP delivered approved project binders to the County.
09/26/23 – THP forwarded approved final pay application to the County.