JC – Germicidal Unit Upgrade

PM: John Nester, Terry Cannon
04/27/22 – SOSS received and approved. TEI to schedule project kickoff.
05/25/22 – Field trip for design kickoff on June 2, 10:30am.
06/02/22 – Design Mtg #1 complete. TEI to research options for whole system UV versus wall mount units.
06/30/22 – Schematic design ideas sent to several manufacturers and pricing has started coming back. We are compiling the study results now. I like the whole unit option.
07/27/22 – Review drawings are ready. We will submit HVAC drawings next week.
08/24/22 – UV design in existing ductwork at AC-D5 being drafted now. TTC did additional fieldwork earlier this month. Bid in September.
09/25/22 – JN has provided contracts, TTC is putting together bid documents. Project should bid end of Sept/early Oct timeframe.
10/26/22 – Out for Bid. Prebid complete, Addendum 1 ready for issuance. Bid Opening on Nov 4.
12/15/22 – Bid was opened, Debra was the apparent low bidder. Pre-award meeting went well and DK was recommended for the job. Contracts and insurance are getting finalized prior to starting work.
01/24/23 – Contracts and PO are in place. We are ready to have the preconst meeting. The first submittal is ready to be reviewed.
02/21/23 – Checked in with DK and they told me they need their submittal back for this job so we reviewed and sent that back this week.
03/10/23 – Equipment ordered and confirmed with the right voltage. Shipping date to be confirmed.
03/30/23 – Permit drawings have been sent to Debra for permitting.
04/25/23 – No update on permit approval yet on city website. TTC checking with DK.
04/26/23 – Parts on in town and at DK office. Permit will be applied for this week. DK ready to start working. Time to have a Pre Const meeting.
05/21/23 – Debra permitting the project now and waiting for badged employee to be available to work on this project.
06/28/23 – TTE sent back permitting responses. Ball is in DK court to get city permit then IBI permit. Dave is trying to get Installation Manual from vendor to submit to the city.
07/26/23 – Permitting not in place yet. Need to check on DK progress. “No detailed information available for the approval of Contractor Registration (This approval is reviewed upon the completion of all other required approvals)”
08/29/23 – Checked with DK a week ago and they had no update. The permit not approved, still in contractor registration phase.
09/27/23 – Talked to Dave at length about this project and its a resource issue for DK. He has not resolved the permit issue yet which he admits they need to get done. DK is currently trying to fix the JC boiler flue before winter and as soon as they are done with that, they will start the this project. DK will get a guy on the Permit this week. I believe they also need EC help for this job and I think that is one of the holdups to get started. All the equipment is in and approved.
10/25/23 – John contact DK this month and demanded a start to this project. Dave Gleason to get people started on this job and coordinate with Andy on access.
12/06/23 – Permit it approved. County reached out earlier this week and asked for an update on progress. TTE reached out to DK several times but also no updates from them at this time. I am thinking we ask Dave for a new project manager for this job so we get someone with more time to help.
01/31/24 – Multiple check ins with Dave Gleason and even Andy, not sure if electricians have started demo, but that is what was supposed to have happened.
02/23/24 – Met DK last week on lighting installation locations. DK has lights installed, need to have electric installed next and start demo.
03/22/24 – Mechanical work is done, need update from DK on electrical demo of existing UV and power for new UV lights.
04/24/24 – DK Electrical has visited the site to start to sort out the electrical scope. John told them to coordinate with the HCSO and Andy for schedule and to be onsite. DK report the new UV lights are powered up, TTE cannot confirm that yet.
05/28/24 – Met with DK today and discussed schedule and first demo of existing units. Sheriff will move inmates around one pod at a time while the units are demolished.
06/26/24 – We had a const meeting earlier this month, one cell will be used first to see how demo goes and Sheriff will move detainees to another cell while DK removes and patches one cell. AJ reported today that he believes the last unit was demolished yesterday and DK should be wrapping up demo very soon.
07/24/24 – Work is complete according to AJ, TTE waiting to punchlist this job.
08/28/24 – Punchlist to be performed 8/29 at 2pm.
09/24/24 – DK onsite patching up existing units, masonry, paint, and patch work on the punchlist. I talked to them today and they will be back down this week and next to wrap this job up.
10/30/24 – TTE checking on final punchlist progress.
12/12/24 – Dave Gleason says that we will have all the closeout paperwork by this Friday.
01/28/25 – Closeout paperwork received. We are working on the closeout process.
02/26/25 – We have received about half of the closeout documents for this project. See new Closeout page.
03/25/25 – Final closeout pages received, we are proceeding to full closeout.
04/23/25 – Project ready to archive.