PM: Matt Butz, John Millar/Matt Rigdon
12/14/22 – Hamilton County published a project list for 2022. Project to be complete by Fall of 2022.
02/25/22 – THP and County met to discuss scope.
04/04/22 – THP submitted a SOSS for review by the County.
04/25/22 – County approved SOSS.
06/10/22 – THP issued design development documents.
06/21/22 – THP received contractor opinion of probable cost. Within project budget.
06/22/22 – County published AIA forms for final bid documents.
06/30/22 – THP documents ready for bid. THP coordinating bid dates. Anticipates bidding in July.
07/11/22 – THP issued “For Bidding” submittal with drawings and project manual.
07/19/22 – THP hosted pre-bid meeting at HC Comm Center Visitor Lot
07/21/22 – THP issued Addendum #1.
08/03/22 – Bid opening scheduled.
08/03/22 – No bids received at opening. THP contacted over 12 contractors during the bid period. Contractors noted extremely busy for 2022.
08/25/22 – Project documents updated and work rescheduled for spring of 2023. New bidding period advertise 8/26/30, prebid 9/6/22 and bids due 9/13/22.
08/26/22 – THP issued “For Bidding” submittal with new schedule for 2023.
09/06/22 – THP hosted pre-bid meeting at HC Comm Center Visitor Lot.
09/14/22 – Bids are due.
09/14/22 – Bids from Rack7, Prus and JK Meurer were received. All base bid within budget. Rack7 was the apparent low bidder.
09/21/22 – THP and Rack7 completed an initial bid review meeting. Rack7 did not include unit cost work in the base bid and has withdrawn from the bid.
09/28/22 – THP and Prus will complete an initial bid review meeting.
09/29/22 – THP and Prus completed an initial bid review meeting. Prus did not include unit cost work in the base bid and has withdrawn from the bid
10/05/22 – THP and JK Muerer completed an initial bid review meeting.
10/11/22 – THP issued a Bid Summary Letter recommending JK Meurer for the contract.
11/21/22 – J.K. Meurer was approved contract and corresponding PO. Kick-Off meeting sometime after the first of the year. Anticipate work after Winter/start of Spring.
01/04/23 – HC sent CO 001.
01/05/23 – THP signed and returned CO 001.
01/06/23 – J.K. Meurer signed and returned CO 001.
01/10/23 – J.K. Meurer to update THP/HC on background checks, expected submittal process date, and intended work completion date. THP proposed date for Pre-construction for March 15, 2023.
01/26/23 – J.K. Meurer to update THP/HC on background checks, expected submittal process date, and intended work completion date. THP proposed date for Pre-construction for March 15, 2023.
02/23/23 – Background checks to begin this month. Anticipating Preconstruction Meeting for March 15, 2023.
03/15/23 – Preconstruction Meeting
03/23/23 – Anticipating work schedule is May 1st-22nd. The following still needs to be submitted by J.K. Meurer: SOV, emergency contacts, and official schedule. No submittals have been submitted; Anticipating Mix Design Submittal.
04/25/23 – No updates for April. Work to start on May 1st (weather pending). Anticipating on-site visit with J.K. Meurer and Hamilton County on May 2nd (weather pending).
05/01/23 – J.K. Meurer provided mix design submittals. Asphalt resurfacing work began at Visitor Lot.
05/02/23 – THP site visit performed. Revisions were made to full depth repair quantities. Approx. 50% less area than original after observation of base course. Revisions by HamCo were made to ADA space to allow for access aisle to be at west side rather than east side of parking space.
05/05/23 – J.K. Meurer completed work at Visitor Lot and THP performed site visit. Work appeared to conform to drawings and revisions.
05/08/23 – J.K. Meurer began work at Secured Lot.
05/09/23 – THP site visit performed. Revisions were made to full depth repair quantities. Approx. 50% less area than original after observation of base course. Revisions by HamCo were made to the berm at the loading dock ramp.
05/15/23 – J.K. Meurer completed work at Secured Lot and THP performed site visit. Work appeared to conform to drawings and revisions.
07/26/23 – Bulletin being prepared and to be sent for review July 31.
08/09/23 – THP met with Ian to review drive repair needs.
09/26/23 – County request gate repair as part of drive work. Motor details sent to THP.
09/28/23 – THP forward JK Meurer quote for drive and gates.
10/06/23 – County approved quote for drive and gate. THP notified JK Meurer to proceed.
10/11/23 – JK Meurer proposed full slab replacement. THP provided slab requirements for the new ramp. JK Meurer provided updated proposal.
10/17/23 – Project budgetary numbers sent to County for review. JK Meurer proposal using cash allowance funds. Work is below total project budget.
10/17/23 – County sent draft Change Order No. 2 for authorization of new drive and gate motor.
10/25/23 – County published executed Change Order No. 2.
10/26/23 – JK Meurer schedule to begin drive work the middle of November.
11/03/23 – Drive repair work rescheduled to accommodate interior renovation project.
12/04/23 – Demolition of the ramp started.
12/06/23 – Lower section of ramp subgrade and steel prepared. Bottom half of ramp poured and concrete tested. THP inspected steel and Terracon tested concrete.
12/07/23 – Upper section of ramp schedule for completion.
01/15/23 – Concrete replacement at ramp was completed mid-December. Email received from contractor that installation of new gate operator is expected to be installed at the end of January.
01/30/23 – Gate contractor notified THP that the operator is now expected for production on 01-31-24. Production is backed up for LiftMaster and the ship date keeps changing. Installation is TBD in February.
0002/28/24 – Gate contractor is to notify THP and County once the vendor is contacted. Delivery has been delayed for approximately two months.
03/13/24 – Gate operator was delivered and installed on site. Overhead Door did not put the operator in service due to the condition of the gate.
03/18/24 – THP, HamCo Facility Manager, and Overhead Door met on site to review condition of inoperable gate.
03/27/24 – THP received quote from Mills Fence Co to replace existing gate. HamCo has approved. CO to be made up next week.
04/25/24 – JK Meurer planning on complete repair to top of drive on 4/26/24.
05/1/24 – JK Meurer and subcontractor has revised their project close out documents and sent to County. Project is closed. No more updates.
05/18/24 – JK Meurer to revise their pay app 2.
05/23/24 – Mills Fence Co checked gate to ensure it is working. JK Meurer and THP to start the project close out process.
09/26/24 – Awaiting final Change Order deduct from Hamilton County and Mills Fence lien waiver for close out documents.
12/11/24 – THP to review close out documents following updated close out procedures.
01/29/25 – Closing out – last phase. All documents are in and reviewed by THP. (3) As-built Hard Copies, (1) copy of final pay app & AIA docs, (3) copies in notebooks of O&M, and (1) USB flash drive. Will hand in at Thursday’s meeting.
02/24/25 – Final pay application approved.
02/25/25 – Final pay application prevailing wage documentation sent to County.